Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: TD-DEV-1023-00433
Permit Details
Apply Date:
10/23/2023
Applicant:
Greg Vega
Description:
Rev 1 submitted 07.30.2025 - update to bike parking** Converting existing 1 story building into Medical Office Building including overlay and reconfiguration of existing parking. lot
Permit Reviews
Permit Number - TD-DEV-1023-00433
Permit Status: Complete
Permit Description: Rev 1 submitted 07.30.2025 - update to bike parking** Converting existing 1 story building into Medical Office Building including overlay and reconfiguration of existing parking. lot
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 10/27/2023 | DEVELOPMENT PACKAGE NEW v.1 | 11/02/2023 | REQUIRES RESUBMIT |
| 12/21/2023 | DEVELOPMENT PACKAGE NEW v.3 | 01/24/2024 | APPROVED |
| 07/30/2025 | DEVELOPMENT PACKAGE NEW REVISION v.1 | 08/26/2025 | APPROVED |
| 11/06/2023 | DEVELOPMENT PACKAGE NEW v.2 | 12/14/2023 | REQUIRES RESUBMIT |
Outstanding Inspections
Permit Status: Complete
Permit Number: TD-DEV-1023-00433
Permite Description: Rev 1 submitted 07.30.2025 - update to bike parking** Converting existing 1 story building into Medical Office Building including overlay and reconfiguration of existing parking. lot
Total Outstanding Inspections - 3
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/30/2024 | For trash and recycling enclosures | N/A | Partial Pass | Contractor, good to pour the retaining wall in the front footer |
| 10/14/2024 | NPPO Pre-Construction | N/A | Partial Pass | Contractors good to pour the footer for the trash enclosure |
| 11/26/2024 | COT - ENGR - Stormwater | N/A | Partial Pass | Contractors good to pour concrete on the 12 inch storm drain east side of the building |
Completed Inspections
Permit Status: Complete
Permit Number: TD-DEV-1023-00433
Permit Description: Rev 1 submitted 07.30.2025 - update to bike parking** Converting existing 1 story building into Medical Office Building including overlay and reconfiguration of existing parking. lot
Total Completed Inspections - 9
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/10/2024 | PDSD Engineering Division Pre-Construction SITE | Passed | I inspected the trash enclosure for the contractor while I was here for the pre-con. The footing is missing two number four in the front they need to be put in before they pour the concrete footer. | |
| 06/26/2025 | For trash and recycling enclosures | Passed | ||
| 06/26/2025 | NPPO Pre-Construction | Passed | ||
| 09/10/2025 | ENGR Engineering Final | Passed | ||
| 10/16/2025 | COT - ENGR - Stormwater | Passed | ||
| 10/20/2025 | COT - ENGR - Signage Final | Passed | ||
| 10/20/2025 | Final inspection to ensure all landscape and water harvesting SITE | Passed | 10/20/25 Areas that allow for 3" to 9" maximum depression more than 10' from building and more than 1' from curbs are depressed. Where slopes and existing structures are located this is not possible and no grading was done in this scope of this project. The areas in plan are depressed and comply within reason considering these conditions. |
|
| 10/20/2025 | PDSD Site/Engineering Division - Landscaping | Passed | 10/20/25 Plants are staked correctly plants are to plan and thriving. Appearance and materials correct. Dedicated Meter and Backflow valve in place for landscaping. |
|
| 10/20/2025 | SITE - Stormwater Final Inspection | Passed | 10/20/25 All erosion control bmp’s are removed slopes are stabilized. No SWPPP on this project. |