Permit: TD-DEV-0824-00236
Permit Details
Apply Date:
08/16/2024
Applicant:
Adam Call
Description:
Revision 2 - Tentative Plat/Development Package for Cielo Reserve Lots 1-52 & Common Area "A", Flexible Lot Development
Permit Reviews
Permit Number - TD-DEV-0824-00236
Permit Status: Issued
Permit Description: Revision 2 - Tentative Plat/Development Package for Cielo Reserve Lots 1-52 & Common Area "A", Flexible Lot Development
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 09/24/2025 | DEVELOPMENT PACKAGE NEW REVISION v.2 | 10/20/2025 | APPROVED |
| 10/31/2024 | DEVELOPMENT PACKAGE NEW v.2 | 12/18/2024 | REQUIRES RESUBMIT |
| 03/27/2025 | DEVELOPMENT PACKAGE NEW REVISION v.2 | 03/28/2025 | APPROVED |
| 12/18/2024 | DEVELOPMENT PACKAGE NEW v.3 | 12/20/2024 | APPROVED |
| 08/04/2025 | DEVELOPMENT PACKAGE NEW REVISION v.1 | 09/10/2025 | REQUIRES RESUBMIT |
| 08/17/2024 | DEVELOPMENT PACKAGE NEW v.1 | 09/23/2024 | REQUIRES RESUBMIT |
| 04/09/2025 | DEVELOPMENT PACKAGE NEW REVISION v.1 | 04/30/2025 | APPROVED |
| 02/07/2025 | DEVELOPMENT PACKAGE NEW REVISION v.1 | 03/19/2025 | REQUIRES RESUBMIT |
Outstanding Inspections
Permit Status: Issued
Permit Number: TD-DEV-0824-00236
Permite Description: Revision 2 - Tentative Plat/Development Package for Cielo Reserve Lots 1-52 & Common Area "A", Flexible Lot Development
Total Outstanding Inspections - 8
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/06/2025 | NPPO Pre-Construction | N/A | Partial Pass | Nursery is good. Barrel cacti need ID tags. TOS saguaro needs blue tape. Extra saguaro identified on site, landscape architect needs to indicate. |
| 03/18/2025 | SITE - Stormwater Setup and Controls | N/A | Complete (Recurring) | Before the contractor starts, he needs to burm up a small area over by the house on the south east quadrant of this property |
| 09/26/2025 | SITE - SWPPP Correction Notice | N/A | Failed | Significant mud tracked out onto Ganley Rd after yesterday's storm. Needs to be cleaned up within 24 hours. Street sweeper showed up while I was on-site. Construction vehicles should not be going from dirt directly onto public streets, track out measures are needed. |
| 03/24/2026 | ENGR Engineering Final | N/A | Not Ready | |
| 03/24/2026 | LAND Landscape Appearance & Function Final | N/A | Not Ready | |
| 03/24/2026 | N/A | Not Ready | ||
| 03/24/2026 | N/A | Not Ready | ||
| 12/24/2025 | SITE - Stormwater Follow-up | N/A | Failed | BMP’s required for disturbed areas and at inlets. |
Completed Inspections
Permit Status: Issued
Permit Number: TD-DEV-0824-00236
Permit Description: Revision 2 - Tentative Plat/Development Package for Cielo Reserve Lots 1-52 & Common Area "A", Flexible Lot Development
Total Completed Inspections - 8
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/06/2025 | PDSD Engineering Division Pre-Construction SITE | Passed | Initial Pre-Con held in CoT office. Discussed sequence of events, and need for NPPO pre-con to verify tagged trees. will complete pre-con when site signage is erected. SWPPP Board, Address, Etc. | |
| 03/18/2025 | NPPO Pre-Construction | Passed | plants are properly accounted for, nursery is in good shape. | |
| 06/24/2025 | Passed | Rough grading is complete, wet utilities are (almost) complete, dry utilities are beginning. Benchmarks, hubs, and staking are in place. Basins have been rough cut. | ||
| 01/28/2026 | NPPO Final | Passed | NPPO plants have been properly preserved or transplanted on site in accordance with approved plans. | |
| 02/02/2026 | ENGR Grading Final | Passed | All grading associated with the development package is complete. Stormwater basins are installed to proper elevations. Landscape areas are correct and ready for cover. Sidewalk, curb, roads: locations and elevations are accurate to approved plans. | |
| 05/05/2026 | Passed | Common area sidewalks are complete in accordance with approved plans. ADA and slope requirements have been met. | ||
| 05/05/2026 | Passed | All common area pedestrian circulation is in compliance with ADA. All common area pedestrian circulation is complete. No striping on site. | ||
| 05/05/2026 | COT - ENGR - Signage Final | Passed | Signage final was passed on 1/28/26. |
Scheduled Inspections
Scheduled Inspections - TD-DEV-0824-00236
Status: Issued
Description: Revision 2 - Tentative Plat/Development Package for Cielo Reserve Lots 1-52 & Common Area "A", Flexible Lot Development
| Scheduled Date | Description | Entered By | Entered Date |
|---|---|---|---|
| SITE - Stormwater Follow-up | Scheduled |
For information about today’s scheduled inspections please refer to the
PDSD Daily Inspections Dashboards (Desktop)
PDSD Daily Inspections Dashboards (Mobile)
.