Permit: TD-DEV-0523-00248
Permit Details
Status:
Inspections Complete
Type:
Development Package
Address:
1145 S WARREN AV
Address NEW:
1145 S WARREN AV
Apply Date:
05/18/2023
Applicant:
JR Durazo
Description:
Development of new commercial soccer facility with parking and landscaping.
Permit Reviews
Permit Number - TD-DEV-0523-00248
Permit Status: Inspections complete
Permit Description: Development of new commercial soccer facility with parking and landscaping.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 05/19/2023 | DEVELOPMENT PACKAGE NEW v.1 | 08/11/2023 | REQUIRES RESUBMIT |
| 04/16/2024 | DEVELOPMENT PACKAGE NEW v.4 | 05/03/2024 | APPROVED |
| 02/28/2024 | DEVELOPMENT PACKAGE NEW v.3 | 04/02/2024 | REQUIRES RESUBMIT |
| 11/08/2023 | DEVELOPMENT PACKAGE NEW v.2 | 12/11/2023 | REQUIRES RESUBMIT |
Outstanding Activity Conditions
Permit Number - TD-DEV-0523-00248
Permit Status: Inspections complete
Permit Description: Development of new commercial soccer facility with parking and landscaping.
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 09/17/2025 | Prior to final - needs review for requests for information, AS-Built will need to be submitted |
Outstanding Inspections
Permit Status: Inspections Complete
Permit Number: TD-DEV-0523-00248
Permite Description: Development of new commercial soccer facility with parking and landscaping.
Total Outstanding Inspections - 11
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/25/2024 | PDSD Site/Engineering Division - NPPO | N/A | Not Ready | Not ready for inspection, trees should have been moved by now into,their temporary area. |
| 10/28/2024 | SITE - Stormwater Setup and Controls | N/A | Not Ready | Site closed. no activity |
| 10/28/2024 | N/A | Not Ready | Site closed. no activity | |
| 11/13/2024 | ENGR - Drainage Structures | N/A | Canceled | 1st row of pipe to the east, trench passed 11/13/24. |
| 11/13/2024 | Consultation SITE | N/A | Canceled | |
| 04/08/2025 | N/A | Canceled | ||
| 04/08/2025 | For trash and recycling enclosures | N/A | Partial Pass | Okay to pour bollard |
| 11/15/2024 | N/A | Canceled | ||
| 07/25/2025 | N/A | Partial Pass | Pipe is correct, valves are functional, wiring is in place, emitters are good. Okay to backfill. | |
| 07/25/2025 | N/A | Partial Pass | Forms including curb ramp leading to ADA parking are set correctly, compaction is 99.5%. Good to pour. | |
| 10/09/2024 | ENGR Grading Final | N/A | Not Ready | Contractor continues to cut the grade not ready for final |
Completed Inspections
Permit Status: Inspections Complete
Permit Number: TD-DEV-0523-00248
Permit Description: Development of new commercial soccer facility with parking and landscaping.
Total Completed Inspections - 8
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/15/2024 | PDSD Engineering Division Pre-Construction SITE | Passed | ||
| 11/06/2024 | SITE - Stormwater Follow-up | Passed | ||
| 11/06/2024 | Passed | |||
| 03/21/2025 | Consultation SITE | Passed | Consultation was on the bollards and mat for the refuse enclosure. Engineer on record is going to have to certify that the footing was done per spec. | |
| 08/15/2025 | Grading Progress ENGR | Passed | Grading is completed, schedule your grading final and a paving inspection for Monday | |
| 08/29/2025 | ENGR Paving | Passed | Compaction was at 98 to 99% and material has passed a proof roll. | |
| 08/29/2025 | ENGR Grading Final | Passed | ||
| 09/12/2025 | ENGR Engineering Final | Passed |