Inspection Status: Re-inspection required
Inspection History: For trash and recycling enclosures
| Date |
Description |
Inspector |
Results |
Comments |
| 02/27/2025 |
For trash and recycling enclosures |
|
Re-inspection required |
Footing was not seen by Tucson so that will require an engineer letter stating it was done to spec. |
| 03/24/2025 |
For trash and recycling enclosures |
|
Partial Pass |
Bollards are passed by photo, 03/24/25 |
| 04/02/2025 |
For trash and recycling enclosures |
|
Not Ready |
Not ready, no rebar in place, do not pour until reinspected. |
| 04/08/2025 |
For trash and recycling enclosures |
|
Partial Pass |
Okay to pour bollard |
| 04/21/2025 |
For trash and recycling enclosures |
|
Partial Pass |
|
| 04/28/2025 |
For trash and recycling enclosures |
|
Partial Pass |
04/28/25, wall grout has passed. |
| 05/12/2025 |
For trash and recycling enclosures |
|
Partial Pass |
05/12/25, slab inspection passed. |