Permit: TD-DEV-0424-00131
Permit Details
Apply Date:
04/18/2024
Applicant:
Brandy Burke
Description:
New Development Package (Site) for FAA AutoCenter
Permit Reviews
Permit Number - TD-DEV-0424-00131
Permit Status: Complete
Permit Description: New Development Package (Site) for FAA AutoCenter
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 04/18/2024 | DEVELOPMENT PACKAGE NEW v.1 | 06/25/2024 | REQUIRES RESUBMIT |
| 09/12/2024 | DEVELOPMENT PACKAGE NEW v.3 | 09/17/2024 | APPROVED |
| 08/07/2024 | DEVELOPMENT PACKAGE NEW v.2 | 09/12/2024 | REQUIRES RESUBMIT |
Outstanding Inspections
Permit Status: Complete
Permit Number: TD-DEV-0424-00131
Permite Description: New Development Package (Site) for FAA AutoCenter
Total Outstanding Inspections - 6
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/08/2025 | Verify required native plant protection, relocation, removal is completed prior to activity on job site | N/A | Not Applicable | there is no NPPO on is project |
| 01/08/2025 | PDSD Site/Engineering Division - NPPO | N/A | Not Applicable | There is no NPPO on this project |
| 12/11/2024 | NPPO Pre-Construction | N/A | Re-inspection required | Informed the contractor to call in every two weeks for swept inspections and for any thing else that he needs out here. Right now he needs to install the wattles and the track out rock. |
| 05/14/2025 | ENGR - Drainage Structures | N/A | Partial Pass | Contractor has been gone for two weeks because the metal building wasn’t delivered on time. Contractor installed the riprap on site. |
| 07/08/2025 | PDSD Site/Engineering Division - Landscaping | N/A | Not Ready | Contractor has not started the landscaping yet |
| 07/18/2025 | Consultation SITE | N/A | Complete (Recurring) | Development Package Inspection list has been cleaned up to reflect the scope of work remaining. Landscape areas around plantings should be depressed per details on page 8. COT-ENGR-Signage Final inspection for ADA parking signs. COT-ENGR-Drainage structures for curb cuts that catch water flow from pavement. SITE-Consultation for general questions and concerns. |
Completed Inspections
Permit Status: Complete
Permit Number: TD-DEV-0424-00131
Permit Description: New Development Package (Site) for FAA AutoCenter
Total Completed Inspections - 6
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/11/2024 | PDSD Engineering Division Pre-Construction SITE | Passed | Informed the contractor to call in every two weeks for swept inspections and for any thing else that he needs out here. Right now he needs to install the wattles and the track out rock. | |
| 02/06/2025 | NPPO Pre-Construction | Passed | I passed a freak on once before. I checked the wattles. Everything is in good. | |
| 03/20/2025 | SITE | Passed | There’s no water harvesting on this project | |
| 07/24/2025 | Passed | |||
| 08/14/2025 | LAND Landscape Appearance & Function Final | Passed | ||
| 08/21/2025 | ENGR Engineering Final | Passed |