Permit: TD-DEV-0325-00077
Permit Details
Status:
Inspections
Type:
Development Package
Address:
10080 E OLD VAIL RD
Address NEW:
10080 E OLD VAIL RD
Apply Date:
03/10/2025
Applicant:
Anthony Boone
Description:
Dental Office, 4,292 SF
Permit Reviews
Permit Number - TD-DEV-0325-00077
Permit Status: Inspections
Permit Description: Dental Office, 4,292 SF
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 07/01/2025 | DEVELOPMENT PACKAGE NEW v.3 | 07/24/2025 | APPROVED |
| 03/13/2025 | DEVELOPMENT PACKAGE NEW v.1 | 04/28/2025 | REQUIRES RESUBMIT |
| 05/08/2025 | DEVELOPMENT PACKAGE NEW v.2 | 06/27/2025 | REQUIRES RESUBMIT |
Outstanding Inspections
Permit Status: Inspections
Permit Number: TD-DEV-0325-00077
Permite Description: Dental Office, 4,292 SF
Total Outstanding Inspections - 3
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/25/2025 | Consultation SITE | N/A | Partial Pass | Discussed storm drain and utilities on site with Contractor and Gustavo. Leaving this inspection as partial pass so that it can be recalled during construction when questions arise. |
| 10/15/2025 | ENGR - Drainage Structures | N/A | Partial Pass | October 15/25 Contractor will send good pictures showing correct rebar and spacing 2 inches from forms and 3 inches from dirt no reinforcing in the dirt. Forms needs to be 6 inch in thickness with spacers evenly spaced. Form set to survey nails correct elevations and offsets correct. Drain pipe sloped correctly, joint to main correct and bedding good. Okay to pour floor and walls pending good pictures. Strip forms inside and out and request reinspection before backfilling. |
| 12/02/2025 | For trash and recycling enclosures | N/A | Partial Pass | Light pole footing on south edge needs cleaned out better before pouring. Trash enclosure needs side bollards and vertical reinforcement spaced appropriately for CMU before pouring footing/slab. |
Completed Inspections
Permit Status: Inspections
Permit Number: TD-DEV-0325-00077
Permit Description: Dental Office, 4,292 SF
Total Completed Inspections - 2
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/11/2025 | PDSD Engineering Division Pre-Construction SITE | Passed | Development Package and SWPPP will need to be on site and available at all times. Storm Water Initial inspection needs to be completed before Inspections can be requested. Make sure NOI is in place. You can then call in Storm water initial Inspection in the portal. Get BMP’s in SWPPP plan in place on site then you can start work. Inspections list: Grading Paving Setback/Sign Footer/Excavation Flatwork Striping Site Consultation |
|
| 09/16/2025 | SITE - Stormwater Setup and Controls | Passed | Stormwater initial meeting held on-site. Control measures are in place as necessary. Site will be monitored for necessary changes. |