Permit: TD-DEV-0226-00048
Permit Details
Apply Date:
02/24/2026
Applicant:
JR Durazo
Description:
CIP-1025-00026-Updates to an existing bike park to include new trails, trail features, and signage. Project is running on an accelerated schedule to reactivate the site.
Permit Reviews
Permit Number - TD-DEV-0226-00048
Permit Status: Inspections
Permit Description: CIP-1025-00026-Updates to an existing bike park to include new trails, trail features, and signage. Project is running on an accelerated schedule to reactivate the site.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 02/24/2026 | DEVELOPMENT PACKAGE NEW v.1 | 03/03/2026 | REQUIRES RESUBMIT |
| 03/03/2026 | DEVELOPMENT PACKAGE NEW v.2 | 03/03/2026 | APPROVED |
Outstanding Activity Conditions
Permit Number - TD-DEV-0226-00048
Permit Status: Inspections
Permit Description: CIP-1025-00026-Updates to an existing bike park to include new trails, trail features, and signage. Project is running on an accelerated schedule to reactivate the site.
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 02/24/2026 | Prior to Final documents, fees and contractor Dust Control/Air Quality Permit is Required. (Utilized with DP's & TP's) |
Outstanding Inspections
Permit Status: Inspections
Permit Number: TD-DEV-0226-00048
Permite Description: CIP-1025-00026-Updates to an existing bike park to include new trails, trail features, and signage. Project is running on an accelerated schedule to reactivate the site.
Total Outstanding Inspections - 1
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/04/2026 | ENGR Engineering Final | N/A | Partial Pass | Site is mostly complete. Still need some cleanup work, install a kiosk and signs, and confirm all ground anchors. SWPPP controls are no longer needed, ADEQ permit may be closed. Recall Engineering Final once final punch list items are complete and park is safe for public access. |
Completed Inspections
Permit Status: Inspections
Permit Number: TD-DEV-0226-00048
Permit Description: CIP-1025-00026-Updates to an existing bike park to include new trails, trail features, and signage. Project is running on an accelerated schedule to reactivate the site.
Total Completed Inspections - 3
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/13/2026 | PDSD Engineering Division Pre-Construction SITE | Passed | 3/13/26 Inspections needed will just be Storm Water initial and Engineering Final SWPPP Board will be in place for Storm Water initial. SWPPP book will also be on site for inspections BMP's are on site and are being installed next week. Request Storm Water initial when BMP's are in place and SWPPP book is ready. |
|
| 03/25/2026 | SITE - Stormwater Setup and Controls | Passed | 3/25/26 SWWWP BMP's are in and are to plan. Inlets are protected. East phase 9 Area's 1 and 2 will be protected with BMP's later when work starts in those Areas. Wattle will be adjusted as discussed with contractors. Construction Entrance on Alvernonon in place. Sign board in place and swift book in place and will be accessible. NOI issued. Responsible party on SWWWP sign board with contact information. OK to start work |
|
| 06/04/2026 | SITE - Zoning Final | Passed | Sitework is complete within zoning requires set by approved plans. |