Permit: TD-DEV-0125-00003
Permit Details
Status:
Complete
Type:
Development Package
Address:
1680 E TUCSON MARKETPLACE BL
Address NEW:
1680 E TUCSON MARKETPLACE BL
Apply Date:
01/07/2025
Applicant:
Aaron Jewell
Description:
LivAway Suites Hotel
Permit Reviews
Permit Number - TD-DEV-0125-00003
Permit Status: Complete
Permit Description: LivAway Suites Hotel
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 04/08/2025 | DEVELOPMENT PACKAGE NEW v.4 | 05/02/2025 | REQUIRES RESUBMIT |
| 07/29/2026 | AS-BUILT v.1 | 07/31/2026 | APPROVED |
| 01/24/2025 | DEVELOPMENT PACKAGE NEW v.2 | 01/31/2025 | REQUIRES RESUBMIT |
| 01/08/2025 | DEVELOPMENT PACKAGE NEW v.1 | 01/17/2025 | REQUIRES RESUBMIT |
| 05/28/2025 | DEVELOPMENT PACKAGE NEW v.6 | 06/03/2025 | APPROVED |
| 05/08/2025 | DEVELOPMENT PACKAGE NEW v.5 | 05/27/2025 | REQUIRES RESUBMIT |
| 02/04/2025 | DEVELOPMENT PACKAGE NEW v.3 | 04/02/2025 | REQUIRES RESUBMIT |
Conditions
Permit Number - TD-DEV-0125-00003
Permit Status: Complete
Permit Description: LivAway Suites Hotel
| Date | Description | Comments |
|---|---|---|
| 07/08/2026 | Prior to final - needs review for requests for information, AS-Built will need to be submitted |
Outstanding Inspections
Permit Status: Complete
Permit Number: TD-DEV-0125-00003
Permite Description: LivAway Suites Hotel
Total Outstanding Inspections - 2
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/19/2025 | ENGR - Drainage Structures | N/A | Partial Pass | Discussed eliminating existing inlet catch basin. Requested additional information from engineer regarding and up or downstream connections. will require this prior to elimination, and will need as-built drawings at end of construction documenting this. |
| 07/23/2026 | ENGR Engineering Final | N/A | Partial Pass | -EV Chargers are not in place at Handicap parking. -Unsatisfied condition- Letter of conformance from engineer of record needs to be satisfied prior to final. -Replace missing cap Fire Hydrant at SW corner of building. |
Completed Inspections
Permit Status: Complete
Permit Number: TD-DEV-0125-00003
Permit Description: LivAway Suites Hotel
Total Completed Inspections - 12
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/18/2025 | PDSD Engineering Division Pre-Construction SITE | Passed | SWPPP board will be seen at the storm water initial. | |
| 07/07/2025 | SITE - Stormwater Setup and Controls | Passed | Very important is to get the SWPPP plan on site rather then trying to find the information in their book. This is needed by the first by-weekly that will be done. | |
| 06/12/2026 | Passed | Sidewalks and concrete flatwork is complete in accordance with approved plans and within ADA requirements. | ||
| 06/17/2026 | Passed | Okay to begin backfilling | ||
| 07/09/2026 | For trash and recycling enclosures | Passed | ||
| 07/09/2026 | Passed | There is a vertical LED strip on the East and West facades of the building that are not shown on the building plans or the outdoor lighting sheets of the DP. This will be considered by Outdoor Lighting Special Inspection for the Building permit. Submit the Report to Satisfy this condition prior to the Building Engineering Final inspection. | ||
| 07/09/2026 | ENGR Grading Final | Passed | ||
| 07/09/2026 | Passed | |||
| 07/09/2026 | Consultation SITE | Passed | ||
| 07/23/2026 | LAND Landscape Appearance & Function Final | Passed | ||
| 07/23/2026 | Passed | |||
| 07/28/2026 | ENGR Engineering Final | Passed |
Scheduled Inspections
Scheduled Inspections - TD-DEV-0125-00003
Status: Complete
Description: LivAway Suites Hotel
| Scheduled Date | Description | Entered By | Entered Date |
|---|---|---|---|
| 11/23/2025 | SITE - Stormwater Follow-up | Scheduled |