Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Inspection Status: Partial Pass

Inspection History: ENGR Engineering Final

Date Description Inspector Results Comments
06/15/2026 ENGR Engineering Final Partial Pass 6/15/26 - .
Remaining items to finish include: Landscaping and ground cover, correct NE basin outlet elevation, finish SW basin outlet structure/pipe, install EV infrastructure, install handrail at north stairwell exit, ensure grade slopes away from building on East side.
07/23/2026 ENGR Engineering Final Partial Pass -EV Chargers are not in place at Handicap parking.
-Unsatisfied condition- Letter of conformance from engineer of record needs to be satisfied prior to final.
-Replace missing cap Fire Hydrant at SW corner of building.
07/28/2026 ENGR Engineering Final Passed