Inspection History Details
Inspection Status: Partial Pass
Inspection History: ENGR Engineering Final
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/15/2026 | ENGR Engineering Final | Partial Pass | 6/15/26 - . Remaining items to finish include: Landscaping and ground cover, correct NE basin outlet elevation, finish SW basin outlet structure/pipe, install EV infrastructure, install handrail at north stairwell exit, ensure grade slopes away from building on East side. |
|
| 07/23/2026 | ENGR Engineering Final | Partial Pass | -EV Chargers are not in place at Handicap parking. -Unsatisfied condition- Letter of conformance from engineer of record needs to be satisfied prior to final. -Replace missing cap Fire Hydrant at SW corner of building. |
|
| 07/28/2026 | ENGR Engineering Final | Passed |