Permit: TC-RES-1025-05155
Permit Details
Status:
Complete
Type:
Residential Building - One or Two Family
Address:
902 W CALLE MARGARITA
Address NEW:
902 W CALLE MARGARITA
Apply Date:
10/23/2025
Applicant:
enrique rivera
Description:
new addition on rear of house
Permit Reviews
Permit Number - TC-RES-1025-05155
Permit Status: Complete
Permit Description: new addition on rear of house
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 11/20/2025 | ADMINISTRATIVE v.1 | 11/24/2025 | REQUIRES RESUBMIT |
| 10/28/2025 | RESIDENTIAL ADD/ALT v.1 | 11/20/2025 | APPROVED |
| 11/25/2025 | ADMINISTRATIVE v.2 | 11/25/2025 | APPROVED |
Conditions
Permit Number - TC-RES-1025-05155
Permit Status: Complete
Permit Description: new addition on rear of house
| Date | Description | Comments |
|---|---|---|
| 10/28/2025 | Contractor with active Arizona Contractor's License for specified scope of work, or a signed Owner Builder Affidavit is required prior to issuance of permit. The Affidavit form is available at https://www.tucsonaz.gov/Departments/Planning-Development-Services/Permits/Residential-Permits. Contractor or Owner must have a TDC Online account and be added to the permit as the correct contact type https://www.tucsonaz.gov/files/sharedassets/public/v/2/pdsd/documents/tdc-faq/new-pdfs/adding-additional-contacts.pdf. If you are providing an Owner Builder Affidavit, the owner MUST be attached as a contact on the permit. |
Outstanding Inspections
Permit Status: Complete
Permit Number: TC-RES-1025-05155
Permite Description: new addition on rear of house
Total Outstanding Inspections - 3
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/11/2025 | COT - RSBU - Excavation/Rebar/Zoning | N/A | Re-inspection required | 12-11-25: missing 10 mil vapor barrier-see Detail 1 of foundation plan. |
| 12/29/2025 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | N/A | Partial Pass | 12-29-25: partial pass-pending 1/2" anchor bolts at several locations. Anchor bolts must be installed in the middle third of the plate; within 12" of the end of each plate & spaced no further than 6' apart. Missing 3/8" x 5" lag bolts at each connection-see ledger detail for more. This items will be checked at intermediates-okay to dry-in roof and continue with construction without covering the mentioned listed items. |
| 01/07/2026 | COT - RSEL - Electrical Final | N/A | Not Ready | 01/07/2026 Not ready. |
Completed Inspections
Permit Status: Complete
Permit Number: TC-RES-1025-05155
Permit Description: new addition on rear of house
Total Completed Inspections - 8
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/11/2025 | COT - RSBU - Excavation/Rebar/Zoning | Passed | 12-11-25: reinforcement/setbacks verified per plans-okay to pour concrete. | |
| 12/29/2025 | COT - RSBU - Roof Nailing | Passed | 12-29-25: okay to dry-in roof. | |
| 01/07/2026 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | Passed | 01/07/2026 Corrections made to 12/29/25 inspection. |
|
| 01/07/2026 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | 01/07/2026 Corrections made to 12/29/25 inspection. |
|
| 02/06/2026 | COT - RSME - Mechanical Final | Passed | ||
| 02/06/2026 | RSBU - Building Final | Passed | ||
| 02/06/2026 | COT - RSBU - Masonry Pregrout | Passed | ||
| 02/06/2026 | COT - RSEL - Electrical Final | Passed |