Permit: TC-RES-0525-02365
Permit Details
Status:
Inspections Complete
Type:
Residential Building - One or Two Family
Address:
578 W TIGER SHARK RD
Address NEW:
578 W TIGER SHARK RD
Apply Date:
05/05/2025
Applicant:
Albert Calderon
Description:
Laundry Room Addition
Permit Reviews
Permit Number - TC-RES-0525-02365
Permit Status: Inspections complete
Permit Description: Laundry Room Addition
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 07/17/2025 | RESIDENTIAL NEW DWELLING REVISION v.2 | 08/12/2025 | APPROVED |
| 07/10/2025 | RESIDENTIAL NEW DWELLING REVISION v.1 | 07/10/2025 | REQUIRES RESUBMIT |
| 05/05/2025 | RESIDENTIAL NEW DWELLING v.1 | 06/09/2025 | APPROVED |
Conditions
Permit Number - TC-RES-0525-02365
Permit Status: Inspections complete
Permit Description: Laundry Room Addition
| Date | Description | Comments |
|---|---|---|
| 05/05/2025 | Contractor with active Arizona Contractor's License for specified scope of work, or a signed Owner Builder Affidavit is required prior to issuance of permit. The Affidavit form is available at https://www.tucsonaz.gov/Departments/Planning-Development-Services/Permits/Residential-Permits. Contractor or Owner must have a TDC Online account and be added to the permit as the correct contact type https://www.tucsonaz.gov/files/sharedassets/public/v/2/pdsd/documents/tdc-faq/new-pdfs/adding-additional-contacts.pdf. If you are providing an Owner Builder Affidavit, the owner MUST be attached as a contact on the permit. | |
| 05/29/2025 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. |
Outstanding Inspections
Permit Status: Inspections Complete
Permit Number: TC-RES-0525-02365
Permite Description: Laundry Room Addition
Total Outstanding Inspections - 3
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/23/2025 | COT - RSEL - Electrical Final | N/A | Not Ready | 9.23.29 Not ready - Call with other finals when build is complete |
| 10/31/2025 | RSBU - Building Final | N/A | Re-inspection required | 10-31-25: hammer arrestors required for washer & dryer, weather resistant gfci receptacles are required at the exterior, install bubble cover receptacles-covers must be rated "heavy duty while in use." With the exception of the outstanding exterior clips/sheathing /framing inspection-please schedule all remaining inspections. NOTE: the exterior clips/sheathing/framing inspection was never inspected. If possible, provide pictures of anchor bolt spacing, all hardware to include hangers, H-25's, and hold-downs if any. Also, provide a video or photos with regard to nailing on the sheathing , drywall screw/or nailing spacing. Where unable to meet this request, a letter from a licensed contractor will be required documenting that the drywall shear wall & sheathing nailing together with all hardware was installed per the plans and meets the 2018 IRC. The letter would have to be submitted to the city for review and approval before a letter of completion could issued. Additionally and aside from the letter, we would require small sections of the drywall at the base be remove so that we could inspect anchor bolt spacing. |
| 09/23/2025 | COT - RSPL - Plumbing Final | N/A | Not Ready | 9.23.29 Not ready - Call with other finals |
Completed Inspections
Permit Status: Inspections Complete
Permit Number: TC-RES-0525-02365
Permit Description: Laundry Room Addition
Total Completed Inspections - 9
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/03/2025 | COT - RSBU - Excavation/Rebar/Zoning | Passed | 9-3-25: corrections made-okay to pour concrete. | |
| 09/23/2025 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | 9.23.25 Approved, proceed |
|
| 09/23/2025 | COT - RSBU - Roof Nailing | Passed | ||
| 11/06/2025 | COT - RSEL - Electrical Final | Passed | 11-6-25: electrical final approved. | |
| 11/06/2025 | COT - RSBU - Preslab | Passed | 11-6-25: previously inspected & approved. | |
| 11/21/2025 | RSBU - Building Final | Passed | ||
| 11/21/2025 | COT - RSPL - Plumbing Final | Passed | ||
| 11/21/2025 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | Passed | ||
| 11/21/2025 | COT - RSPL - Rough Soil | Passed |