Permit: TC-RES-0326-01109
Permit Details
Status:
Inspections Complete
Type:
Residential Building - One or Two Family
Address:
130 N MELROSE AV UNIT 2
Address NEW:
130 N MELROSE AV UNIT 2
Apply Date:
03/04/2026
Applicant:
Chris Steele
Description:
Accessory Dwelling Unit (ADU)
Permit Reviews
Permit Number - TC-RES-0326-01109
Permit Status: Inspections complete
Permit Description: Accessory Dwelling Unit (ADU)
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 04/13/2026 | RESIDENTIAL ADU v.3 | 04/22/2026 | APPROVED |
| 03/24/2026 | RESIDENTIAL ADU v.2 | 04/06/2026 | REQUIRES RESUBMIT |
| 08/20/2026 | RESIDENTIAL ADU REVISION v.1 | N/A | REQUIRES RESUBMIT |
| 03/06/2026 | RESIDENTIAL ADU v.1 | 03/18/2026 | REQUIRES RESUBMIT |
Conditions
Permit Number - TC-RES-0326-01109
Permit Status: Inspections complete
Permit Description: Accessory Dwelling Unit (ADU)
| Date | Description | Comments |
|---|---|---|
| 03/25/2026 | Submit the Air Leakage & Duct Tightness Test Report completed by an Approved Special Inspector prior to Final Inspections. | |
| 03/06/2026 | Contractor with active Arizona Contractor's License for specified scope of work, or a signed Owner Builder Affidavit is required prior to issuance of permit. The Affidavit form is available at https://www.tucsonaz.gov/Departments/Planning-Development-Services/Permits/Residential-Permits. Contractor or Owner must have a TDC Online account and be added to the permit as the correct contact type https://www.tucsonaz.gov/files/sharedassets/public/v/2/pdsd/documents/tdc-faq/new-pdfs/adding-additional-contacts.pdf. If you are providing an Owner Builder Affidavit, the owner MUST be attached as a contact on the permit. | |
| 03/18/2026 | Manual J |
Outstanding Inspections
Permit Status: Inspections Complete
Permit Number: TC-RES-0326-01109
Permite Description: Accessory Dwelling Unit (ADU)
Total Outstanding Inspections - 1
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/18/2026 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | N/A | Partial Pass | 5/18/2026 Partial pass pending hanger per D1-20 detail, D1-11 & D2-17 corner post connections. Roof joist modification details received and uploaded into permit. Verified added anchor bolt at marked locations 12" from sill plate edge and sister stud damaged stud upstairs as marked. |
Completed Inspections
Permit Status: Inspections Complete
Permit Number: TC-RES-0326-01109
Permit Description: Accessory Dwelling Unit (ADU)
Total Completed Inspections - 18
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/01/2026 | COT - RSPL - Rough Soil | Passed | Okay to backfill. Shading required. 5/1/2026 | |
| 05/06/2026 | COT - RSBU - Excavation/Rebar/Zoning | Passed | ||
| 05/06/2026 | COT - RSBU - Preslab | Passed | All corrections were made. Okay for concrete placement. 5/6/2026 | |
| 05/08/2026 | COT - RSPL - Yard Water Line | Passed | 05/08/2026 Verified tie in riser, under test - ok to backfill, shading required. |
|
| 05/13/2026 | BULD - Electrical Clearance | Passed | 5/13/2026 Approved clearance TEP ECO for 3-meter pack new ADU. |
|
| 05/13/2026 | COT - RSEL - Electrical Underground | Passed | 5/13/2026 2.5" schedule 40 conduit 15’ run from transformer to new ADU panel - okay to backfill with shading. 2" schedule 40 conduit run of 60’ from existing house new load center to new ADU panel - okay to backfill, shading required. |
|
| 05/13/2026 | COT - RSEL - Grounding/Bonding | Passed | ||
| 05/18/2026 | COT - RSBU - Roof Nailing | Passed | 5/18/2026 Attached roof joist modification detail. |
|
| 05/29/2026 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | Passed | 05/29/2026 Corrections made to 5/18/26 inspection. |
|
| 05/29/2026 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | 05/29/2026 Verified moved electrical outlet above range, added nail plates to DWV within 1.25" to face on sill plates. |
|
| 06/17/2026 | COT - RSBU - Firewall/Fire Barrier/Firestop | Passed | 06/17/2026 Approved, verified garage firewall and drywall nail schedule throughout. Okay to tape and texture. |
|
| 08/18/2026 | RSEL - Electrical Progress | Passed | ||
| 08/18/2026 | RSPL - Plumbing Progress | Passed | ||
| 08/18/2026 | COT - RSEL - Electrical Final | Passed | ||
| 08/18/2026 | COT - RSEL - Outdoor Lighting | Passed | ||
| 08/18/2026 | COT - RSME - Mechanical Final | Passed | ||
| 08/18/2026 | COT - RSPL - Plumbing Final | Passed | ||
| 08/20/2026 | RSBU - Building Final | Passed | Passed |