Permit Details

Status:
Inspections Complete
Type:
Residential Building - One or Two Family
Apply Date:
03/04/2026
Applicant:
Chris Steele
Description:
Accessory Dwelling Unit (ADU)

Permit Reviews

Permit Number - TC-RES-0326-01109
Permit Status: Inspections complete
Permit Description: Accessory Dwelling Unit (ADU)
Start Date Submittal Complete Date Status  
04/13/2026 RESIDENTIAL ADU v.3 04/22/2026 APPROVED Review Details
03/24/2026 RESIDENTIAL ADU v.2 04/06/2026 REQUIRES RESUBMIT Review Details
08/20/2026 RESIDENTIAL ADU REVISION v.1 N/A REQUIRES RESUBMIT Review Details
03/06/2026 RESIDENTIAL ADU v.1 03/18/2026 REQUIRES RESUBMIT Review Details

Conditions

Permit Number - TC-RES-0326-01109
Permit Status: Inspections complete
Permit Description: Accessory Dwelling Unit (ADU)
Date Description Comments
03/25/2026 Submit the Air Leakage & Duct Tightness Test Report completed by an Approved Special Inspector prior to Final Inspections.
03/06/2026 Contractor with active Arizona Contractor's License for specified scope of work, or a signed Owner Builder Affidavit is required prior to issuance of permit. The Affidavit form is available at https://www.tucsonaz.gov/Departments/Planning-Development-Services/Permits/Residential-Permits. Contractor or Owner must have a TDC Online account and be added to the permit as the correct contact type https://www.tucsonaz.gov/files/sharedassets/public/v/2/pdsd/documents/tdc-faq/new-pdfs/adding-additional-contacts.pdf. If you are providing an Owner Builder Affidavit, the owner MUST be attached as a contact on the permit.
03/18/2026 Manual J

Outstanding Inspections

Permit Status: Inspections Complete
Permit Number: TC-RES-0326-01109
Permite Description: Accessory Dwelling Unit (ADU)
Total Outstanding Inspections - 1
Last Inspection Date Description Inspector Results Comments
05/18/2026 COT - RSBU - Exterior/Interior Clips/Sheathing/Framing N/A Partial Pass 5/18/2026
Partial pass pending hanger per D1-20 detail, D1-11 & D2-17 corner post connections. Roof joist modification details received and uploaded into permit. Verified added anchor bolt at marked locations 12" from sill plate edge and sister stud damaged stud upstairs as marked.

Completed Inspections

Permit Status: Inspections Complete
Permit Number: TC-RES-0326-01109
Permit Description: Accessory Dwelling Unit (ADU)
Total Completed Inspections - 18
Date Description Inspector Results Comments
05/01/2026 COT - RSPL - Rough Soil Passed Okay to backfill. Shading required. 5/1/2026
05/06/2026 COT - RSBU - Excavation/Rebar/Zoning Passed
05/06/2026 COT - RSBU - Preslab Passed All corrections were made. Okay for concrete placement. 5/6/2026
05/08/2026 COT - RSPL - Yard Water Line Passed 05/08/2026
Verified tie in riser, under test - ok to backfill, shading required.
05/13/2026 BULD - Electrical Clearance Passed 5/13/2026
Approved clearance TEP ECO for 3-meter pack new ADU.
05/13/2026 COT - RSEL - Electrical Underground Passed 5/13/2026
2.5" schedule 40 conduit 15’ run from transformer to new ADU panel - okay to backfill with shading. 2" schedule 40 conduit run of 60’ from existing house new load center to new ADU panel - okay to backfill, shading required.
05/13/2026 COT - RSEL - Grounding/Bonding Passed
05/18/2026 COT - RSBU - Roof Nailing Passed 5/18/2026
Attached roof joist modification detail.
05/29/2026 COT - RSBU - Exterior/Interior Clips/Sheathing/Framing Passed 05/29/2026
Corrections made to 5/18/26 inspection.
05/29/2026 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Passed 05/29/2026
Verified moved electrical outlet above range, added nail plates to DWV within 1.25" to face on sill plates.
06/17/2026 COT - RSBU - Firewall/Fire Barrier/Firestop Passed 06/17/2026
Approved, verified garage firewall and drywall nail schedule throughout. Okay to tape and texture.
08/18/2026 RSEL - Electrical Progress Passed
08/18/2026 RSPL - Plumbing Progress Passed
08/18/2026 COT - RSEL - Electrical Final Passed
08/18/2026 COT - RSEL - Outdoor Lighting Passed
08/18/2026 COT - RSME - Mechanical Final Passed
08/18/2026 COT - RSPL - Plumbing Final Passed
08/20/2026 RSBU - Building Final Passed Passed

Documents

File Name Document Type  
COFT - PDSD - PERMIT CARD (SSRS).PDF DOCUMENTS VIEW
CONS-MARES ADU (UNIT-2) PERMIT SET (4-6-26) REV_V3.PDF DOCUMENTS VIEW