Permit Details

Status:
Complete
Type:
Residential Building - One or Two Family
Apply Date:
03/24/2025
Applicant:
Francisco Gallardo
Description:
REV_1, Add dual meter unit; Accessory Dwelling Unit

Permit Reviews

Permit Number - TC-RES-0325-01502
Permit Status: Complete
Permit Description: REV_1, Add dual meter unit; Accessory Dwelling Unit
Start Date Submittal Complete Date Status  
12/31/2025 RESIDENTIAL ADU REVISION v.1 01/07/2026 APPROVED Review Details
11/13/2025 ADMINISTRATIVE v.2 11/13/2025 REQUIRES RESUBMIT Review Details
10/13/2025 RESIDENTIAL NEW DWELLING v.3 10/24/2025 APPROVED Review Details
06/29/2026 BUILDING DEFERRED SUBMITTAL REVIEW v.2 06/30/2026 APPROVED Review Details
07/15/2025 RESIDENTIAL NEW DWELLING v.2 07/15/2025 REQUIRES RESUBMIT Review Details
02/19/2026 RESIDENTIAL ADU REVISION v.1 03/04/2026 APPROVED Review Details
04/03/2025 RESIDENTIAL NEW DWELLING v.1 04/30/2025 REQUIRES RESUBMIT Review Details
10/24/2025 ADMINISTRATIVE v.1 10/24/2025 REQUIRES RESUBMIT Review Details
06/18/2026 BUILDING DEFERRED SUBMITTAL REVIEW v.1 06/18/2026 REQUIRES RESUBMIT Review Details
11/13/2025 ADMINISTRATIVE v.3 11/13/2025 APPROVED Review Details

Conditions

Permit Number - TC-RES-0325-01502
Permit Status: Complete
Permit Description: REV_1, Add dual meter unit; Accessory Dwelling Unit
Date Description Comments
04/28/2025 Please contact Pima County Addressing to resolve issue. Addressing@pima.gov or 520-724-9512
04/03/2025 Contractor with active Arizona Contractor's License for specified scope of work, or a signed Owner Builder Affidavit is required prior to issuance of permit. The Affidavit form is available at https://www.tucsonaz.gov/Departments/Planning-Development-Services/Permits/Residential-Permits. Contractor or Owner must have a TDC Online account and be added to the permit as the correct contact type https://www.tucsonaz.gov/files/sharedassets/public/v/2/pdsd/documents/tdc-faq/new-pdfs/adding-additional-contacts.pdf. If you are providing an Owner Builder Affidavit, the owner MUST be attached as a contact on the permit.
04/28/2025 Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building.

Outstanding Inspections

Permit Status: Complete
Permit Number: TC-RES-0325-01502
Permite Description: REV_1, Add dual meter unit; Accessory Dwelling Unit
Total Outstanding Inspections - 2
Last Inspection Date Description Inspector Results Comments
02/18/2026 COT - RSBU - Exterior/Interior Clips/Sheathing/Framing N/A Re-inspection required 2.18.26
Multiple items from previous list have not been addressed - inspection stopped.
03/25/2026 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. N/A Re-inspection required 3-25-26: missing smoke detector at hallway, secure all dwv, add Boca plates at sill & top plates at marked locations, fire foam all penetrations at top plates, dwv resting on top of 2x4 is not a listed means of support, therefore, add plumbers tape around dwv, remove cover plate at metal boxes in living room & at bedroom to verify ground, a 12" clearance between can lights and per lines is required. Either relocate per lines allowing for 12" clearance or block using plywood, drywall, osb.

Completed Inspections

Permit Status: Complete
Permit Number: TC-RES-0325-01502
Permit Description: REV_1, Add dual meter unit; Accessory Dwelling Unit
Total Completed Inspections - 13
Date Description Inspector Results Comments
12/30/2025 COT - RSBU - Preslab Passed 12/30/2025
Approved per site plan. Verified existing fence will be moved to accommodate setbacks. Okay for concrete placement.
12/30/2025 COT - RSBU - Excavation/Rebar/Zoning Passed 12/30/2025
Approved per site plan. Verified existing fence will be moved to accommodate setbacks. Okay for concrete placement.
02/20/2026 COT - RSBU - Roof Nailing Passed 2-20-26: roof inspection approved. Okay to dry-in.
02/20/2026 COT - RSBU - Exterior/Interior Clips/Sheathing/Framing Passed 2-20-26: exterior clips/sheathing approved. Okay to continue with construction.
03/11/2026 COT - RSPL - Yard Water Line Passed 03/11/2026
Main water line under test with blue tracer wire and holding, approved to backfill with shading material.
03/20/2026 BULD - Electrical Clearance Passed 3/20/2026
Approved clearance TEP INCR for Unit 2 ADU cutover. TEP tech on site required re-inspect since subpanel in ADU was not completed prior to clearance.
03/27/2026 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Passed 3.27.26
Corrections made, proceed
04/03/2026 COT - RSBU - Interior Shear Bracing Passed 4-3-26: okay to tape & texture drywall.
05/05/2026 COT - RSME - Mechanical Final Passed 5.5.26
Approved
05/05/2026 COT - RSPL - Plumbing Final Passed 5.5.26
Approved
05/05/2026 COT - RSEL - Electrical Final Passed 5.5.26
Approved
05/07/2026 RSBU - Building Final Passed
05/12/2026 COT - RSPL - Rough Soil Passed 05/12/2026
Passed on 5/5/26.