Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Permit Details

Status:
Complete
Type:
Model Building Permit
Apply Date:
12/31/2025
Applicant:
Brandon Matheson
Description:
737-ADU Model Plan (Model Master Plan TC-MDP-1125-00735)

Permit Reviews

Permit Number - TC-MDP-1225-00808
Permit Status: Complete
Permit Description: 737-ADU Model Plan (Model Master Plan TC-MDP-1125-00735)
Start Date Submittal Complete Date Status  
02/06/2026 SITE FROM MODEL TEMPLATE - INFILL BUILDERS v.2 02/12/2026 APPROVED Review Details
01/02/2026 SITE FROM MODEL TEMPLATE - INFILL BUILDERS v.1 01/16/2026 REQUIRES RESUBMIT Review Details
06/02/2026 BUILDING DEFERRED SUBMITTAL REVIEW v.1 06/02/2026 APPROVED Review Details
02/12/2026 RESTAMP - RESIDENTIAL v.1 02/18/2026 APPROVED Review Details

Conditions

Permit Number - TC-MDP-1225-00808
Permit Status: Complete
Permit Description: 737-ADU Model Plan (Model Master Plan TC-MDP-1125-00735)
Date Description Comments
12/26/2025 Submit the Air Leakage & Duct Tightness Test Report completed by an Approved Special Inspector prior to Final Inspections.
12/26/2025 Contractor with active Arizona Contractor's License for specified scope of work, or a signed Owner Builder Affidavit is required prior to issuance of permit. The Affidavit form is available at https://www.tucsonaz.gov/Departments/Planning-Development-Services/Permits/Residential-Permits. Contractor or Owner must have a TDC Online account and be added to the permit as the correct contact type https://www.tucsonaz.gov/files/sharedassets/public/v/2/pdsd/documents/tdc-faq/new-pdfs/adding-additional-contacts.pdf. If you are providing an Owner Builder Affidavit, the owner MUST be attached as a contact on the permit.
12/26/2025 Manual J Report
12/26/2025 Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building.

Outstanding Inspections

Permit Status: Complete
Permit Number: TC-MDP-1225-00808
Permite Description: 737-ADU Model Plan (Model Master Plan TC-MDP-1125-00735)
Total Outstanding Inspections - 9
Last Inspection Date Description Inspector Results Comments
03/10/2026 COT - RSBU - Excavation/Rebar/Zoning N/A Re-inspection required 3-10-26: provide a 1 1/2" clearance between DWV & forms, install chairs/blocks throughout pad, footing depth not per plans-a few areas at 21", reinforcement at pad is not per plans-should be #3 rebar @ 24' o.c., add reinforcement, compact pad -noted puddle of water along with water in footing.
03/10/2026 COT - RSBU - Preslab N/A Re-inspection required 3-10-26: provide a 1 1/2" clearance between DWV & forms, install chairs/blocks throughout pad, footing depth not per plans-a few areas at 21", reinforcement at pad is not per plans-should be #3 rebar @ 24' o.c., add reinforcement, compact pad -noted puddle of water along with water in footing.
03/26/2026 COT - RSBU - Roof Nailing N/A Not Ready Provide ladder prior to next inspection. 3/26/2026
03/26/2026 COT - RSBU - Firewall/Fire Barrier/Firestop N/A Partial Pass Partial pass. 1st fire wall approved. 3/26/2026
03/26/2026 COT - RSBU - Interior Shear Bracing N/A Partial Pass Partial pass. 1st fire wall approved. 3/26/2026
03/26/2026 COT - RSBU - Exterior/Interior Clips/Sheathing/Framing N/A Not Ready Nailing at shear not per schedule throughout. Provide shot pins 6" from edge and 24" o.c. Bottom plate greater than 12" requires two pins. Provide truss calcs prior to next inspection. Interior walls call to be 16" o.c. 24 o.c in field. Stopped inspection. Other items may vary. 3/26/2026
05/29/2026 COT - RSEL - Electrical Underground N/A Not Applicable
05/29/2026 COT - RSPL - Gas Pressure Test N/A Not Applicable
06/15/2026 COT - RSPL - Plumbing Final N/A Not Ready

Completed Inspections

Permit Status: Complete
Permit Number: TC-MDP-1225-00808
Permit Description: 737-ADU Model Plan (Model Master Plan TC-MDP-1125-00735)
Total Completed Inspections - 15
Date Description Inspector Results Comments
03/02/2026 COT - RSPL - Sewer Passed 3” sewer line connected to main sewer line. Ok to cover progress areas.
03/27/2026 COT - RSBU - Roof Nailing Passed
04/27/2026 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Passed
05/05/2026 COT - RSBU - Firewall/Fire Barrier/Firestop Passed
05/05/2026 COT - RSBU - Interior Shear Bracing Passed
05/05/2026 COT - RSPL - Yard Water Line Passed
05/11/2026 BULD - Electrical Clearance Passed 05/11/2026
Clearance TEP ECO.
05/11/2026 COT - RSBU - Exterior/Interior Clips/Sheathing/Framing Passed 05/11/2026
Corrections made to prior inspection.
05/29/2026 COT - RSPL - Rough Soil Passed
06/11/2026 COT - RSEL - Outdoor Lighting Passed
06/11/2026 COT - RSME - Mechanical Final Passed
06/11/2026 ENGR Engineering Final Passed Site is complete in accordance with approved plans.
06/15/2026 COT - RSEL - Electrical Final Passed 06/15/2026
All corrections made to prior inspection.
06/15/2026 RSBU - Building Final Passed 06/15/2026
All corrections made to prior inspection.
06/16/2026 COT - RSPL - Plumbing Final Passed 06/16/2026
Corrections made to condensate and whips, verified painted exposed plastic.

Documents

File Name Document Type  
COFO_FINALCOFO_RESIDENTIAL (SSRS).PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD (SSRS).PDF DOCUMENTS VIEW
1321.2 V2_V2.PDF DOCUMENTS VIEW