Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: TC-MDP-0624-00748
Permit Details
Apply Date:
06/26/2024
Applicant:
Thomas Tulloss
Description:
SFR LE23003 T22-M0056
Permit Reviews
Permit Number - TC-MDP-0624-00748
Permit Status: Issued
Permit Description: SFR LE23003 T22-M0056
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
06/27/2024 | SITE FROM MODEL PERMIT - PRODUCTION v.1 | 07/01/2024 | APPROVED |
Outstanding Activity Conditions
Permit Number - TC-MDP-0624-00748
Permit Status: Issued
Permit Description: SFR LE23003 T22-M0056
Total Outstanding Activity Conditions - 6
Date | Name |
---|---|
06/28/2024 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. |
06/28/2024 | SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED. |
06/28/2024 | Post-Tension Inspection Report is required. |
06/28/2024 | Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy. |
06/28/2024 | SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED. |
07/10/2023 | Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy. |
Conditions
Permit Number - TC-MDP-0624-00748
Permit Status: Issued
Permit Description: SFR LE23003 T22-M0056
Date | Description | Comments |
---|---|---|
06/28/2024 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. | |
07/10/2023 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. | |
06/28/2024 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. |
Outstanding Inspections
Permit Status: Issued
Permit Number: TC-MDP-0624-00748
Permite Description: SFR LE23003 T22-M0056
Total Outstanding Inspections - 2
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
11/19/2024 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | N/A | Re-inspection required | Partial pass. Provide 4" at san tee. DWV not on test. 11/18/2024 11/19/24 vent needs to be 10' away from the fresh air intake. Seal penetrations throughout, straps required throughout on pvc, DWV not on test. Trap for shower needs strap. |
11/19/2024 | BULD - Electrical Clearance | N/A | Re-inspection required | Properly set panel plate. 11/19/24 |
Completed Inspections
Permit Status: Issued
Permit Number: TC-MDP-0624-00748
Permit Description: SFR LE23003 T22-M0056
Total Completed Inspections - 14
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
08/08/2024 | COT - RSPL - Rough Soil | Passed | Okay to backfill. Shading required. 8/8/2024 | |
08/08/2024 | COT - RSPL - Sewer | Passed | Okay to backfill. Shading required. 8/8/2024 | |
08/08/2024 | COT - RSPL - Yard Water Line | Passed | Okay to backfill. Shading required. 8/8/2024 | |
08/21/2024 | COT - RSBU - Preslab | Passed | ||
08/21/2024 | COT - RSEL - Electrical Underground | Passed | ||
08/21/2024 | COT - RSBU - Excavation/Rebar/Zoning | Passed | ||
08/21/2024 | COT - RSEL - Grounding/Bonding | Passed | ||
10/11/2024 | COT - RSBU - Roof Nailing | Passed | ||
10/24/2024 | COT - RSBU - Exterior Clips/Sheathing | Passed | 10-24-24, items noted from inspection 9-18 have been corrected.Okay to proceed with construction. | |
11/18/2024 | COT - RSPL - Gas Pressure Test | Passed | ||
11/18/2024 | RSBU - Building Progress | Passed | ||
11/22/2024 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | 11-22-24, items requiring correction have been rectified. Intermediate inspection approved-okay to proceed with construction. | |
12/02/2024 | BULD - Electrical Clearance | Passed | 12-2-24, ECO issued to TEP. | |
12/02/2024 | COT - RSBU - Interior Shear Bracing | Passed | 12-2-24, interior shear bracing verified as per approved plans. Okay to tape and texture |