Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: TC-MDP-0624-00719
Permit Details
Apply Date:
06/10/2024
Applicant:
Daria Hopkins
Description:
SFR 230.2380 T21-M0028
Permit Reviews
Permit Number - TC-MDP-0624-00719
Permit Status: Issued
Permit Description: SFR 230.2380 T21-M0028
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
06/11/2024 | SITE FROM MODEL PERMIT - PRODUCTION v.1 | 06/12/2024 | APPROVED |
11/07/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 11/07/2024 | APPROVED |
Outstanding Activity Conditions
Permit Number - TC-MDP-0624-00719
Permit Status: Issued
Permit Description: SFR 230.2380 T21-M0028
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
06/06/2024 | Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy. |
Conditions
Permit Number - TC-MDP-0624-00719
Permit Status: Issued
Permit Description: SFR 230.2380 T21-M0028
Date | Description | Comments |
---|---|---|
11/07/2024 | SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED. | |
06/11/2024 | Post-Installed Anchor Inspection Report is required. | |
06/11/2024 | Post-Tension Inspection Report is required. | |
06/06/2024 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. | |
06/11/2024 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. |
Completed Inspections
Permit Status: Issued
Permit Number: TC-MDP-0624-00719
Permit Description: SFR 230.2380 T21-M0028
Total Completed Inspections - 13
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
09/16/2024 | COT - RSPL - Yard Water Line | Passed | Okay to backfill. Shading required. 9/16/2024 | |
09/16/2024 | COT - RSPL - Sewer | Passed | Okay to backfill. Shading required. 9/16/2024 | |
09/16/2024 | COT - RSPL - Rough Soil | Passed | ||
09/24/2024 | COT - RSBU - Excavation/Rebar/Zoning | Passed | Passed 9/24/2024 | |
09/24/2024 | COT - RSBU - Preslab | Passed | Passed 9/24/2024 | |
09/24/2024 | COT - RSEL - Electrical Underground | Passed | Passed 9/24/2024 | |
09/24/2024 | COT - RSEL - Grounding/Bonding | Passed | Passed 9/24/2024 | |
10/14/2024 | COT - RSBU - Roof Nailing | Passed | Approved. 10/14/2024 | |
10/22/2024 | COT - RSBU - Exterior Clips/Sheathing | Passed | ||
11/05/2024 | BULD - Electrical Clearance | Passed | 11-5-24, electrical panel approved to be energized. | |
11/05/2024 | COT - RSPL - Gas Pressure Test | Passed | 11-5-24, gas pressure test verified. | |
11/06/2024 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | 11-6-24, listed items from previous inspection have been corrected. Intermediate inspection approved. | |
11/15/2024 | COT - RSBU - Interior Shear Bracing | Passed | 11-15-24, interior shear bracing verified as per approved plans. |