Permit: TC-MDP-0424-00395
Permit Details
Status:
Inspections Complete
Type:
Model Building Permit
Address:
6724 E VIA DE AYATE
Address NEW:
6724 E VIA DE AYATE
Apply Date:
04/02/2024
Applicant:
Craig Morczynski
Description:
SFR LENNLE4004 T22-M0048
Permit Reviews
Permit Number - TC-MDP-0424-00395
Permit Status: Inspections complete
Permit Description: SFR LENNLE4004 T22-M0048
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 04/04/2024 | SITE FROM MODEL PERMIT - SUBDIVISION v.1 | 04/11/2024 | APPROVED |
Outstanding Activity Conditions
Permit Number - TC-MDP-0424-00395
Permit Status: Inspections complete
Permit Description: SFR LENNLE4004 T22-M0048
Total Outstanding Activity Conditions - 7
| Date | Name |
|---|---|
| 04/02/2024 | Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy. |
| 04/11/2024 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. |
| 04/11/2024 | SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED. |
| 04/11/2024 | Post-Tension Inspection Report is required. |
| 04/11/2024 | SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED. |
| 07/18/2023 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. |
| 07/18/2023 | Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy. |
Conditions
Permit Number - TC-MDP-0424-00395
Permit Status: Inspections complete
Permit Description: SFR LENNLE4004 T22-M0048
| Date | Description | Comments |
|---|---|---|
| 04/11/2024 | Contractor with active Arizona Contractor's License for specified scope of work, or a signed Owner Builder Affidavit https://www.tucsonaz.gov/files/sharedassets/public/v/1/pdsd/documents/permits/residential-permits/pdsd_owner_builder_affidavit_081623.pdf, is required prior to issuance of permit. Contractor or Owner must have a TDC Online account and be added to the permit as the correct contact type https://www.tucsonaz.gov/files/sharedassets/public/v/2/pdsd/documents/tdc-faq/new-pdfs/adding-additional-contacts.pdf. If you are providing an Owner Builder Affidavit, the owner MUST be attached as a contact on the permit. | |
| 04/02/2024 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. | |
| 04/11/2024 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. |
Outstanding Inspections
Permit Status: Inspections Complete
Permit Number: TC-MDP-0424-00395
Permite Description: SFR LENNLE4004 T22-M0048
Total Outstanding Inspections - 3
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/07/2024 | BULD - Electrical Clearance | N/A | Re-inspection required | 10/7/24 needs to be bonded to U bar. |
| 03/06/2025 | COT - RSME - Mechanical Final | N/A | Re-inspection required | 6 Mar 25 1. Missing fire rating tag on garage door. 2. Insulation in drain pan on Air handlers 3. Refrigerant line needed to be supported 4. Condenser pad needs to be 3" above earth 5. A/C drain is covered with stucco. 6. Attic light bulb must be protected. |
| 03/06/2025 | RSBU - Building Final | N/A | Re-inspection required | 6 Mar 25 1. Missing fire rating tag on garage door. 2. Insulation in drain pan on Air handlers 3. Refrigerant line needed to be supported 4. Condenser pad needs to be 3" above earth 5. A/C drain is covered with stucco. 6. Attic light bulb must be protected. |
Completed Inspections
Permit Status: Inspections Complete
Permit Number: TC-MDP-0424-00395
Permit Description: SFR LENNLE4004 T22-M0048
Total Completed Inspections - 21
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/18/2024 | COT - RSPL - Rough Soil | Passed | ||
| 07/18/2024 | COT - RSPL - Sewer | Passed | ||
| 07/18/2024 | COT - RSPL - Yard Water Line | Passed | ||
| 07/30/2024 | COT - RSBU - Excavation/Rebar/Zoning | Passed | ||
| 07/30/2024 | COT - RSBU - Preslab | Passed | ||
| 07/30/2024 | COT - RSEL - Electrical Underground | Passed | ||
| 07/30/2024 | COT - RSEL - Grounding/Bonding | Passed | ||
| 09/09/2024 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | Passed | 9/9/2024 corrections were made. Approved. | |
| 09/09/2024 | COT - RSBU - Roof Nailing | Passed | 9/9/2024 corrections were made. Approved. | |
| 10/29/2024 | COT - RSPL - Gas Pressure Test | Passed | 10-29-24, gas test approved. | |
| 10/29/2024 | BULD - Electrical Clearance | Passed | 10-29-24, panel approved for power | |
| 11/21/2024 | COT - RSBU - Interior Shear Bracing | Passed | 11-21-24, interior shear wall verified as per approved plans. Okay to tape & texture. | |
| 01/28/2025 | COT - BULD - SWG Clearance | Passed | 1/28/25 approval for SWG clearance. | |
| 03/06/2025 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | ||
| 03/06/2025 | COT - RSEL - Electrical Final | Passed | ||
| 03/06/2025 | COT - RSEL - Outdoor Lighting | Passed | ||
| 03/06/2025 | COT - RSPL - Plumbing Final | Passed | ||
| 03/06/2025 | ENGR Engineering Final | Passed | CO Ready | |
| 03/06/2025 | RSBU - Building Progress | Passed | ||
| 03/14/2025 | COT - RSME - Mechanical Final | Passed | 14 March 25 Pass |
|
| 03/14/2025 | RSBU - Building Final | Passed | 14 March 25 Pass |