Permit: TC-MDP-0125-00055
Permit Details
Status:
Inspections Complete
Type:
Model Building Permit
Address:
12785 E MEAGAN RIDGE PL
Address NEW:
12785 E MEAGAN RIDGE PL
Apply Date:
01/29/2025
Applicant:
Description:
SFR RKM45R T21-M0093 (REVISION Delta 4) (Model master plan TC-MDP-1222-00031)
Permit Reviews
Permit Number - TC-MDP-0125-00055
Permit Status: Inspections complete
Permit Description: SFR RKM45R T21-M0093 (REVISION Delta 4) (Model master plan TC-MDP-1222-00031)
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/30/2025 | SITE FROM MODEL PERMIT - PRODUCTION v.1 | 02/06/2025 | APPROVED |
Outstanding Activity Conditions
Permit Number - TC-MDP-0125-00055
Permit Status: Inspections complete
Permit Description: SFR RKM45R T21-M0093 (REVISION Delta 4) (Model master plan TC-MDP-1222-00031)
Total Outstanding Activity Conditions - 5
| Date | Name |
|---|---|
| 01/28/2025 | Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy. For More Information visit https://www.pima.gov/1076/Sewer-Connection-Permits, To check your permit status https://permits.pima.gov/ |
| 01/30/2025 | SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED. |
| 01/30/2025 | Post-Installed Anchor Inspection Report is required. |
| 01/30/2025 | Post-Tension Inspection Report is required. |
| 01/30/2025 | Soils Special Inspection Required. |
Conditions
Permit Number - TC-MDP-0125-00055
Permit Status: Inspections complete
Permit Description: SFR RKM45R T21-M0093 (REVISION Delta 4) (Model master plan TC-MDP-1222-00031)
| Date | Description | Comments |
|---|---|---|
| 01/28/2025 | Contractor with active Arizona Contractor's License for specified scope of work, or a signed Owner Builder Affidavit https://www.tucsonaz.gov/files/sharedassets/public/v/1/pdsd/documents/permits/residential-permits/pdsd_owner_builder_affidavit_081623.pdf, is required prior to issuance of permit. Contractor or Owner must have a TDC Online account and be added to the permit as the correct contact type https://www.tucsonaz.gov/files/sharedassets/public/v/2/pdsd/documents/tdc-faq/new-pdfs/adding-additional-contacts.pdf. If you are providing an Owner Builder Affidavit, the owner MUST be attached as a contact on the permit. | |
| 01/28/2025 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. For review and assessment: apply online at https://permits.pima.gov/ or contact us at sewer@pima.gov, (520) 724-9900. |
Completed Inspections
Permit Status: Inspections Complete
Permit Number: TC-MDP-0125-00055
Permit Description: SFR RKM45R T21-M0093 (REVISION Delta 4) (Model master plan TC-MDP-1222-00031)
Total Completed Inspections - 21
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/01/2025 | COT - RSPL - Rough Soil | Passed | ||
| 04/01/2025 | COT - RSPL - Sewer | Passed | ||
| 04/01/2025 | COT - RSPL - Yard Water Line | Passed | ||
| 04/07/2025 | COT - RSBU - Excavation/Rebar/Zoning | Passed | ||
| 04/07/2025 | COT - RSBU - Preslab | Passed | ||
| 04/07/2025 | COT - RSEL - Electrical Underground | Passed | ||
| 05/07/2025 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | Passed | 5/7/25 corrections made | |
| 05/07/2025 | COT - RSBU - Roof Nailing | Passed | 5/7/25 corrections made | |
| 05/16/2025 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | ||
| 05/16/2025 | BULD - Electrical Clearance | Passed | 5/16/25 TEP CLEARANCE: ECO |
|
| 05/16/2025 | COT - RSEL - Grounding/Bonding | Passed | ||
| 05/16/2025 | COT - RSPL - Gas Pressure Test | Passed | ||
| 05/29/2025 | COT - RSBU - Interior Shear Bracing | Passed | 5-29-25: interior shear wall approved. Okay to tape & texture. | |
| 07/03/2025 | COT - BULD - SWG Clearance | Passed | ||
| 07/14/2025 | RSBU - Building Progress | Passed | 7.14.25 All receptacles are per plan and up to code. Firedoor at garage verified, thermostat height verified. Breaker schedule verified. No open unused areas at panel. Lines secured. AAV at island. Attic unit supported and installed per code. Max breaker for AC verified correct. Hammer arrestors verified. |
|
| 07/14/2025 | COT - RSEL - Electrical Final | Passed | 7.14.25 All receptacles are per plan and up to code. Firedoor at garage verified, thermostat height verified. Breaker schedule verified. No open unused areas at panel. Lines secured. AAV at island. Attic unit supported and installed per code. Max breaker for AC verified correct. Hammer arrestors verified. |
|
| 07/14/2025 | COT - RSEL - Outdoor Lighting | Passed | 7.14.25 All receptacles are per plan and up to code. Firedoor at garage verified, thermostat height verified. Breaker schedule verified. No open unused areas at panel. Lines secured. AAV at island. Attic unit supported and installed per code. Max breaker for AC verified correct. Hammer arrestors verified. |
|
| 07/14/2025 | COT - RSME - Mechanical Final | Passed | 7.14.25 All receptacles are per plan and up to code. Firedoor at garage verified, thermostat height verified. Breaker schedule verified. No open unused areas at panel. Lines secured. AAV at island. Attic unit supported and installed per code. Max breaker for AC verified correct. Hammer arrestors verified. |
|
| 07/14/2025 | COT - RSPL - Plumbing Final | Passed | 7.14.25 All receptacles are per plan and up to code. Firedoor at garage verified, thermostat height verified. Breaker schedule verified. No open unused areas at panel. Lines secured. AAV at island. Attic unit supported and installed per code. Max breaker for AC verified correct. Hammer arrestors verified. |
|
| 07/14/2025 | ENGR Engineering Final | Passed | ||
| 07/14/2025 | RSBU - Building Final | Passed | 7.14.25 All receptacles are per plan and up to code. Firedoor at garage verified, thermostat height verified. Breaker schedule verified. No open unused areas at panel. Lines secured. AAV at island. Attic unit supported and installed per code. Max breaker for AC verified correct. Hammer arrestors verified. |