Permit: TC-COM-1224-02333
Permit Details
Status:
Issued
Type:
Commercial Building
Address:
2121 N CRAYCROFT RD BLDG 4
Address NEW:
2121 N CRAYCROFT RD BLDG 4
Apply Date:
12/11/2024
Applicant:
Masters
Description:
New Shell for Starbucks
Permit Reviews
Permit Number - TC-COM-1224-02333
Permit Status: Issued
Permit Description: New Shell for Starbucks
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 12/17/2024 | COMMERCIAL REVIEW - FULL v.1 | 01/13/2025 | REQUIRES RESUBMIT |
| 12/04/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 12/11/2025 | APPROVED |
| 02/27/2025 | COMMERCIAL REVIEW - FULL v.3 | 03/24/2025 | APPROVED |
| 05/14/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 05/15/2025 | APPROVED |
| 05/20/2025 | COMMERCIAL REVIEW - FULL REVISION v.1 | 06/11/2025 | APPROVED |
| 03/24/2025 | RESTAMP - COMMERCIAL v.1 | 03/25/2025 | APPROVED |
| 08/28/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 09/02/2025 | APPROVED |
| 02/04/2025 | COMMERCIAL REVIEW - FULL v.2 | 02/20/2025 | REQUIRES RESUBMIT |
Outstanding Activity Conditions
Permit Number - TC-COM-1224-02333
Permit Status: Issued
Permit Description: New Shell for Starbucks
Total Outstanding Activity Conditions - 7
| Date | Name |
|---|---|
| 02/05/2025 | AIR BALANCING REPORT IS REQUIRED. |
| 02/05/2025 | Applies to All: Deferred submittal documents must be submitted and approved prior to installation of construction elements included in deferred submittal documents. |
| 02/05/2025 | Special inspections must be performed by an approved third party inspection agency at the owner's expense. Special inspection forms and reports are required to be submitted for review and approved prior to issuance of final approval documents. |
| 02/05/2025 | SPECIAL INSPECTION FOR OUTDOOR LIGHTING IS REQUIRED. |
| 02/05/2025 | Post-Installed Anchor Inspection Report is required. |
| 02/05/2025 | SPECIAL INSPECTION FOR REINFORCING STEEL AND/OR PRE-STRESSING TENDONS IS REQUIRED. |
| 02/05/2025 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. |
Conditions
Permit Number - TC-COM-1224-02333
Permit Status: Issued
Permit Description: New Shell for Starbucks
| Date | Description | Comments |
|---|---|---|
| 02/05/2025 | SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED. | |
| 12/17/2024 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact. | |
| 03/25/2025 | Prior to Issuance: This project requires issuance of a Development Package (DP) permit prior to issuance of this permit. Prior to TCO/Final: This project requires full completion of a Development Package (DP) permit prior to Temporary C of O and/or final completion this permit. | |
| 02/05/2025 | SPECIAL INSPECTION FOR FOUNDATION/EXCAVATION IS REQUIRED. | |
| 02/05/2025 | Masonry Inspection Report submittal review is required. | |
| 12/17/2024 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. For review and assessment: apply online at https://permits.pima.gov/ or contact us at sewer@pima.gov, (520) 724-9900. | |
| 02/05/2025 | SPECIAL INSPECTION FOR SITE PREPARATION IS REQUIRED. | |
| 02/05/2025 | A Special Inspections Intermediate Certificate must be submitted and reviewed prior to issuance of this permit. | |
| 02/05/2025 | SPECIAL INSPECTION FOR STRUCTURAL MASONRY IS REQUIRED. | |
| 02/05/2025 | SPECIAL INSPECTION FOR WELDING IS REQUIRED. |
Outstanding Inspections
Permit Status: Issued
Permit Number: TC-COM-1224-02333
Permite Description: New Shell for Starbucks
Total Outstanding Inspections - 13
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/24/2025 | COT - HCBU - Roof Nailing | N/A | Partial Pass | 6-24-25: roof nailing/sheathing approved. Okay to continue with construction at progress areas. |
| 07/21/2025 | COT - HCME - Venting | N/A | Not Applicable | |
| 08/14/2025 | COT - BULD - SWG Clearance | N/A | Not Applicable | |
| 08/18/2025 | COT - HCBU - Interior Shear Bracing | N/A | Not Applicable | |
| 08/18/2025 | COT - FCON - Sprinkler - Final | N/A | Not Applicable | Not a sprinklered building. |
| 08/18/2025 | COT - FCON - Alarm - Final | N/A | Not Applicable | No Fire Alarm in building. |
| 08/04/2025 | COT - HCME - Mechanical Progress | N/A | Canceled | Canceled per contractor. 8/4/2025 |
| 08/01/2025 | COT - HCME - Mechanical Final | N/A | Partial Pass | All except access ladder. |
| 08/01/2025 | COT - HCEL - Electrical Progress | N/A | Partial Pass | Site signs. |
| 08/04/2025 | COT - HCEL - Electrical Above Ceiling | N/A | Canceled | Canceled per contractor. 8/4/2025 |
| 08/04/2025 | COT - HCPL - Plumbing Roof Drains | N/A | Not Ready | |
| COT - FCON - Fire - Final | N/A | Not Ready | Address shall be placed on building. | |
| 08/18/2025 | COT - HCBU - Preslab | N/A | Not Ready |
Completed Inspections
Permit Status: Issued
Permit Number: TC-COM-1224-02333
Permit Description: New Shell for Starbucks
Total Completed Inspections - 25
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/15/2025 | PDSD Heavy Commercial Building Division Pre-Construction Meeting | Passed | ||
| 05/20/2025 | COT - HCBU - Excavation/Rebar/Zoning | Passed | Superintendent Mark Flesher 520-981-7697 Requesting inspection to please be around 12:00 |
|
| 05/20/2025 | COT - HCEL - Grounding/Bonding | Passed | Superintendent Mark Flesher 520-981-7697 Requesting inspection to please be around 12:00 |
|
| 05/22/2025 | COT - LCBU - Excavation/Rebar/Zoning | Passed | ||
| 05/22/2025 | COT - HCEL - Electrical Underground | Passed | ||
| 07/02/2025 | COT - HCPL - Gas Pressure Test | Passed | 7-2-25: gas pressure test approved. | |
| 07/09/2025 | COT - HCBU - Exterior Clips/Sheathing | Passed | ||
| 07/09/2025 | COT - HCBU - Framing | Passed | ||
| 07/16/2025 | COT - HCPL - Plumbing Progress | Passed | Main waterline. | |
| 07/21/2025 | COT - HCBU - Roof Nailing | Passed | ||
| 08/04/2025 | COT - HCBU - Masonry Pregrout | Passed | ||
| 08/14/2025 | BULD - Electrical Clearance | Passed | ECO building 4 |
|
| 08/18/2025 | COT - HCPL - Gas Final | Passed | ||
| 08/18/2025 | COT - HCPL - Plumbing Final | Passed | ||
| 08/25/2025 | COT - HCME - Mechanical Progress | Passed | ||
| 08/25/2025 | COT - HCEL - Outdoor Lighting | Passed | ||
| 08/25/2025 | COT - HCME - Mechanical Final | Passed | ||
| 08/26/2025 | COT - HCEL - Electrical Progress | Passed | ||
| 08/27/2025 | TRSP - ROW - Final/Close-Out | Passed | ||
| 08/27/2025 | COT - HCPL - Plumbing Roof Drains | Passed | ||
| 08/28/2025 | COT - FCON - Fire - Final | Passed | ||
| 08/29/2025 | COT - HCBU - Building Final | Passed | ||
| 08/29/2025 | COT - HCBU - Building Progress | Passed | ||
| 08/29/2025 | ENGR Engineering Final | Passed | Shell building is complete in accordance with approved plans. Okay for Letter of Completion. | |
| 11/19/2025 | COT - HCBU - Preslab | Passed |