Inspection Status: Partial Pass
Inspection History: COT - HCEL - Electrical Progress
| Date |
Description |
Inspector |
Results |
Comments |
| 07/01/2025 |
COT - HCEL - Electrical Progress |
|
Partial Pass |
7-1-25: verified 2-3" schedule 40 electrical feeder conduits from transformer to main panel located on east side-Okay to backfill approximately 60' of open trench. |
| 07/08/2025 |
COT - HCEL - Electrical Progress |
|
Partial Pass |
Site lighting |
| 07/16/2025 |
COT - HCEL - Electrical Progress |
|
Canceled |
|
| 07/23/2025 |
COT - HCEL - Electrical Progress |
|
Partial Pass |
Lines to signs, Entrance signs and clearance bar at Southwest area. |
| 07/28/2025 |
COT - HCEL - Electrical Progress |
|
Partial Pass |
7-28-25: total of 11 Schedule 40 electrical conduits inside of building verified per schedule on Detail E0.1. Okay to continue construction at progress areas. |
| 07/31/2025 |
COT - HCEL - Electrical Progress |
|
Partial Pass |
partial for can lights. |
| 08/01/2025 |
COT - HCEL - Electrical Progress |
|
Partial Pass |
Site signs. |
| 08/18/2025 |
COT - HCEL - Electrical Progress |
|
Partial Pass |
Drive through loop. |
| 08/26/2025 |
COT - HCEL - Electrical Progress |
|
Passed |
|