Inspection Status: Partial Pass

Inspection History: ENGR Engineering Final

Permit Number - TC-COM-1224-02333

Inspection Description - ENGR Engineering Final

Inspection Status - Partial Pass

Date Description Inspector Results Comments
08/01/2025 ENGR Engineering Final Partial Pass Sidewalks progress is good. No issues currently.
08/27/2025 ENGR Engineering Final Partial Pass bldg. 4, Starbucks. Paving is complete and good. Requesting erosion mitigation in semi-permanent drainage ditch between Starbucks and Hotel. Requested drainage relief at North end of paving. Advised to ensure positive drainage away from building at downspouts.
08/29/2025 ENGR Engineering Final Passed Shell building is complete in accordance with approved plans. Okay for Letter of Completion.