Inspection Status: Partial Pass
Inspection History: ENGR Engineering Final
| Date |
Description |
Inspector |
Results |
Comments |
| 08/01/2025 |
ENGR Engineering Final
|
|
Partial Pass |
Sidewalks progress is good. No issues currently. |
| 08/27/2025 |
ENGR Engineering Final
|
|
Partial Pass |
bldg. 4, Starbucks. Paving is complete and good. Requesting erosion mitigation in semi-permanent drainage ditch between Starbucks and Hotel. Requested drainage relief at North end of paving. Advised to ensure positive drainage away from building at downspouts. |
| 08/29/2025 |
ENGR Engineering Final
|
|
Passed |
Shell building is complete in accordance with approved plans. Okay for Letter of Completion. |