Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit Details

Status:
Complete
Type:
Commercial Building
Apply Date:
11/08/2022
Applicant:
Description:
New Service Facility

Permit Reviews

Permit Number - TC-COM-1122-00067
Permit Status: Complete
Permit Description: New Service Facility
Start Date Submittal Complete Date Status  
11/18/2022 COMMERCIAL REVIEW - FULL v.1 03/15/2023 REQUIRES RESUBMIT Review Details
04/27/2023 COMMERCIAL REVIEW - FULL v.2 04/27/2023 REQUIRES RESUBMIT Review Details
05/07/2024 BUILDING DEFERRED SUBMITTAL REVIEW v.1 05/07/2024 APPROVED Review Details
04/29/2024 BUILDING DEFERRED SUBMITTAL REVIEW v.1 04/30/2024 APPROVED Review Details
05/04/2023 COMMERCIAL REVIEW - FULL v.3 05/08/2023 APPROVED Review Details
05/08/2023 RESTAMP - COMMERCIAL v.1 05/09/2023 APPROVED Review Details
04/05/2024 BUILDING DEFERRED SUBMITTAL REVIEW v.1 04/08/2024 APPROVED Review Details

Conditions

Permit Number - TC-COM-1122-00067
Permit Status: Complete
Permit Description: New Service Facility
Date Description Comments
04/05/2024 AIR BALANCING REPORT IS REQUIRED.
04/05/2024 SPECIAL INSPECTION FOR BOLTS INSTALLED IN CONCRETE IS REQUIRED.
04/05/2024 SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED.
04/05/2024 SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED.
04/05/2024 SPECIAL INSPECTION FOR EXPANSION ANCHORS IS REQUIRED.
03/14/2023 Plan review applications expire 180 days from date of submittal unless the permit has been issued. Permits expire 180 days after issuance or last approved inspection.
04/05/2024 SPECIAL INSPECTION FOR FIELD WELDING IS REQUIRED.
04/05/2024 SPECIAL INSPECTION FOR HIGH STRENGTH BOLTING IS REQUIRED.
04/05/2024 Masonry Inspection Report submittal review is required.
04/05/2024 SPECIAL INSPECTION FOR OUTDOOR LIGHTING IS REQUIRED.
04/05/2024 SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED.
04/05/2024 SPECIAL INSPECTION FOR STRUCTURAL MASONRY IS REQUIRED.
04/05/2024 WATER STERILIZATION REPORT IS REQUIRED.

Outstanding Inspections

Permit Status: Complete
Permit Number: TC-COM-1122-00067
Permite Description: New Service Facility
Total Outstanding Inspections - 6
Last Inspection Date Description Inspector Results Comments
08/22/2023 COT - HCEL - Grounding/Bonding N/A Partial Pass partial for UFER connection
07/13/2023 COT - HCEL - Electrical Underground N/A Partial Pass Column line C east.
08/22/2023 COT - HCBU - Excavation/Rebar/Zoning N/A Partial Pass
11/27/2023 COT - HCBU - Framing N/A Partial Pass 11/27/23: Framing in rooms: 110,109,108,107,106,105,103,102,104,113,101,130,116,115,118,117,114,129,128,127,120,121,119,123,124,122. Per plan ok to proceed.
12/05/2023 COT - HCBU - Interior Shear Bracing N/A Partial Pass 11/28/23 south 1/2 of office area ok to tape
12/5/23: north 1/2 of office area ok to tape.
12/06/2023 COT - HCEL - Electrical Intermediate N/A Partial Pass 11/3/23:Electrical intermediate in rooms: 108,107,106,105,103,102,104,113,101,130,116,115,118,117,114,129,128,127,120,121,119,123,124,122. Per plan ok to proceed.
12/6/23: electrical rough-in in restroom 111 per plan ok to proceed.

Completed Inspections

Permit Status: Complete
Permit Number: TC-COM-1122-00067
Permit Description: New Service Facility
Total Completed Inspections - 35
Date Description Inspector Results Comments
08/18/2023 COT - HCPL - Sewer Passed Sewer line is connected to the main sewer system and holding a water test. Okay to shade pipe and backfill trench.
08/22/2023 COT - HCBU - Preslab Passed
10/06/2023 COT - HCPL - Yard Water Line Passed ok to cover
11/09/2023 COT - HCPL - Plumbing Intermediate Passed
12/21/2023 COT - HCPL - Plumbing Above Ceiling Passed
02/06/2024 COT - HCPL - Gas Pressure Test Passed
02/06/2024 COT - HCBU - Building Above Ceiling Passed Approved, corrections addressed, okay to cover progress areas
02/21/2024 BULD - Electrical Clearance Passed 2/21/24: ECO for SES 2M at 6393 S CAMPBELL AV BLDG2. OK TO ENERGIZE
02/27/2024 COT - BULD - SWG Clearance Passed Approved gas piping and pressure test, SWG Clearance is required for the meter set at building 2
03/22/2024 COT - FCON - Sprinkler - Final Passed
03/22/2024 COT - HCPL - Gas Final Passed
04/03/2024 COT - HCPL - Rough Soil Passed
04/03/2024 COT - HCPL - Backwater Valve Passed
04/03/2024 COT - HCEL - Grounding/Bonding Passed
04/03/2024 COT - HCEL - Electrical Underground Passed
04/12/2024 COT - HCBU - Excavation/Rebar/Zoning Passed
04/12/2024 COT - HCBU - Framing Passed
04/12/2024 COT - HCBU - Interior Shear Bracing Passed
04/12/2024 COT - HCEL - Electrical Intermediate Passed
04/12/2024 COT - HCPL - Plumbing Final Passed
04/12/2024 COT - FCON - Fire - Final Passed
04/12/2024 COT - FCON - Alarm - Final Passed Approved on 4/2/24 on permit TF-FCP-0324-00212.
04/12/2024 COT - HCBU - Exterior Clips/Sheathing Passed
04/12/2024 COT - HCBU - Masonry Pregrout Passed
04/12/2024 COT - HCBU - Roof Nailing Passed
04/12/2024 COT - HCBU - Stem Wall/Retaining Wall Passed
04/12/2024 COT - HCEL - Electrical Above Ceiling Passed
04/12/2024 COT - HCEL - Electrical Final Passed
04/12/2024 COT - HCEL - Outdoor Lighting Passed
04/12/2024 COT - HCME - Mechanical Above Ceiling Passed
04/12/2024 COT - HCME - Mechanical Final Passed
04/12/2024 COT - HCME - Mechanical Intermediate Passed
04/30/2024 COT - HCBU - Building Final Passed
04/30/2024 COT - HCBU - TCO Passed
04/30/2024 ENGR Engineering Final Passed

Documents

File Name Document Type  
COFO_FINALCOFO_COMMERCIAL.PDF DOCUMENTS VIEW
COFO_FINALCOFO_COMMERCIAL.PDF DOCUMENTS VIEW
63211197.CLOSE OUT-SIGNED1REVISED-2024-05-07_V1.PDF DOCUMENTS VIEW
SIC - OUTDOOR LIGHTING-2024-04-29_V1.PDF DOCUMENTS VIEW
63211197.CLOSE OUT-SIGNED-2024-04-04_V1.PDF DOCUMENTS VIEW
EPIROC (CHLORINATION REPORT)-2024-04-04_V1.PDF DOCUMENTS VIEW
HVAC TAB REPORT_V1.PDF DOCUMENTS VIEW
CONS-STANTEC_APPROVED_PLANS_V1.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
CONS-STANTEC_APPROVED_PLANS_V1.PDF DOCUMENTS VIEW
STANTEC_APPROVED_ENERGY_ENVELOPE_V1.PDF DOCUMENTS VIEW
STANTEC_APPROVED_CALCS_STRUCT_PEMB_REACT_V1.PDF DOCUMENTS VIEW
STANTEC_APPROVED_CALCS_STRUCT_PEMB_V1.PDF DOCUMENTS VIEW
STANTEC_SIC-2023-03-14_V1.PDF DOCUMENTS VIEW
STANTEC_APPROVED_CALCS_STRUCT_V1.PDF DOCUMENTS VIEW
STANTEC_APPROVED_GEOTECH_V1.PDF DOCUMENTS VIEW
STANTEC_APPROVED_PLANS_PEMB_V1.PDF DOCUMENTS VIEW
1_EPIROC (BUILDING 2) SERVICE FACILITY PEMB - BUILDING DRAWINGS (U22S0563A_PERMITS)_V1.PDF DOCUMENTS VIEW
1_EPIROC (BUILDING 2) SERVICE FACILITY PEMB - COLUMN BASE REACTIONS (U22S0563A_CBRS)_V1.PDF DOCUMENTS VIEW
1_EPIROC (BUILDING 2) SERVICE FACILITY PEMB - STRUCTURAL DESING CALCULATIONS (U22S0563A_CALCS_LOC)_V1.PDF DOCUMENTS VIEW
1_EPIROC (BUILDING 2) SERVICE FACILITY STRUCTURAL CALCULATIONS_V1.PDF DOCUMENTS VIEW
1_SERVICE FACILITY COMCHECK REPORT_V1.PDF DOCUMENTS VIEW
CONS-1_PLAN SET_V1.PDF DOCUMENTS VIEW
STANTEC PSA_V1.PDF DOCUMENTS VIEW