Permit: TC-COM-1122-00067
Permit Details
Apply Date:
11/08/2022
Applicant:
Description:
New Service Facility
Permit Reviews
Permit Number - TC-COM-1122-00067
Permit Status: Complete
Permit Description: New Service Facility
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
11/18/2022 | COMMERCIAL REVIEW - FULL v.1 | 03/15/2023 | REQUIRES RESUBMIT |
04/27/2023 | COMMERCIAL REVIEW - FULL v.2 | 04/27/2023 | REQUIRES RESUBMIT |
05/07/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 05/07/2024 | APPROVED |
04/29/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 04/30/2024 | APPROVED |
05/04/2023 | COMMERCIAL REVIEW - FULL v.3 | 05/08/2023 | APPROVED |
05/08/2023 | RESTAMP - COMMERCIAL v.1 | 05/09/2023 | APPROVED |
04/05/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 04/08/2024 | APPROVED |
Conditions
Permit Number - TC-COM-1122-00067
Permit Status: Complete
Permit Description: New Service Facility
Date | Description | Comments |
---|---|---|
04/05/2024 | AIR BALANCING REPORT IS REQUIRED. | |
04/05/2024 | SPECIAL INSPECTION FOR BOLTS INSTALLED IN CONCRETE IS REQUIRED. | |
04/05/2024 | SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED. | |
04/05/2024 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. | |
04/05/2024 | SPECIAL INSPECTION FOR EXPANSION ANCHORS IS REQUIRED. | |
03/14/2023 | Plan review applications expire 180 days from date of submittal unless the permit has been issued. Permits expire 180 days after issuance or last approved inspection. | |
04/05/2024 | SPECIAL INSPECTION FOR FIELD WELDING IS REQUIRED. | |
04/05/2024 | SPECIAL INSPECTION FOR HIGH STRENGTH BOLTING IS REQUIRED. | |
04/05/2024 | Masonry Inspection Report submittal review is required. | |
04/05/2024 | SPECIAL INSPECTION FOR OUTDOOR LIGHTING IS REQUIRED. | |
04/05/2024 | SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED. | |
04/05/2024 | SPECIAL INSPECTION FOR STRUCTURAL MASONRY IS REQUIRED. | |
04/05/2024 | WATER STERILIZATION REPORT IS REQUIRED. |
Outstanding Inspections
Permit Status: Complete
Permit Number: TC-COM-1122-00067
Permite Description: New Service Facility
Total Outstanding Inspections - 6
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
08/22/2023 | COT - HCEL - Grounding/Bonding | N/A | Partial Pass | partial for UFER connection |
07/13/2023 | COT - HCEL - Electrical Underground | N/A | Partial Pass | Column line C east. |
08/22/2023 | COT - HCBU - Excavation/Rebar/Zoning | N/A | Partial Pass | |
11/27/2023 | COT - HCBU - Framing | N/A | Partial Pass | 11/27/23: Framing in rooms: 110,109,108,107,106,105,103,102,104,113,101,130,116,115,118,117,114,129,128,127,120,121,119,123,124,122. Per plan ok to proceed. |
12/05/2023 | COT - HCBU - Interior Shear Bracing | N/A | Partial Pass | 11/28/23 south 1/2 of office area ok to tape 12/5/23: north 1/2 of office area ok to tape. |
12/06/2023 | COT - HCEL - Electrical Intermediate | N/A | Partial Pass | 11/3/23:Electrical intermediate in rooms: 108,107,106,105,103,102,104,113,101,130,116,115,118,117,114,129,128,127,120,121,119,123,124,122. Per plan ok to proceed. 12/6/23: electrical rough-in in restroom 111 per plan ok to proceed. |
Completed Inspections
Permit Status: Complete
Permit Number: TC-COM-1122-00067
Permit Description: New Service Facility
Total Completed Inspections - 35
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
08/18/2023 | COT - HCPL - Sewer | Passed | Sewer line is connected to the main sewer system and holding a water test. Okay to shade pipe and backfill trench. | |
08/22/2023 | COT - HCBU - Preslab | Passed | ||
10/06/2023 | COT - HCPL - Yard Water Line | Passed | ok to cover | |
11/09/2023 | COT - HCPL - Plumbing Intermediate | Passed | ||
12/21/2023 | COT - HCPL - Plumbing Above Ceiling | Passed | ||
02/06/2024 | COT - HCPL - Gas Pressure Test | Passed | ||
02/06/2024 | COT - HCBU - Building Above Ceiling | Passed | Approved, corrections addressed, okay to cover progress areas | |
02/21/2024 | BULD - Electrical Clearance | Passed | 2/21/24: ECO for SES 2M at 6393 S CAMPBELL AV BLDG2. OK TO ENERGIZE | |
02/27/2024 | COT - BULD - SWG Clearance | Passed | Approved gas piping and pressure test, SWG Clearance is required for the meter set at building 2 | |
03/22/2024 | COT - FCON - Sprinkler - Final | Passed | ||
03/22/2024 | COT - HCPL - Gas Final | Passed | ||
04/03/2024 | COT - HCPL - Rough Soil | Passed | ||
04/03/2024 | COT - HCPL - Backwater Valve | Passed | ||
04/03/2024 | COT - HCEL - Grounding/Bonding | Passed | ||
04/03/2024 | COT - HCEL - Electrical Underground | Passed | ||
04/12/2024 | COT - HCBU - Excavation/Rebar/Zoning | Passed | ||
04/12/2024 | COT - HCBU - Framing | Passed | ||
04/12/2024 | COT - HCBU - Interior Shear Bracing | Passed | ||
04/12/2024 | COT - HCEL - Electrical Intermediate | Passed | ||
04/12/2024 | COT - HCPL - Plumbing Final | Passed | ||
04/12/2024 | COT - FCON - Fire - Final | Passed | ||
04/12/2024 | COT - FCON - Alarm - Final | Passed | Approved on 4/2/24 on permit TF-FCP-0324-00212. | |
04/12/2024 | COT - HCBU - Exterior Clips/Sheathing | Passed | ||
04/12/2024 | COT - HCBU - Masonry Pregrout | Passed | ||
04/12/2024 | COT - HCBU - Roof Nailing | Passed | ||
04/12/2024 | COT - HCBU - Stem Wall/Retaining Wall | Passed | ||
04/12/2024 | COT - HCEL - Electrical Above Ceiling | Passed | ||
04/12/2024 | COT - HCEL - Electrical Final | Passed | ||
04/12/2024 | COT - HCEL - Outdoor Lighting | Passed | ||
04/12/2024 | COT - HCME - Mechanical Above Ceiling | Passed | ||
04/12/2024 | COT - HCME - Mechanical Final | Passed | ||
04/12/2024 | COT - HCME - Mechanical Intermediate | Passed | ||
04/30/2024 | COT - HCBU - Building Final | Passed | ||
04/30/2024 | COT - HCBU - TCO | Passed | ||
04/30/2024 | ENGR Engineering Final | Passed |