Inspection Status: Passed
Inspection History: COT - HCBU - Excavation/Rebar/Zoning
| Date |
Description |
Inspector |
Results |
Comments |
| 04/12/2024 |
COT - HCBU - Excavation/Rebar/Zoning |
|
Passed |
|
| 06/29/2023 |
COT - HCBU - Excavation/Rebar/Zoning |
|
Partial Pass |
partial approval for all pad footings except on grid line B ok to place concrete |
| 07/28/2023 |
COT - HCBU - Excavation/Rebar/Zoning |
|
Partial Pass |
Gridlines C to E .5, Full length of building OK to place concrete reference, third-party inspection |
| 08/10/2023 |
COT - HCBU - Excavation/Rebar/Zoning |
|
Partial Pass |
2nd half of slab |
| 08/22/2023 |
COT - HCBU - Excavation/Rebar/Zoning |
|
Partial Pass |
|