Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

PRO is currently experiencing an outage. Some documents and records may not be available on PRO momentarily. We apologize for the inconvenience and are working to restore full access.

Permit Details

Status:
Complete
Type:
Commercial Building
Address NEW:
3820 E FORT LOWELL RD
Apply Date:
10/10/2023
Applicant:
burak bekat
Description:
New 2 story multifamily building with 8 units

Permit Reviews

Permit Number - TC-COM-1023-02382
Permit Status: Complete
Permit Description: New 2 story multifamily building with 8 units
Start Date Submittal Complete Date Status  
10/11/2023 COMMERCIAL REVIEW - FULL v.1 11/02/2023 REQUIRES RESUBMIT Review Details
08/27/2025 BUILDING DEFERRED SUBMITTAL REVIEW v.1 08/28/2025 APPROVED Review Details
01/04/2024 RESTAMP - COMMERCIAL v.1 01/09/2024 APPROVED Review Details
01/21/2026 BUILDING DEFERRED SUBMITTAL REVIEW v.1 01/23/2026 APPROVED Review Details
11/30/2023 COMMERCIAL REVIEW - FULL v.2 12/06/2023 REQUIRES RESUBMIT Review Details
01/23/2026 BUILDING DEFERRED SUBMITTAL REVIEW v.1 01/28/2026 APPROVED Review Details
12/03/2025 COMMERCIAL REVIEW - FULL v.1 12/30/2025 APPROVED Review Details
12/19/2023 COMMERCIAL REVIEW - FULL v.3 01/04/2024 APPROVED Review Details

Conditions

Permit Number - TC-COM-1023-02382
Permit Status: Complete
Permit Description: New 2 story multifamily building with 8 units
Date Description Comments
01/04/2024 SPECIAL INSPECTION FOR BOLTS INSTALLED IN CONCRETE IS REQUIRED.
01/04/2024 SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED.
10/11/2023 Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact.
10/11/2023 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment.
06/24/2025 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. For review and assessment: apply online at https://permits.pima.gov/ or contact us at sewer@pima.gov, (520) 724-9900.
01/04/2024 SPECIAL INSPECTION FOR SITE PREPARATION IS REQUIRED.
12/18/2025 A Special Inspections Intermediate Certificate must be submitted and reviewed prior to issuance of this permit.
12/18/2025 SPECIAL INSPECTION FOR SPECIAL MOMENT RESISTING STEEL FRAMES IS REQUIRED.
01/04/2024 SPECIAL INSPECTION FOR STRUCTURAL MASONRY IS REQUIRED.
01/04/2024 SPECIAL INSPECTION FOR STRUCTURAL WELDING IS REQUIRED.
01/04/2024 Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building.

Outstanding Inspections

Permit Status: Complete
Permit Number: TC-COM-1023-02382
Permite Description: New 2 story multifamily building with 8 units
Total Outstanding Inspections - 8
Last Inspection Date Description Inspector Results Comments
09/19/2025 COT - HCPL - Plumbing Roof Drains N/A Not Ready
10/31/2025 COT - HCPL - Plumbing Intermediate N/A Partial Pass
10/29/2025 COT - HCME - Mechanical Intermediate N/A Partial Pass
12/23/2025 COT - BULD - SWG Clearance N/A Not Applicable
11/10/2025 COT - HCBU - Stem Wall/Retaining Wall N/A Partial Pass Wall on North side, reinforcement and height are good, okay to grout final lift.
12/30/2025 COT - FCON - Alarm - Final N/A Not Ready
12/30/2025 TRSP - ROW - Final/Close-Out N/A Re-inspection required
COT - FCON - Fire - Final N/A Not Ready Called in wrong inspection.

Completed Inspections

Permit Status: Complete
Permit Number: TC-COM-1023-02382
Permit Description: New 2 story multifamily building with 8 units
Total Completed Inspections - 19
Date Description Inspector Results Comments
07/03/2025 COT - HCPL - Rough Soil Passed
07/15/2025 COT - HCPL - Yard Water Line Passed
08/28/2025 COT - HCBU - Roof Nailing Passed
09/18/2025 COT - HCBU - Preslab Passed
10/01/2025 COT - HCPL - Plumbing Roof Drains Passed
10/14/2025 BULD - Electrical Clearance Passed Clearance for TEP ECO. House panel, 201,202,203,204,101,102,103,&104. 10/14/2025
10/24/2025 COT - HCBU - Framing Passed
11/13/2025 COT - HCPL - Plumbing Intermediate Passed
11/13/2025 COT - HCEL - Electrical Intermediate Passed
11/13/2025 COT - HCME - Mechanical Intermediate Passed
12/12/2025 COT - HCEL - Electrical Underground Passed
12/19/2025 COT - HCPL - Plumbing Final Passed
12/23/2025 COT - HCBU - Stem Wall/Retaining Wall Passed
12/23/2025 COT - HCME - Mechanical Final Passed
12/23/2025 COT - HCEL - Electrical Final Passed
12/30/2025 COT - FCON - Sprinkler - Final Passed
12/30/2025 ENGR Engineering Final Passed Site is safe and accessible, complete in accordance with approved plans.
01/06/2026 TRSP - ROW - Final/Close-Out Passed
01/20/2026 COT - HCBU - Building Final Passed