Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Inspection Status: Partial Pass

Inspection History: COT - HCBU - Stem Wall/Retaining Wall 

Permit Number - TC-COM-1023-02382

Inspection Description - COT - HCBU - Stem Wall/Retaining Wall 

Inspection Status - Partial Pass

Date Description Inspector Results Comments
09/25/2025 COT - HCBU - Stem Wall/Retaining Wall  Partial Pass 9/25/25
Ok to grout first lift pending fixing weep blocks at NE corner to be at finish grade and RFI no control joint @ 16’... Bond beam in place and horizontal reinforcement correct. Verts are lapped correct. Grout all cells and vibrate all grout. Call us back out for pre grout inspection when done with 2nd lift for us to check reinforcement.
10/10/2025 COT - HCBU - Stem Wall/Retaining Wall  Partial Pass 10/10/25
Pre grout of 2nd lift of Screen wall on west side South of refuse enclosures, and 25 foot section south of driveway at South perimeter. There are 2 expansion joints @ 16'. Horizontal reinforcement and Bond beam segmente at joint. 3' section of #4 wrapped with duct tape on center at joint floats at expansion joint. Okay to grout 2nd lift and bond beam. Vibrate all grout.

Request pre grout inspection for second lift for north wall when ready.. Include expansion joints in center of the long sections of wall, put in bond being the same way.
11/10/2025 COT - HCBU - Stem Wall/Retaining Wall  Partial Pass Wall on North side, reinforcement and height are good, okay to grout final lift.
12/23/2025 COT - HCBU - Stem Wall/Retaining Wall  Passed