Permit Details

Status:
Needs Resubmittal
Type:
Commercial Building
Address NEW:
8650 S ALVERNON WY
Apply Date:
09/02/2025
Applicant:
Ian Regan
Description:
RESTRICTED ACCESS Construction of Outdoor Concrete Equipment Test Pad - Ref.: TD-DEV-0325-00075 3500000.00

Permit Reviews

Permit Number - TC-COM-0925-01611
Permit Status: Needs resubmittal
Permit Description: RESTRICTED ACCESS Construction of Outdoor Concrete Equipment Test Pad - Ref.: TD-DEV-0325-00075 3500000.00
Start Date Submittal Complete Date Status  
04/27/2026 SPECIAL INSPECTION REVIEW v.1 04/29/2026 APPROVED Review Details
01/23/2026 COMMERCIAL REVIEW - LIMITED v.3 02/09/2026 REQUIRES RESUBMIT Review Details
09/30/2025 COMMERCIAL REVIEW - LIMITED v.2 10/21/2025 REQUIRES RESUBMIT Review Details
09/04/2025 COMMERCIAL REVIEW - LIMITED v.1 09/22/2025 REQUIRES RESUBMIT Review Details
04/06/2026 ADMINISTRATIVE v.1 04/06/2026 REQUIRES RESUBMIT Review Details
03/05/2026 COMMERCIAL REVIEW - LIMITED v.4 03/25/2026 APPROVED Review Details
09/09/2026 COMMERCIAL REVIEW - FULL REVISION v.1 09/09/2026 REQUIRES RESUBMIT Review Details
04/27/2026 ADMINISTRATIVE v.2 N/A IN REVIEW Review Details
06/26/2026 SPECIAL INSPECTION REVIEW v.1 06/29/2026 APPROVED Review Details
08/27/2026 SPECIAL INSPECTION REVIEW v.1 08/31/2026 APPROVED Review Details

Outstanding Activity Conditions

Permit Number - TC-COM-0925-01611
Permit Status: Needs resubmittal
Permit Description: RESTRICTED ACCESS Construction of Outdoor Concrete Equipment Test Pad - Ref.: TD-DEV-0325-00075 3500000.00
Total Outstanding Activity Conditions - 4
Date Name
04/28/2026 SPECIAL INSPECTION FOR FOUNDATION/EXCAVATION IS REQUIRED.
04/28/2026 Post-Installed Anchor Inspection Report is required.
04/28/2026 SPECIAL INSPECTION FOR SITE PREPARATION IS REQUIRED.
06/29/2026 Special inspections must be performed by an approved third party inspection agency at the owner's expense. Special inspection forms and reports are required to be submitted for review and approved prior to issuance of final approval documents.

Conditions

Permit Number - TC-COM-0925-01611
Permit Status: Needs resubmittal
Permit Description: RESTRICTED ACCESS Construction of Outdoor Concrete Equipment Test Pad - Ref.: TD-DEV-0325-00075 3500000.00
Date Description Comments
09/19/2025 SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED.
09/04/2025 Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact.
09/04/2025 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. For review and assessment: apply online at https://permits.pima.gov/ or contact us at sewer@pima.gov, (520) 724-9900.
09/19/2025 A Special Inspections Intermediate Certificate must be submitted and reviewed prior to issuance of this permit.

Outstanding Inspections

Permit Status: Needs Resubmittal
Permit Number: TC-COM-0925-01611
Permite Description: RESTRICTED ACCESS Construction of Outdoor Concrete Equipment Test Pad - Ref.: TD-DEV-0325-00075 3500000.00
Total Outstanding Inspections - 6
Last Inspection Date Description Inspector Results Comments
07/24/2026 COT - LCEL - Grounding/Bonding N/A Re-inspection required 7-24-26: excavation/ reinforcement on 5 light pole cages verified per plans. Remove all loose fill from bottom of trenches, install grounds, and we need to verify anchor bolts.
06/26/2026 COT - LCEL - Electrical Underground N/A Partial Pass 6-26-26: verified 4 electrical schedule 40 conduit stub-ups to pull boxes and a total of 4 Caldwell grounds (3/0 ) to reinforcement on future slab on grade. 2 grounds at reinforcement located at the northeast section and the other set located near the center of slab. Okay to backfill progress areas using shading materials.
09/01/2026 ENGR Engineering Final N/A Partial Pass 9/1/26: OKAY TO REQUEST LEVEL 3 TCO (Submit generator plan sheets on building permit as a revision)
09/01/2026 COT - LCBU - Building Final N/A Partial Pass 9/1/26: OKAY TO REQUEST LEVEL 3 TCO (Submit generator plan sheets on building permit as a revision)
07/02/2026 COT - LCBU - Preslab N/A Partial Pass 7-2-26: reinforcement at 2 equipment slab on grade pads verified per detail 101. Okay for concrete placement.
07/01/2026 COT - LCBU - Excavation/Rebar/Zoning N/A Re-inspection required 7-1-26: called POC at 723am and left message advising that I would be on site in the next 5 minutes. Arrived on site at 727am and waited for an escort at Gate 81A. I waited until 737am and left. Reschedule inspection when ready.
Note: another failed inspection will result with a re-inspection fee.

Completed Inspections

Permit Status: Needs Resubmittal
Permit Number: TC-COM-0925-01611
Permit Description: RESTRICTED ACCESS Construction of Outdoor Concrete Equipment Test Pad - Ref.: TD-DEV-0325-00075 3500000.00
Total Completed Inspections - 4
Date Description Inspector Results Comments
05/14/2026 PDSD Building Division Pre-Construction Meeting Passed
09/01/2026 PDSD Building Division SIte Consultation Passed
09/01/2026 COT - LCBU - Preslab Passed
09/01/2026 COT - LCBU - Excavation/Rebar/Zoning Passed