Inspection Status: Partial Pass
Inspection History: COT - LCEL - Electrical Underground
| Date |
Description |
Inspector |
Results |
Comments |
| 06/23/2026 |
COT - LCEL - Electrical Underground |
|
Partial Pass |
6-23-26: verified trench depth at 3' for 1" schedule 40 electrical conduits for light pole cages. Okay to backfill approximately 1400' of trench using shading materials. |
| 06/26/2026 |
COT - LCEL - Electrical Underground |
|
Partial Pass |
6-26-26: verified 4 electrical schedule 40 conduit stub-ups to pull boxes and a total of 4 Caldwell grounds (3/0 ) to reinforcement on future slab on grade. 2 grounds at reinforcement located at the northeast section and the other set located near the center of slab. Okay to backfill progress areas using shading materials. |
| 07/30/2026 |
COT - LCEL - Electrical Underground |
|
Partial Pass |
7-30-26: excavation/reinforcement, conduits & bonding on 5 light pole cages approved. Okay for concrete placement. |