Inspection Status: Partial Pass
Inspection History: COT - LCBU - Excavation/Rebar/Zoning
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/08/2026 | COT - LCBU - Excavation/Rebar/Zoning | Partial Pass | 6/8/26: GL 1 and 3 ready for concrete placement ( submit revised set of plans on DP to accurately reflect 5" Concrete over 4" ABC) | |
| 06/29/2026 | COT - LCBU - Excavation/Rebar/Zoning | Re-inspection required | 6-29-26: add blocks/chairs along edges/ends & remove all loose fill (throughout) from underneath reinforcement at each equipment pad. Reschedule inspection when corrections are made. | |
| 07/01/2026 | COT - LCBU - Excavation/Rebar/Zoning | Re-inspection required | 7-1-26: called POC at 723am and left message advising that I would be on site in the next 5 minutes. Arrived on site at 727am and waited for an escort at Gate 81A. I waited until 737am and left. Reschedule inspection when ready. Note: another failed inspection will result with a re-inspection fee. |