Permit: TC-COM-0825-01557
Permit Details
Status:
Complete
Type:
Commercial Building
Address:
4443 E SPEEDWAY BL
Address NEW:
4443 E SPEEDWAY BL
Apply Date:
08/19/2025
Applicant:
Erika Hernandez
Description:
Interior Remodel of existing building REV 1: Revision to A5.1 detail REV 2: Change gas pack HVAC on the roof to electrical heat pump HVAC.
Permit Reviews
Permit Number - TC-COM-0825-01557
Permit Status: Complete
Permit Description: Interior Remodel of existing building
REV 1: Revision to A5.1 detail
REV 2: Change gas pack HVAC on the roof to electrical heat pump HVAC.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 10/13/2025 | COMMERCIAL REVIEW - FULL v.2 | 11/04/2025 | REQUIRES RESUBMIT |
| 03/13/2026 | SPECIAL INSPECTION REVIEW v.1 | 03/16/2026 | APPROVED |
| 12/12/2025 | COMMERCIAL REVIEW - FULL REVISION v.1 | 12/12/2025 | REQUIRES RESUBMIT |
| 03/16/2026 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 03/17/2026 | APPROVED |
| 12/19/2025 | COMMERCIAL REVIEW - FULL REVISION v.3 | 01/15/2026 | APPROVED |
| 12/18/2025 | COMMERCIAL REVIEW - FULL REVISION v.2 | 12/18/2025 | REQUIRES RESUBMIT |
| 03/26/2026 | COMMERCIAL REVIEW - FULL REVISION v.2 | 04/20/2026 | APPROVED |
| 11/07/2025 | COMMERCIAL REVIEW - FULL v.3 | 11/13/2025 | APPROVED |
| 11/13/2025 | RESTAMP - COMMERCIAL v.1 | 11/17/2025 | APPROVED |
| 02/02/2026 | COMMERCIAL REVIEW - FULL REVISION v.1 | 02/24/2026 | REQUIRES RESUBMIT |
| 12/18/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 12/18/2025 | IN REVIEW |
| 08/20/2025 | COMMERCIAL REVIEW - FULL v.1 | 09/17/2025 | REQUIRES RESUBMIT |
Conditions
Permit Number - TC-COM-0825-01557
Permit Status: Complete
Permit Description: Interior Remodel of existing building
REV 1: Revision to A5.1 detail
REV 2: Change gas pack HVAC on the roof to electrical heat pump HVAC.
| Date | Description | Comments |
|---|---|---|
| 09/11/2025 | AIR BALANCING REPORT IS REQUIRED. | |
| 08/20/2025 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact. | |
| 08/20/2025 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. For review and assessment: apply online at https://permits.pima.gov/ or contact us at sewer@pima.gov, (520) 724-9900. | |
| 09/16/2025 | SPECIAL INSPECTION OF STEEL CONSTRUCTION IS REQUIRED. | |
| 11/12/2025 | WATER STERILIZATION REPORT IS REQUIRED. |
Outstanding Inspections
Permit Status: Complete
Permit Number: TC-COM-0825-01557
Permite Description: Interior Remodel of existing building
REV 1: Revision to A5.1 detail
REV 2: Change gas pack HVAC on the roof to electrical heat pump HVAC.
Total Outstanding Inspections - 8
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/01/2025 | COT - LCBU - Framing | N/A | Partial Pass | Partial pass pending steel beams lower showroom, revision from architect on beam fastening |
| 03/13/2026 | BULD - Electrical Clearance | N/A | Not Applicable | |
| 03/13/2026 | COT - BULD - SWG Clearance | N/A | Not Applicable | |
| 03/13/2026 | COT - LCPL - Gas Final | N/A | Not Applicable | |
| 03/13/2026 | COT - LCPL - Gas Pressure Test | N/A | Not Applicable | |
| COT - FCON - Alarm - Final | N/A | Not Ready | ||
| COT - FCON - Sprinkler - Final | N/A | Not Ready | Sprinkler heads are taped off. | |
| 03/18/2026 | COT - HCBU - TCO | N/A | Partial Pass | Level Four |
Completed Inspections
Permit Status: Complete
Permit Number: TC-COM-0825-01557
Permit Description: Interior Remodel of existing building
REV 1: Revision to A5.1 detail
REV 2: Change gas pack HVAC on the roof to electrical heat pump HVAC.
Total Completed Inspections - 18
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/01/2025 | COT - LCEL - Electrical Intermediate | Passed | Passed 12/1/25 | |
| 12/09/2025 | COT - LCBU - Framing | Passed | ||
| 12/16/2025 | COT - LCPL - Plumbing Intermediate | Passed | ||
| 02/13/2026 | COT - LCME - Mechanical Intermediate | Passed | ||
| 03/12/2026 | COT - LCBU - Building Final | Passed | ||
| 03/12/2026 | COT - LCEL - Electrical Final | Passed | ||
| 03/12/2026 | COT - LCME - Mechanical Final | Passed | ||
| 03/13/2026 | COT - LCPL - Plumbing Final | Passed | ||
| 03/13/2026 | ENGR Engineering Final | Passed | ||
| 03/16/2026 | TRSP - ROW - Final/Close-Out | Passed | ||
| 03/13/2026 | COT - LCPL - Plumbing Above Ceiling | Passed | ||
| 03/13/2026 | COT - LCEL - Electrical Above Ceiling | Passed | ||
| 03/13/2026 | COT - LCPL - Rough Soil | Passed | ||
| 03/13/2026 | COT - LCBU - Preslab | Passed | ||
| 03/16/2026 | COT - FCON - Alarm - Final | Passed | ||
| 03/16/2026 | COT - FCON - Sprinkler - Final | Passed | ||
| 03/19/2026 | COT - FCON - Fire - Final | Passed | ||
| 04/23/2026 | COT - HCBU - TCO | Passed |