Permit: TC-COM-0825-01536
Permit Details
Apply Date:
08/14/2025
Applicant:
Brittany Mason
Description:
TI TO REMODELED EMPLOYEE LOCKER ROOM, EMPLOYEE RESTROOM, AND EMPLOYEE BREAK ROOM. TOTAL AREA OF WORK IS APPX 1525 SF. PLEASE PROCESS FOR FAST TRACK REVIEW.
Permit Reviews
Permit Number - TC-COM-0825-01536
Permit Status: Complete
Permit Description: TI TO REMODELED EMPLOYEE LOCKER ROOM, EMPLOYEE RESTROOM, AND EMPLOYEE BREAK ROOM. TOTAL AREA OF WORK IS APPX 1525 SF. PLEASE PROCESS FOR FAST TRACK REVIEW.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 03/03/2026 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 03/10/2026 | APPROVED |
| 08/15/2025 | COMMERCIAL REVIEW - LIMITED v.1 | 08/29/2025 | APPROVED |
| 03/03/2026 | SPECIAL INSPECTION REVIEW v.1 | 03/03/2026 | REQUIRES RESUBMIT |
| 04/02/2026 | SPECIAL INSPECTION REVIEW v.2 | N/A | APPROVED |
| 02/06/2026 | SPECIAL INSPECTION REVIEW v.1 | 02/09/2026 | APPROVED |
Conditions
Permit Number - TC-COM-0825-01536
Permit Status: Complete
Permit Description: TI TO REMODELED EMPLOYEE LOCKER ROOM, EMPLOYEE RESTROOM, AND EMPLOYEE BREAK ROOM. TOTAL AREA OF WORK IS APPX 1525 SF. PLEASE PROCESS FOR FAST TRACK REVIEW.
| Date | Description | Comments |
|---|---|---|
| 03/10/2026 | SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED. | |
| 08/15/2025 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact. | |
| 08/29/2025 | SPECIAL INSPECTION OF EPOXY INSTALLATIONS IS REQUIRED.( during installation of all bolts and/or reinforcing bars to ensure that installation and embedment requirements have been met) | |
| 03/10/2026 | SPECIAL INSPECTION FOR HIGH STRENGTH BOLTING IS REQUIRED. | |
| 08/15/2025 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. For review and assessment: apply online at https://permits.pima.gov/ or contact us at sewer@pima.gov, (520) 724-9900. | |
| 02/06/2026 | A Special Inspections Intermediate Certificate must be submitted and reviewed prior to issuance of this permit. | |
| 08/29/2025 | WATER STERILIZATION REPORT IS REQUIRED. |
Outstanding Inspections
Permit Status: Complete
Permit Number: TC-COM-0825-01536
Permite Description: TI TO REMODELED EMPLOYEE LOCKER ROOM, EMPLOYEE RESTROOM, AND EMPLOYEE BREAK ROOM. TOTAL AREA OF WORK IS APPX 1525 SF. PLEASE PROCESS FOR FAST TRACK REVIEW.
Total Outstanding Inspections - 3
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/03/2025 | COT - LCBU - Framing | N/A | Partial Pass | Partial pass. New interior wall along with beams and post in place. Okay to proceed progress areas. 12/3/2025 |
| 11/26/2025 | COT - LCBU - Excavation/Rebar/Zoning | N/A | Partial Pass | Footings in locker room, #4 rebar dowels to existing slab. Underground plumbing in restroom. Ok to place concrete in progress areas. |
| 12/08/2025 | COT - LCPL - Plumbing Intermediate | N/A | Partial Pass | 12-8-25: in wall DWV/ domestic per plans at 1st & second level. Firefoam penetrations at penetrations and add a strap to DWV located next to urinal. Also, either provide supports at domestic above ceiling in bathroom or add 10 mil tape to prevent contact with copper and other metal. Will recheck items at electrical intermediates . |
Completed Inspections
Permit Status: Complete
Permit Number: TC-COM-0825-01536
Permit Description: TI TO REMODELED EMPLOYEE LOCKER ROOM, EMPLOYEE RESTROOM, AND EMPLOYEE BREAK ROOM. TOTAL AREA OF WORK IS APPX 1525 SF. PLEASE PROCESS FOR FAST TRACK REVIEW.
Total Completed Inspections - 20