Permit: TC-COM-0825-01536

Parcel: 132130530


Addresses:

755 E 44TH ST

Inspection Status: Passed

Inspection History: COT - LCBU - Framing

Date Description Inspector Results Comments
01/08/2026 COT - LCBU - Framing Passed Ok to cover framed walls in new storage area.
01/21/2026 COT - LCBU - Framing Passed Two New 4x4 post and and LVL beam to support mezzanine. Running along through the IT room. New set of RFI is going to be submitted to the city for review. 1/21/2026
12/03/2025 COT - LCBU - Framing Partial Pass Partial pass. New interior wall along with beams and post in place. Okay to proceed progress areas. 12/3/2025
12/11/2025 COT - LCBU - Framing Partial Pass 12/11/25
Storage area upstairs 2x8s verified, ok to lay T/G panels. Please provide revision letter and asbuilts for LVL under the window.
12/24/2025 COT - LCBU - Framing Partial Pass 12-24-25: new 1 3/4" x 16" LVL Beam with (2) #10 x 6" screws at each joist to new beam inspected. LVL Beam spans approximately 10' underneath window and an RFI to be submitted to the city for review/approval. Okay to continue with construction at progress area at own risk.