Inspection Status: Passed
Inspection History: COT - LCPL - Plumbing Intermediate
| Date |
Description |
Inspector |
Results |
Comments |
| 02/06/2026 |
COT - LCPL - Plumbing Intermediate |
|
Passed |
|
| 11/24/2025 |
COT - LCPL - Plumbing Intermediate |
|
Partial Pass |
11-24-25: underground plumbing 1st. floor at men's restroom verified under test & per plans. However, Architect to submit an RFI for current slope/setup. Okay to backfill progress areas-shading required. |
| 12/08/2025 |
COT - LCPL - Plumbing Intermediate |
|
Partial Pass |
12-8-25: in wall DWV/ domestic per plans at 1st & second level. Firefoam penetrations at penetrations and add a strap to DWV located next to urinal. Also, either provide supports at domestic above ceiling in bathroom or add 10 mil tape to prevent contact with copper and other metal. Will recheck items at electrical intermediates . |