Permit: TC-COM-0626-00869
Permit Details
Apply Date:
06/11/2026
Applicant:
Daniel Osete
Description:
Construction of a 60' x 40' pre-engineered metal building (PEMB) including office build-out and a restroom, along with associated site improvements such as grading and utilites.
Permit Reviews
Permit Number - TC-COM-0626-00869
Permit Status: In review
Permit Description: Construction of a 60' x 40' pre-engineered metal building (PEMB) including office build-out and a restroom, along with associated site improvements such as grading and utilites.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 08/14/2026 | COMMERCIAL REVIEW - FULL v.2 | N/A | IN REVIEW |
| 06/16/2026 | COMMERCIAL REVIEW - FULL v.1 | 07/10/2026 | REQUIRES RESUBMIT |
Outstanding Activity Conditions
Permit Number - TC-COM-0626-00869
Permit Status: In review
Permit Description: Construction of a 60' x 40' pre-engineered metal building (PEMB) including office build-out and a restroom, along with associated site improvements such as grading and utilites.
Total Outstanding Activity Conditions - 7
| Date | Name |
|---|---|
| 06/16/2026 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact. |
| 06/16/2026 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. For review and assessment: apply online at https://permits.pima.gov/ or contact us at sewer@pima.gov, (520) 724-9900. |
| 07/09/2026 | AIR BALANCING REPORT IS REQUIRED. |
| 07/09/2026 | Pre-Engineered Metal Building (PEMB) Construction Plans and Structural Calculations must be submitted and approved prior to the foundation inspections. The PEMB documents must be reviewed and stamped by the Engineer of Record(EOR) and then Approved by the Building Safety prior to foundation inspection and PEMB installation. |
| 07/09/2026 | Separate submittal to PC RWRD is required for new septic system. For review and assessment: apply online at https://permits.pima.gov/ or contact us at sewer@pima.gov, (520) 724-9900. |
| 07/09/2026 | A Special Inspections Intermediate Certificate must be submitted and reviewed prior to issuance of this permit. |
| 07/09/2026 | WATER STERILIZATION REPORT IS REQUIRED. |