Permit Details

Status:
Inspections
Type:
Commercial Building
Apply Date:
06/09/2023
Applicant:
Zachary Hollifield
Description:
New Office and Warehouse/40-Truck Dock.

Permit Reviews

Permit Number - TC-COM-0623-01468
Permit Status: Inspections
Permit Description: New Office and Warehouse/40-Truck Dock.
Start Date Submittal Complete Date Status  
08/15/2024 RESTAMP - COMMERCIAL v.1 08/16/2024 APPROVED Review Details
11/22/2023 COMMERCIAL REVIEW - FULL v.3 12/20/2023 REQUIRES RESUBMIT Review Details
06/09/2023 COMMERCIAL REVIEW - FULL v.1 06/30/2023 REQUIRES RESUBMIT Review Details
02/22/2024 COMMERCIAL REVIEW - FULL v.5 03/21/2024 REQUIRES RESUBMIT Review Details
09/19/2023 COMMERCIAL REVIEW - FULL v.2 10/13/2023 REQUIRES RESUBMIT Review Details
07/15/2024 COMMERCIAL REVIEW - FULL v.6 08/15/2024 APPROVED Review Details
01/17/2024 COMMERCIAL REVIEW - FULL v.4 02/09/2024 REQUIRES RESUBMIT Review Details

Outstanding Activity Conditions

Permit Number - TC-COM-0623-01468
Permit Status: Inspections
Permit Description: New Office and Warehouse/40-Truck Dock.
Total Outstanding Activity Conditions - 4
Date Name
02/06/2024 SPECIAL INSPECTION FOR BOLTS INSTALLED IN CONCRETE IS REQUIRED.
02/06/2024 SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED.
02/06/2024 Masonry Inspection Report submittal review is required.
02/06/2024 SPECIAL INSPECTION FOR WELD REINF STEEL IS REQUIRED.

Conditions

Permit Number - TC-COM-0623-01468
Permit Status: Inspections
Permit Description: New Office and Warehouse/40-Truck Dock.
Date Description Comments
06/09/2023 Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit.
06/09/2023 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment.

Outstanding Inspections

Permit Status: Inspections
Permit Number: TC-COM-0623-01468
Permite Description: New Office and Warehouse/40-Truck Dock.
Total Outstanding Inspections - 5
Last Inspection Date Description Inspector Results Comments
10/22/2024 COT - HCPL - Plumbing Progress N/A Partial Pass Room numbers #112, #110, #109, #108. Underground plumbing per plan an under test. Okay to backfill progress areas. Shading required. 10/9/2024

Pre-con for sub starting sewer line on-site. 10/14/2024
10/22/24: 6"SDR PVC from Manhole on west side of property to first manhole south west of office area. Pending air test and continuation of sewer pipe. Ok to backfill progress area.
10/18/2024 COT - HCPL - Plumbing Intermediate N/A Partial Pass 10/18/24: 6" SDR-35 PVC 100' run running east from first manhole west side of project. Ok to backfill at risk. Pressure test required.
11/08/2024 COT - HCEL - Grounding/Bonding N/A Partial Pass Partial pass. 1/0 UFER in place and secured to the rebar. 11/8/2024
11/18/2024 COT - HCBU - Excavation/Rebar/Zoning N/A Partial Pass Canceled per contractor. 10/8/2024

Grid line #6 - #14 on B. From B to B.6 footers and reinforcements per plans okay for concrete placement. 10/9/2024

From B.6 to C. Grid line #14 - #4. Footers and reinforcements per plan. Okay for concrete placement. 10/11/2024

Grid line A. #1-#4. D #4-#1. A-D office side. Okay for concrete placement. 10/15/2024
10/18/24: reinforcement per plan at stem wall and piers at GL B-C/12-14
10/23/24: reinforcement per plan at stem wall and piers at GL C 11-6.
10/29/24: reinforcement per plan at stem wall and piers GL C/ 6-2
11/7/24: reinforcement per plan at stem wall and piers GL A/3.5-4.5, D/2.5-3.1, C-D/3.1, C/3.1/4.5

11/8/2024 reinforcement per plan at stem all footings. D/1-2.5, 1/A-D, A/1-3.1, 3.1/A-A.5. okay for concrete placement in progress areas.
11/12/24: reinforcement per plan at stem wall at GL A-D/1-3
11/18/24: reinforcement per plan at warehouse slab ok to proceed.
12/09/2024 COT - HCEL - Electrical Progress N/A Partial Pass 11/4/24: electrical underground stub-outs from building at south west corner of building for CT-cabinet, secondary, outside lighting, generator, transformer switch, ok to proceed
11/13/24: not ready
12/9/24: electrical underground for TEP 4" PVC schedule 40 conduit 400' run south of building.

Documents

File Name Document Type  
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
CONS-SAIA TUCSON R6 SET 20240522_V7.PDF DOCUMENTS VIEW