Inspection Status: Partial Pass

Inspection History: COT - HCEL - Electrical Progress  

Permit Number - TC-COM-0623-01468

Inspection Description - COT - HCEL - Electrical Progress  

Inspection Status - Partial Pass

Date Description Inspector Results Comments
01/30/2025 COT - HCEL - Electrical Progress   Partial Pass 11/4/24: electrical underground stub-outs from building at south west corner of building for CT-cabinet, secondary, outside lighting, generator, transformer switch, ok to proceed
11/13/24: not ready
12/9/24: electrical underground for TEP 4" PVC schedule 40 conduit 400' run south of building.
1/30/25: electrical in wall at office area per plan ok to proceed with drywall,
03/17/2025 COT - HCEL - Electrical Progress   Partial Pass 3-17-25, 2-4" secondary Schedule 40 conduits for generator. Okay to backfill progress areas.
03/20/2025 COT - HCEL - Electrical Progress   Partial Pass 3-20-25, partial pass for low voltage/ power Schedule 40 conduits at approximately 150' for south gates, 80' for north gates and another 60' for future cable company conduits that head west from generator area located on southwest quad of building. Okay to backfill progress areas.
03/26/2025 COT - HCEL - Electrical Progress   Partial Pass 11/4/24: electrical underground stub-outs from building at south west corner of building for CT-cabinet, secondary, outside lighting, generator, transformer switch, ok to proceed
11/13/24: not ready
12/9/24: electrical underground for TEP 4" PVC schedule 40 conduit 400' run south of building.
1/30/25: electrical in wall at office area per plan ok to proceed with drywall,

3-17-25, 2-4" secondary Schedule 40 conduits for generator. Okay to backfill progress areas.
3-20-25, partial pass for low voltage/ power Schedule 40 conduits at approximately 150' for south gates, 80' for north gates and another 60' for future cable company conduits that head west from generator area located on southwest quad of building. Okay to backfill progress areas.
3/26/25: partial pass for low volt. Power schedule 40 conduit 80' for north light poles ok to proceed with backfill.
04/02/2025 COT - HCEL - Electrical Progress   Partial Pass 4-2-25, partial pass for Schedule 40 conduits located on Westside of building. Okay to backfill trenches for conduits running north and south.
11/04/2024 COT - HCEL - Electrical Progress   Partial Pass 11/4/24: electrical underground stub-outs from building at south west corner of building for CT-cabinet, secondary, outside lighting, generator, transformer switch, ok to proceed
11/13/2024 COT - HCEL - Electrical Progress   Not Ready 11/4/24: electrical underground stub-outs from building at south west corner of building for CT-cabinet, secondary, outside lighting, generator, transformer switch, ok to proceed
11/13/24: not ready
12/09/2024 COT - HCEL - Electrical Progress   Partial Pass 11/4/24: electrical underground stub-outs from building at south west corner of building for CT-cabinet, secondary, outside lighting, generator, transformer switch, ok to proceed
11/13/24: not ready
12/9/24: electrical underground for TEP 4" PVC schedule 40 conduit 400' run south of building.