Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Inspection Status: Canceled

Inspection History: COT - HCBU - Excavation/Rebar/Zoning 

Permit Number - TC-COM-0623-01468

Inspection Description - COT - HCBU - Excavation/Rebar/Zoning 

Inspection Status - Canceled

Date Description Inspector Results Comments
10/08/2024 COT - HCBU - Excavation/Rebar/Zoning  Canceled Canceled per contractor. 10/8/2024
10/09/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Grid line #6 - #14 on B. From B to B.6 footers and reinforcements per plans okay for concrete placement. 10/9/2024
10/11/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass From B.6 to C. Grid line #14 - #4. Footers and reinforcements per plan. Okay for concrete placement. 10/11/2024
10/15/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Grid line A. #1-#4. D #4-#1. A-D office side. Okay for concrete placement. 10/15/2024
10/18/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Canceled per contractor. 10/8/2024

Grid line #6 - #14 on B. From B to B.6 footers and reinforcements per plans okay for concrete placement. 10/9/2024

From B.6 to C. Grid line #14 - #4. Footers and reinforcements per plan. Okay for concrete placement. 10/11/2024

Grid line A. #1-#4. D #4-#1. A-D office side. Okay for concrete placement. 10/15/2024
10/18/24: reinforcement per plan at stem wall and piers at GL B-C/12-14
10/23/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Canceled per contractor. 10/8/2024

Grid line #6 - #14 on B. From B to B.6 footers and reinforcements per plans okay for concrete placement. 10/9/2024

From B.6 to C. Grid line #14 - #4. Footers and reinforcements per plan. Okay for concrete placement. 10/11/2024

Grid line A. #1-#4. D #4-#1. A-D office side. Okay for concrete placement. 10/15/2024
10/18/24: reinforcement per plan at stem wall and piers at GL B-C/12-14
10/23/24: reinforcement per plan at stem wall and piers at GL C 11-6.
10/29/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Canceled per contractor. 10/8/2024

Grid line #6 - #14 on B. From B to B.6 footers and reinforcements per plans okay for concrete placement. 10/9/2024

From B.6 to C. Grid line #14 - #4. Footers and reinforcements per plan. Okay for concrete placement. 10/11/2024

Grid line A. #1-#4. D #4-#1. A-D office side. Okay for concrete placement. 10/15/2024
10/18/24: reinforcement per plan at stem wall and piers at GL B-C/12-14
10/23/24: reinforcement per plan at stem wall and piers at GL C 11-6.
10/29/24: reinforcement per plan at stem wall and piers GL C/ 6-2
11/07/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Canceled per contractor. 10/8/2024

Grid line #6 - #14 on B. From B to B.6 footers and reinforcements per plans okay for concrete placement. 10/9/2024

From B.6 to C. Grid line #14 - #4. Footers and reinforcements per plan. Okay for concrete placement. 10/11/2024

Grid line A. #1-#4. D #4-#1. A-D office side. Okay for concrete placement. 10/15/2024
10/18/24: reinforcement per plan at stem wall and piers at GL B-C/12-14
10/23/24: reinforcement per plan at stem wall and piers at GL C 11-6.
10/29/24: reinforcement per plan at stem wall and piers GL C/ 6-2
11/7/24: reinforcement per plan at stem wall and piers GL A/3.5-4.5, D/2.5-3.1, C-D/3.1, C/3.1/4.5
11/08/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 11/8/2024 reinforcement per plan at stem all footings. D/1-2.5, 1/A-D, A/1-3.1, 3.1/A-A.5. okay for concrete placement in progress areas.
COT - HCBU - Excavation/Rebar/Zoning  Scheduled