Inspection History: COT - HCPL - Plumbing Progress 

Permit Number - TC-COM-0623-01468

Inspection Description - COT - HCPL - Plumbing Progress 

Inspection Status - Partial Pass

Date Description Inspector Results Comments
10/09/2024 COT - HCPL - Plumbing Progress  Partial Pass Room numbers #112, #110, #109, #108. Underground plumbing per plan an under test. Okay to backfill progress areas. Shading required. 10/9/2024
10/14/2024 COT - HCPL - Plumbing Progress  Partial Pass Pre-con for sub starting sewer line on-site. 10/14/2024
10/22/2024 COT - HCPL - Plumbing Progress  Partial Pass Room numbers #112, #110, #109, #108. Underground plumbing per plan an under test. Okay to backfill progress areas. Shading required. 10/9/2024

Pre-con for sub starting sewer line on-site. 10/14/2024
10/22/24: 6"SDR PVC from Manhole on west side of property to first manhole south west of office area. Pending air test and continuation of sewer pipe. Ok to backfill progress area.
10/23/2024 COT - HCPL - Plumbing Progress  Partial Pass Room numbers #112, #110, #109, #108. Underground plumbing per plan an under test. Okay to backfill progress areas. Shading required. 10/9/2024

Pre-con for sub starting sewer line on-site. 10/14/2024
10/22/24: 6"SDR PVC from Manhole on west side of property to first manhole south west of office area. Pending air test and continuation of sewer pipe. Ok to backfill progress area.
10/23/24: 4" SDR PVC from manhole #2 to building tie-in, 40 foot run of 6" SDR PVC from Manhole #2 running east to manhole #3.
10/25/2024 COT - HCPL - Plumbing Progress  Partial Pass Room numbers #112, #110, #109, #108. Underground plumbing per plan an under test. Okay to backfill progress areas. Shading required. 10/9/2024

Pre-con for sub starting sewer line on-site. 10/14/2024
10/22/24: 6"SDR PVC from Manhole on west side of property to first manhole south west of office area. Pending air test and continuation of sewer pipe. Ok to backfill progress area.
10/23/24: 4" SDR PVC from manhole #4 to building tie-in, 40 foot run of 6" SDR PVC from Manhole #4 east to manhole #3.
10/25/24: 6" SDR piping from manhole #4 to manhole #3 completel. Ok to proceed. Manhole #1 stubbing out 20' ok to proceed.
10/29/2024 COT - HCPL - Plumbing Progress  Partial Pass Room numbers #112, #110, #109, #108. Underground plumbing per plan an under test. Okay to backfill progress areas. Shading required. 10/9/2024

Pre-con for sub starting sewer line on-site. 10/14/2024
10/22/24: 6"SDR PVC from Manhole on west side of property to first manhole south west of office area. Pending air test and continuation of sewer pipe. Ok to backfill progress area.
10/23/24: 4" SDR PVC from manhole #4 to building tie-in, 40 foot run of 6" SDR PVC from Manhole #4 east to manhole #3.
10/25/24: 6" SDR piping from manhole #4 to manhole #3 completel. Ok to proceed. Manhole #1 stubbing out 20' ok to proceed.
10/18/24: 6" SDR-35 PVC 100' run running east from first manhole west side of project. Ok to backfill at risk. Pressure test required.
10/29/24: 6"SDR-35 PVC COMPLETE FROM MANHOLE #1 to Manhole 4 ok to proceed with Air test.