Permit: TC-COM-0525-01005
Permit Details
Status:
Issued
Type:
Commercial Building
Address:
5651 S HOUGHTON RD
Address NEW:
5651 S HOUGHTON RD
Apply Date:
05/15/2025
Applicant:
Dave Damitio
Description:
New McDonald's building
Permit Reviews
Permit Number - TC-COM-0525-01005
Permit Status: Issued
Permit Description: New McDonald's building
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 09/09/2025 | COMMERCIAL REVIEW - FULL v.3 | 09/18/2025 | APPROVED |
| 02/03/2026 | COMMERCIAL REVIEW - FULL REVISION v.1 | 02/26/2026 | REQUIRES RESUBMIT |
| 06/08/2026 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 06/09/2026 | APPROVED |
| 09/22/2025 | ADMINISTRATIVE v.1 | 09/22/2025 | REQUIRES RESUBMIT |
| 04/16/2026 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 04/24/2026 | APPROVED |
| 09/18/2025 | RESTAMP - COMMERCIAL v.1 | 09/22/2025 | APPROVED |
| 05/16/2025 | COMMERCIAL REVIEW - FULL v.1 | 06/20/2025 | REQUIRES RESUBMIT |
| 06/01/2026 | SPECIAL INSPECTION REVIEW v.1 | 06/02/2026 | APPROVED |
| 07/24/2025 | COMMERCIAL REVIEW - FULL v.2 | 08/15/2025 | REQUIRES RESUBMIT |
| 12/18/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 12/26/2025 | APPROVED |
| 10/24/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 10/27/2025 | APPROVED |
| 03/20/2026 | COMMERCIAL REVIEW - FULL REVISION v.2 | 04/01/2026 | APPROVED |
Conditions
Permit Number - TC-COM-0525-01005
Permit Status: Issued
Permit Description: New McDonald's building
| Date | Description | Comments |
|---|---|---|
| 05/16/2025 | Please contact Pima County Addressing to resolve issue. Addressing@pima.gov or 520-724-9512 | |
| 09/10/2025 | SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED. | |
| 05/16/2025 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact. | |
| 06/02/2026 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. | |
| 09/10/2025 | SPECIAL INSPECTION FOR FIELD WELDING IS REQUIRED. | |
| 09/10/2025 | SPECIAL INSPECTION FOR FOUNDATION/EXCAVATION IS REQUIRED. | |
| 08/07/2025 | SPECIAL INSPECTION FOR OUTDOOR LIGHTING IS REQUIRED. | |
| 08/07/2025 | An Outdoor Lighting Special Inspections Intermediate Certificate must be submitted and reviewed prior to issuance of this permit. https://www.tucsonaz.gov/files/sharedassets/public/v/1/city-services/planning-development-services/documents/special_inspection_certificate_odl.pdf | |
| 09/10/2025 | A Special Inspections Intermediate Certificate must be submitted and reviewed prior to issuance of this permit. | |
| 05/28/2026 | WATER STERILIZATION REPORT IS REQUIRED. | |
| 07/31/2025 | Prior to project being finalized applicant must provide recorded documents for the water and electrical easements shown to be recorded under separate instruments on sheet SP1 of TD-DEV-0525-00132 |
Outstanding Inspections
Permit Status: Issued
Permit Number: TC-COM-0525-01005
Permite Description: New McDonald's building
Total Outstanding Inspections - 11
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/15/2025 | zzzPDSD Building Division - Site Excavation/Layout/Rebar | N/A | Not Ready | |
| 12/12/2025 | COT - HCEL - Grounding/Bonding | N/A | Partial Pass | 12.12.25 Partial for ufer only |
| 01/17/2026 | COT - HCPL - Sewer | N/A | Re-inspection required | 1/16/26: Missing Clean out per C500 detail 2, two-way clean out not per plans at 2" connection to building per detail 6, 2" vent for grease trap must have tracer wire attached to plumbing underground. Corrections must be made prior to backfill. |
| 01/06/2026 | COT - HCPL - Rough Soil | N/A | Partial Pass | underslab |
| 03/09/2026 | COT - HCPL - Gas Pressure Test | N/A | Canceled | |
| 03/17/2026 | COT - HCBU - Masonry Pregrout | N/A | Not Ready | |
| 02/24/2026 | COT - HCBU - Building Progress | N/A | Partial Pass | Lath |
| COT - FCON - Hood System - Final | N/A | Not Ready | ||
| COT - FCON - Fire - Final | N/A | Not Ready | ||
| 05/29/2026 | COT - HCBU - CofO | N/A | Partial Pass | 5/29/26: OKAY TO APPLY FOR LEVEL 1 TCO ONLY. FOR STOCKING AND STORAGE ONLY. NO PUBLIC/EMPLOYEES |
| 05/29/2026 | COT - HCBU - Building Final | N/A | Partial Pass | 5/29/26: OKAY TO APPLY FOR LEVEL 1 TCO ONLY. FOR STOCKING AND STORAGE ONLY. NO PUBLIC/EMPLOYEES |
Completed Inspections
Permit Status: Issued
Permit Number: TC-COM-0525-01005
Permit Description: New McDonald's building
Total Completed Inspections - 40
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/04/2025 | COT - HCEL - Electrical Underground | Passed | 12.4.25 Conduit type and depth from panel to transformer verified and approved |
|
| 12/11/2025 | COT - HCEL - Electrical Progress | Passed | 12.4.25 Proceed Ok to backfill progress areas |
|
| 12/12/2025 | COT - HCBU - Excavation/Rebar/Zoning | Passed | Approved to pour | |
| 02/05/2026 | COT - HCPL - Yard Water Line | Passed | ||
| 02/06/2026 | COT - HCBU - Exterior Clips/Sheathing | Passed | ||
| 02/06/2026 | COT - HCBU - Roof Nailing | Passed | ||
| 02/06/2026 | COT - HCBU - Preslab | Passed | ||
| 02/12/2026 | zzzPDSD Building Division - Site Excavation/Layout/Rebar | Passed | Passed for all exterior light poles and signs | |
| 02/12/2026 | COT - HCEL - Outdoor Lighting | Passed | Passed for all exterior light poles and signs | |
| 02/12/2026 | COT - HCEL - Grounding/Bonding | Passed | Passed for all exterior light poles and signs | |
| 02/19/2026 | COT - LCPL - Yard Water Line | Passed | 2/19/26 passed | |
| 02/24/2026 | COT - HCPL - Sewer | Passed | ||
| 02/24/2026 | COT - HCPL - Rough Soil | Passed | ||
| 02/25/2026 | COT - HCPL - Plumbing Roof Drains | Passed | ||
| 03/03/2026 | COT - HCPL - Plumbing Intermediate | Passed | ||
| 03/02/2026 | COT - HCBU - Framing | Passed | In wall complete, do not cover until after plumbing complete | |
| 03/02/2026 | COT - HCEL - Electrical Intermediate | Passed | In wall complete, do not cover until after plumbing complete | |
| 03/03/2026 | COT - HCME - Mechanical Intermediate | Passed | ||
| 04/17/2026 | COT - HCBU - Building Above Ceiling | Passed | ||
| 04/17/2026 | COT - HCEL - Electrical Above Ceiling | Passed | ||
| 04/17/2026 | COT - HCPL - Plumbing Above Ceiling | Passed | ||
| 04/17/2026 | COT - HCPL - Gas Pressure Test | Passed | ||
| 04/17/2026 | COT - HCME - Mechanical Progress | Passed | ||
| 04/20/2026 | TRSP - ROW - Final/Close-Out | Passed | right of way related work, new sidewalk attached to bike lane, completed, approved | |
| 04/20/2026 | COT - HCPL - Plumbing Progress | Passed | ||
| 04/23/2026 | COT - BULD - SWG Clearance | Passed | 4/23/26 Southwest gas clearance: SWG |
|
| 04/27/2026 | BULD - Electrical Clearance | Passed | 4/27/26 CLEARANCE ECO | |
| 04/30/2026 | COT - HCBU - Masonry Pregrout | Passed | passed | |
| 04/30/2026 | COT - HCBU - Building Progress | Passed | First wrap on hood | |
| 05/01/2026 | COT - LCBU - Building Progress | Passed | 2nd wrap on hoods | |
| 05/21/2026 | COT - FCON - Alarm - Final | Passed | ||
| 05/21/2026 | COT - HCPL - Gas Final | Passed | ||
| 05/21/2026 | COT - HCME - Mechanical Final | Passed | ||
| 05/26/2026 | COT - FCON - Hood System - Final | Passed | ||
| 05/26/2026 | COT - HCEL - Electrical Final | Passed | ||
| 05/27/2026 | COT - HCPL - Plumbing Final | Passed | ||
| 05/28/2026 | COT - FCON - Fire - Final | Passed | ||
| 05/28/2026 | ENGR Engineering Final | Passed | Site is complete in accordance with approved plans. | |
| 06/04/2026 | COT - HCBU - CofO | Passed | ||
| 06/04/2026 | COT - HCBU - Building Final | Passed |