Permit: TC-COM-0525-00942
Permit Details
Status:
Complete
Type:
Commercial Building
Address:
10080 E OLD VAIL RD
Address NEW:
10080 E OLD VAIL RD
Apply Date:
05/08/2025
Applicant:
Ethan Epling
Description:
THE SCOPE OF WORK CONSISTS OF A NEW SINGLE TENANT GROUND UP PROJECT. THE STRUCTURE INCLUDES, BUT IS NOT LIMITED TO, A REINFORCED STRUCTURAL CONCRETE SLAB, WOOD STUD FRAMING & ENGINEERED WOOD JOISTS. INTERIOR CONSTRUCTION WILL COMPRISE OF METAL STUD FRAMING. ALL NEW CONSTRUCTION WILL MATCH THAT ALLOWED PER THE CONSTRUCTION TYPE LISTED BELOW.
Permit Reviews
Permit Number - TC-COM-0525-00942
Permit Status: Complete
Permit Description: THE SCOPE OF WORK CONSISTS OF A NEW SINGLE TENANT GROUND UP PROJECT. THE STRUCTURE
INCLUDES, BUT IS NOT LIMITED TO, A REINFORCED STRUCTURAL CONCRETE SLAB, WOOD STUD
FRAMING & ENGINEERED WOOD JOISTS. INTERIOR CONSTRUCTION WILL COMPRISE OF METAL STUD
FRAMING. ALL NEW CONSTRUCTION WILL MATCH THAT ALLOWED PER THE CONSTRUCTION TYPE
LISTED BELOW.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 02/11/2026 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 02/11/2026 | APPROVED |
| 09/15/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 09/19/2025 | APPROVED |
| 04/30/2026 | SPECIAL INSPECTION REVIEW v.2 | N/A | IN REVIEW |
| 09/19/2025 | ADMINISTRATIVE v.2 | 09/19/2025 | APPROVED |
| 09/11/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 09/12/2025 | APPROVED |
| 09/12/2025 | ADMINISTRATIVE v.1 | 09/12/2025 | REQUIRES RESUBMIT |
| 08/08/2025 | COMMERCIAL REVIEW - FULL v.3 | 08/18/2025 | APPROVED |
| 04/10/2026 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 04/14/2026 | APPROVED |
| 08/18/2025 | RESTAMP - COMMERCIAL v.1 | 08/20/2025 | APPROVED |
| 05/05/2026 | SPECIAL INSPECTION REVIEW v.1 | N/A | IN REVIEW |
| 03/13/2026 | SPECIAL INSPECTION REVIEW v.1 | 03/13/2026 | REQUIRES RESUBMIT |
| 07/10/2025 | COMMERCIAL REVIEW - FULL v.2 | 07/31/2025 | REQUIRES RESUBMIT |
| 05/13/2025 | COMMERCIAL REVIEW - FULL v.1 | 06/09/2025 | REQUIRES RESUBMIT |
| 03/24/2026 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 03/25/2026 | APPROVED |
Conditions
Permit Number - TC-COM-0525-00942
Permit Status: Complete
Permit Description: THE SCOPE OF WORK CONSISTS OF A NEW SINGLE TENANT GROUND UP PROJECT. THE STRUCTURE
INCLUDES, BUT IS NOT LIMITED TO, A REINFORCED STRUCTURAL CONCRETE SLAB, WOOD STUD
FRAMING & ENGINEERED WOOD JOISTS. INTERIOR CONSTRUCTION WILL COMPRISE OF METAL STUD
FRAMING. ALL NEW CONSTRUCTION WILL MATCH THAT ALLOWED PER THE CONSTRUCTION TYPE
LISTED BELOW.
| Date | Description | Comments |
|---|---|---|
| 08/18/2025 | SPECIAL INSPECTION FOR BOLTS INSTALLED IN CONCRETE IS REQUIRED. | |
| 08/18/2025 | SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED. | |
| 05/13/2025 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact. | |
| 08/18/2025 | SPECIAL INSPECTION FOR FIELD WELDING IS REQUIRED. | |
| 08/18/2025 | SPECIAL INSPECTION FOR FOUNDATION/EXCAVATION IS REQUIRED. | |
| 04/10/2026 | SPECIAL INSPECTION FOR OUTDOOR LIGHTING IS REQUIRED. | |
| 07/31/2025 | Separate submittal to PC Industrial Wastewater Control is required for dental offices, dental schools and clinics. Contact Kelsey.McMonagle@pima.gov for review and assessment of compliance with the rules for amalgam separators. | |
| 09/12/2025 | SPECIAL INSPECTION FOR REINFORCING STEEL AND/OR PRE-STRESSING TENDONS IS REQUIRED. | |
| 08/18/2025 | A Special Inspections Intermediate Certificate must be submitted and reviewed prior to issuance of this permit. | |
| 02/02/2026 | WATER STERILIZATION REPORT IS REQUIRED. | |
| 08/18/2025 | SPECIAL INSPECTION FOR WELDING IS REQUIRED. | |
| 08/18/2025 | SPECIAL INSPECTION FOR WOOD FRAMED DIAPHRAGMS AND SHEAR WALLS IS REQUIRED. |
Outstanding Inspections
Permit Status: Complete
Permit Number: TC-COM-0525-00942
Permite Description: THE SCOPE OF WORK CONSISTS OF A NEW SINGLE TENANT GROUND UP PROJECT. THE STRUCTURE
INCLUDES, BUT IS NOT LIMITED TO, A REINFORCED STRUCTURAL CONCRETE SLAB, WOOD STUD
FRAMING & ENGINEERED WOOD JOISTS. INTERIOR CONSTRUCTION WILL COMPRISE OF METAL STUD
FRAMING. ALL NEW CONSTRUCTION WILL MATCH THAT ALLOWED PER THE CONSTRUCTION TYPE
LISTED BELOW.
Total Outstanding Inspections - 14
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/28/2025 | For trash and recycling enclosures | N/A | Not Ready | Called, Ethan Epling, phone number: (520) 730-0197. Drove to site no access and no activity. |
| 11/28/2025 | COT - HCEL - Electrical Underground | N/A | Re-inspection required | 11/28/25 LIGHT POLES: 1. West light pole is missing spare 3/4" stub out; Rebar clearance needs to be 3" minimum from earth, very little clearance on the sides. 2. South light pole caisson rebar sitting on the ground; Sonos tube installed upside down. 3. East light pole, 3" clearance needed on the sides for Rebar from earth and Sonos tube installed upside down. |
| 10/02/2025 | COT - HCPL - Rough Soil | N/A | Partial Pass | 10-2-25: partial pass pending sewer/ water. Underground plumbing on DWV verified per plans-okay to backfill progress areas with shading materials. |
| 10/03/2025 | COT - LCPL - Yard Water Line | N/A | Not Ready | |
| 01/09/2026 | COT - HCPL - Plumbing Progress | N/A | Partial Pass | Partial pass. Inspection is for wall approved for both DWV and domestic water lines. Isolators were mentioned for PVC running through metal studs. Possible leak at north end center of building above ceiling. Re pressurize system prior to next inspection. 1/9/2026 |
| 01/06/2026 | COT - HCEL - Electrical Progress | N/A | Partial Pass | 1/6/26: electrical in-wall approved for rough-ins. |
| 12/18/2025 | COT - HCME - Mechanical Above Ceiling | N/A | Partial Pass | Partial pass for paddy, ok to wrap and insulate |
| 12/23/2025 | COT - HCBU - Building Progress | N/A | Partial Pass | 12/23/25: wire and lathe inspection |
| 03/04/2026 | COT - BULD - SWG Clearance | N/A | Not Applicable | |
| 03/20/2026 | COT - FCON - Fire - Final | N/A | Partial Pass | Sprinkler trim shall be installed, med gas tank shall be secured. |
| 11/07/2025 | COT - HCBU - Preslab | N/A | Partial Pass | 11-7-25: 10 mil vapor retarder in place-okay to pour slab. |
| 04/29/2026 | COT - HCBU - Building Final | N/A | Partial Pass | 4-29-26: pending 3rd party outdoor lighting inspection. |
| 12/16/2025 | COT - HCEL - Outdoor Lighting | N/A | Partial Pass | 12/16/25 Needed Electrical underground for exterior lighting; Ok to backfill. |
| 05/06/2026 | TRSP - ROW - Final/Close-Out | N/A | Deferred | Cones not related to work in ROW. No objections to CofO. |
Completed Inspections
Permit Status: Complete
Permit Number: TC-COM-0525-00942
Permit Description: THE SCOPE OF WORK CONSISTS OF A NEW SINGLE TENANT GROUND UP PROJECT. THE STRUCTURE
INCLUDES, BUT IS NOT LIMITED TO, A REINFORCED STRUCTURAL CONCRETE SLAB, WOOD STUD
FRAMING & ENGINEERED WOOD JOISTS. INTERIOR CONSTRUCTION WILL COMPRISE OF METAL STUD
FRAMING. ALL NEW CONSTRUCTION WILL MATCH THAT ALLOWED PER THE CONSTRUCTION TYPE
LISTED BELOW.
Total Completed Inspections - 35
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/03/2025 | COT - HCPL - Sewer | Passed | ||
| 10/28/2025 | COT - HCBU - Excavation/Rebar/Zoning | Passed | Passed 10/28/25 ok to pour concrete | |
| 12/05/2025 | COT - HCBU - Roof Nailing | Passed | Passed 12/5/25 nailing per plans | |
| 12/05/2025 | COT - HCBU - Exterior Clips/Sheathing | Passed | Passed 12/5/25 nailing per plans | |
| 12/05/2025 | COT - HCBU - Framing | Passed | Passed 12/5/25 nailing per plans | |
| 01/14/2026 | BULD - Electrical Clearance | Passed | 1/14/26:ECO TEP CLEARANCE 10080 E OLD VAIL RD | |
| 01/22/2026 | COT - HCPL - Plumbing Above Ceiling | Passed | 1-22-26: corrections made. Plumbing above ceiling approved-okay to continue with construction at progress areas. | |
| 02/08/2026 | COT - HCPL - Rough Soil | Passed | ||
| 02/08/2026 | COT - LCPL - Yard Water Line | Passed | ||
| 02/10/2026 | COT - HCEL - Electrical Above Ceiling | Passed | 2-10-26: electrical above ceiling lighting, electrical mc cable and supports for conduits verified per approved plans. A few junction boxes were either painted over or not labeled altogether. These items will be verified at finals-okay to continue with construction at progress areas. | |
| 03/04/2026 | COT - HCBU - Building Above Ceiling | Passed | ||
| 03/04/2026 | COT - HCEL - Electrical Intermediate | Passed | ||
| 03/04/2026 | COT - HCPL - Plumbing Progress | Passed | ||
| 03/04/2026 | COT - HCPL - Medical Gas Preconstruction Mtg | Passed | ||
| 03/04/2026 | COT - HCEL - Electrical Progress | Passed | ||
| 03/04/2026 | COT - HCEL - Grounding/Bonding | Passed | ||
| 03/04/2026 | COT - HCPL - Plumbing Roof Drains | Passed | ||
| 03/04/2026 | COT - HCPL - Plumbing Intermediate | Passed | ||
| 03/04/2026 | COT - HCME - Mechanical Above Ceiling | Passed | ||
| 03/04/2026 | COT - HCME - Mechanical Progress | Passed | ||
| 03/04/2026 | COT - HCBU - Building Progress | Passed | ||
| 04/07/2026 | COT - FCON - Sprinkler - Final | Passed | ||
| 04/07/2026 | COT - FCON - Fire - Final | Passed | ||
| 04/10/2026 | COT - HCBU - Preslab | Passed | 4-10-26: previously inspected and approved. | |
| 04/10/2026 | COT - HCME - Mechanical Intermediate | Passed | 4-10-26: previously inspected and approved. | |
| 04/10/2026 | COT - HCBU - Firewall/Fire Barrier/Firestop | Passed | 4-10-26: approved. | |
| 04/10/2026 | COT - HCPL - Medical Gas/Final | Passed | 4-10-26: approved. | |
| 04/10/2026 | COT - HCPL - Medical Gas/Test | Passed | 4-10-26: approved. | |
| 04/13/2026 | ENGR Engineering Final | Passed | Site is complete in accordance with approved plans. | |
| 05/01/2026 | COT - HCME - Mechanical Final | Passed | 5-1-26: mechanical final approved. | |
| 05/01/2026 | COT - HCPL - Plumbing Final | Passed | 5-1-26: plumbing final approved. | |
| 05/01/2026 | COT - HCEL - Electrical Final | Passed | 5-1-26: electrical final approved. | |
| 05/01/2026 | COT - HCBU - Building Final | Passed | 5-1-26: Building final approved. Okay to apply for C of O. | |
| 05/01/2026 | COT - HCBU - CofO | Passed | 5-1-26: Building final approved. Okay to apply for C of O. | |
| 05/01/2026 | COT - HCEL - Outdoor Lighting | Passed | 5-1-26: outdoor lighting approved. Report added to attachments. |