| 01/12/2026 | COT - HCPL - Plumbing Above Ceiling | Re-inspection required | 1/12/26: Per IPC table 308.5 horizontal supports on PVC is required 4’ o.c. (Supports over spaced throughout above ceiling and in wall), Per table 308.5 copper 1 1/4” or smaller required to have supports 6’ o.c at horizontal supports, properly secure copper piping throughout, R-3 insulation required at hot water piping 3/4” or larger, per previous notes | |
| 01/21/2026 | COT - HCPL - Plumbing Above Ceiling | Re-inspection required | 1-21-26: add 10 mil tape where copper lines above ceiling are in contact with other metals. Add isolators to DWV at metal framing and add some straps to copper lines between studs. See support schedule indicated from inspection 1/12/26. Schedule another plumbing above ceiling inspection to verify corrections. | |
| 01/21/2026 | COT - HCPL - Plumbing Above Ceiling | Re-inspection required (with fee) | 1-21-26: add 10 mil tape where copper lines above ceiling are in contact with other metals. Add isolators to DWV at metal framing and add some straps to copper lines between studs. See support schedule indicated from inspection 1/12/26. Schedule another plumbing above ceiling inspection to verify corrections. | |
| 01/22/2026 | COT - HCPL - Plumbing Above Ceiling | Passed | 1-22-26: corrections made. Plumbing above ceiling approved-okay to continue with construction at progress areas. |