Inspection Status: Not Ready
Inspection History: COT - HCBU - Building Final
| Date |
Description |
Inspector |
Results |
Comments |
| 03/04/2026 |
COT - HCBU - Building Final |
|
Not Ready |
|
| 04/10/2026 |
COT - HCBU - Building Final |
|
Re-inspection required |
4-10-26: add a plastic bushing at the rooftop mini split disconnect, add a 90degree elbow at mop sink together with a hose, add a metallic label at rooftop's disconnect-the label must identify the purpose and the circuit. |
| 04/29/2026 |
COT - HCBU - Building Final |
|
Partial Pass |
4-29-26: pending 3rd party outdoor lighting inspection. |
| 05/01/2026 |
COT - HCBU - Building Final |
|
Passed |
5-1-26: Building final approved. Okay to apply for C of O. |