Permit Details

Status:
Complete
Type:
Commercial Building
Address NEW:
6950 S COUNTRY CLUB RD
Apply Date:
05/05/2025
Applicant:
burak bekat
Description:
Office tenant improvement

Permit Reviews

Permit Number - TC-COM-0525-00909
Permit Status: Complete
Permit Description: Office tenant improvement
Start Date Submittal Complete Date Status  
07/29/2026 BUILDING DEFERRED SUBMITTAL REVIEW v.1 07/30/2026 APPROVED Review Details
05/08/2025 COMMERCIAL REVIEW - FULL v.1 06/04/2025 APPROVED Review Details
07/23/2025 RESTAMP - COMMERCIAL v.1 07/28/2025 REQUIRES RESUBMIT Review Details
07/28/2025 RESTAMP - COMMERCIAL v.2 07/28/2025 APPROVED Review Details
12/12/2025 BUILDING DEFERRED SUBMITTAL REVIEW v.1 12/18/2025 APPROVED Review Details
12/08/2025 BUILDING DEFERRED SUBMITTAL REVIEW v.1 12/09/2025 APPROVED Review Details

Conditions

Permit Number - TC-COM-0525-00909
Permit Status: Complete
Permit Description: Office tenant improvement
Date Description Comments
05/14/2025 There are two addresses associated with this location 6950 S COUNTRY CLUB RD TUCSON, AZ 85756 & 6950 S COUNTRY CLUB RD UNIT 304 TUCSON, AZ 85756. Please confirm the address for this permit application.
05/27/2025 AIR BALANCING REPORT IS REQUIRED.
05/08/2025 Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact.
05/27/2025 WATER STERILIZATION REPORT IS REQUIRED.

Outstanding Inspections

Permit Status: Complete
Permit Number: TC-COM-0525-00909
Permite Description: Office tenant improvement
Total Outstanding Inspections - 6
Last Inspection Date Description Inspector Results Comments
12/16/2025 BULD - Electrical Clearance N/A Not Applicable 12-16-25: not applicable.
08/20/2025 COT - HCEL - Electrical Progress N/A Partial Pass Partial pass. In wall. Offices first floor. 146 &147. Second floor offices 219, 220, & 221. Cafe wall 214. Okay to proceed progress areas. 8/20/2025
12/16/2025 COT - HCME - Mechanical Progress N/A Partial Pass 12-16-25; partial pass-office areas 1st & 2nd floor. Pending inspection on other half of building.
12/23/2025 COT - HCBU - Building Above Ceiling N/A Re-inspection required 12-23-25: add support to DWV above ceiling at east end of mezzanine, missing plumbing fixture rm. 115, label hydronic piping where change of direction occurs-above ceiling at warehouse, submit elevator certification report, flashing required around exhaust boots on rooftops, adjust restroom doors to 5 pounds of pressure.
12/16/2025 COT - HCBU - CofO N/A Not Ready 12-16-25: not ready. See building final notes & pending required inspections to,include, fire, engineering, right of way, and elevator report.
12/23/2025 COT - HCBU - Building Final N/A Re-inspection required 12-23-25: add support to DWV above ceiling at east end of mezzanine, missing plumbing fixture rm. 115, label hydronic piping where change of direction occurs-above ceiling at warehouse, submit elevator certification report, flashing required around exhaust boots on rooftops, adjust restroom doors to 5 pounds of pressure.

Completed Inspections

Permit Status: Complete
Permit Number: TC-COM-0525-00909
Permit Description: Office tenant improvement
Total Completed Inspections - 16
Date Description Inspector Results Comments
10/06/2025 COT - HCME - Mechanical Above Ceiling Passed 10-6-25: corrections made-okay to cont with construction at progress areas.
10/06/2025 COT - HCEL - Electrical Above Ceiling Passed 10-6-25: corrections made-okay to cont with construction at progress areas.
10/06/2025 COT - HCBU - Framing Passed 10-6-25: framing at mezzanine approved.
10-6-25: correction- framing & MEP’s at office areas approved.
12/18/2025 COT - FCON - Alarm - Final Passed
12/18/2025 COT - FCON - Fire - Final Passed
12/18/2025 COT - FCON - Sprinkler - Final Passed
12/23/2025 COT - HCBU - Building Progress Passed 12-23-25: approved.
12/23/2025 COT - HCEL - Electrical Final Passed 12-23-25: approved.
12/23/2025 COT - HCEL - Electrical Progress Passed 12-23-25: approved.
12/23/2025 COT - HCME - Mechanical Final Passed 12-23-25: approved.
01/05/2026 TRSP - ROW - Final/Close-Out Passed
12/29/2025 ENGR Engineering Final Passed Exterior is complete, all egress doors are uninhibited.
01/07/2026 COT - HCME - Mechanical Progress Passed 1-7-26: approved.
01/07/2026 COT - HCBU - Building Above Ceiling Passed 1-7-26: approved.
01/09/2026 COT - HCBU - CofO Passed 1-9-26: okay for a Level 4 TCO pending Fire approval.
Note: upload a copy of the elevator certificate as an attachment.
01/09/2026 COT - HCBU - Building Final Passed 1-9-26: building final approved.