Inspection Status: Re-inspection required
Inspection History: COT - HCBU - Building Final
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/07/2026 | COT - HCBU - Building Final | Re-inspection required | 1-7-26: label hydronic piping where change of direction occurs. | |
| 01/09/2026 | COT - HCBU - Building Final | Passed | 1-9-26: building final approved. | |
| 12/16/2025 | COT - HCBU - Building Final | Partial Pass | 12-16-25: adjust restroom doors to 5 pounds of pressure, lower restroom mirrors-40" to the reflective surface, install door leading to break room, install cover plate for low voltage at main entrance floor, install cover plate at west wall upstairs. Note: submit a 3rd party report for elevator. |
|
| 12/23/2025 | COT - HCBU - Building Final | Re-inspection required | 12-23-25: add support to DWV above ceiling at east end of mezzanine, missing plumbing fixture rm. 115, label hydronic piping where change of direction occurs-above ceiling at warehouse, submit elevator certification report, flashing required around exhaust boots on rooftops, adjust restroom doors to 5 pounds of pressure. |