Inspection Status: Partial Pass

Inspection History: COT - HCBU - Framing

Date Description Inspector Results Comments
08/20/2025 COT - HCBU - Framing Partial Pass Offices first floor. 146 &147. Second floor offices 219, 220, & 221. Cafe wall 214. Pending kickers at every 4' remove drywall screws. Provide structural screws per the plan. 8/20/2025
08/22/2025 COT - HCBU - Framing Partial Pass 8-22-25: Framing corrections made at listed rooms to include, 146, 147, 214, 219, 220, and 221-okay to continue at progress areas.
09/29/2025 COT - HCBU - Framing Partial Pass 9-29-25: framing at mezzanine verified per plan-kickers at 4' o.c. to be verified at plywood is installed. Okay to drywall progress areas.
10/06/2025 COT - HCBU - Framing Passed 10-6-25: framing at mezzanine approved.
10-6-25: correction- framing & MEP’s at office areas approved.