| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/20/2025 | COT - HCBU - Framing | Partial Pass | Offices first floor. 146 &147. Second floor offices 219, 220, & 221. Cafe wall 214. Pending kickers at every 4' remove drywall screws. Provide structural screws per the plan. 8/20/2025 | |
| 08/22/2025 | COT - HCBU - Framing | Partial Pass | 8-22-25: Framing corrections made at listed rooms to include, 146, 147, 214, 219, 220, and 221-okay to continue at progress areas. | |
| 09/29/2025 | COT - HCBU - Framing | Partial Pass | 9-29-25: framing at mezzanine verified per plan-kickers at 4' o.c. to be verified at plywood is installed. Okay to drywall progress areas. | |
| 10/06/2025 | COT - HCBU - Framing | Passed | 10-6-25: framing at mezzanine approved. 10-6-25: correction- framing & MEP’s at office areas approved. |