Permit: TC-COM-0523-01370
Permit Details
Apply Date:
05/23/2023
Applicant:
Brandy Burke
Description:
Manufacturing Fit-Up. Intent to apply for annual facilities permit once CofO is issued.
Permit Reviews
Permit Number - TC-COM-0523-01370
Permit Status: Complete
Permit Description: Manufacturing Fit-Up. Intent to apply for annual facilities permit once CofO is issued.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 11/15/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 11/17/2023 | APPROVED |
| 06/13/2023 | RESTAMP - COMMERCIAL v.1 | 06/20/2023 | APPROVED |
| 09/27/2023 | COMMERCIAL REVIEW - FULL v.1 | 10/27/2023 | REQUIRES RESUBMIT |
| 06/12/2023 | COMMERCIAL REVIEW - FULL v.2 | 06/13/2023 | APPROVED |
| 11/02/2023 | COMMERCIAL REVIEW - FULL v.2 | 11/09/2023 | APPROVED |
| 11/30/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 12/04/2023 | APPROVED |
| 05/25/2023 | COMMERCIAL REVIEW - FULL v.1 | 06/08/2023 | REQUIRES RESUBMIT |
| 11/09/2023 | RESTAMP - COMMERCIAL v.1 | 11/14/2023 | APPROVED |
Conditions
Permit Number - TC-COM-0523-01370
Permit Status: Complete
Permit Description: Manufacturing Fit-Up. Intent to apply for annual facilities permit once CofO is issued.
| Date | Description | Comments |
|---|---|---|
| 11/01/2023 | AIR BALANCING/COMMISSIONING REPORT IS REQUIRED. | |
| 11/09/2023 | SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED. | |
| 11/17/2023 | SPECIAL INSPECTION FOR FIELD WELDING IS REQUIRED. | |
| 11/09/2023 | SPECIAL INSPECTION FOR FOUNDATION/EXCAVATION IS REQUIRED. | |
| 11/17/2023 | SPECIAL INSPECTION FOR HIGH STRENGTH BOLTING IS REQUIRED. | |
| 11/17/2023 | SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED. | |
| 11/01/2023 | WATER STERILIZATION REPORT IS REQUIRED. |
Outstanding Inspections
Permit Status: Complete
Permit Number: TC-COM-0523-01370
Permite Description: Manufacturing Fit-Up. Intent to apply for annual facilities permit once CofO is issued.
Total Outstanding Inspections - 6
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/19/2023 | COT - HCBU - Framing | N/A | Partial Pass | Screen room. |
| 09/19/2023 | COT - HCEL - Electrical Intermediate | N/A | Partial Pass | Screen room. |
| 10/23/2023 | COT - BULD - SWG Clearance | N/A | Not Applicable | |
| 08/31/2023 | COT - HCPL - Rough Soil | N/A | Partial Pass | |
| 10/27/2023 | BULD - Electrical Clearance | N/A | Not Applicable | |
| COT - FCON - Alarm - Final | N/A | Not Ready | need alarm company to call in their permit. |
Completed Inspections
Permit Status: Complete
Permit Number: TC-COM-0523-01370
Permit Description: Manufacturing Fit-Up. Intent to apply for annual facilities permit once CofO is issued.
Total Completed Inspections - 17
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/11/2023 | COT - HCBU - Preslab | Passed | ||
| 09/14/2023 | COT - HCPL - Plumbing Intermediate | Passed | Wash out room. | |
| 09/25/2023 | COT - HCBU - Framing | Passed | Office area. 9/25/23: screen room and break room, all framing and rough electric approved. |
|
| 09/25/2023 | COT - HCEL - Electrical Intermediate | Passed | Office area. 9/25/23: screen room and break room, all framing and rough electric approved. |
|
| 10/10/2023 | COT - LCME - Mechanical Final | Passed | ||
| 10/10/2023 | COT - HCME - Mechanical Intermediate | Passed | ||
| 10/23/2023 | COT - LCEL - Electrical Final | Passed | 10/23/23: Level 1 TCO furniture/stock (no public) | |
| 10/23/2023 | COT - FCON - Sprinkler - Final | Passed | ||
| 10/27/2023 | COT - HCPL - Rough Soil | Passed | 8/23/23: new floor sink in Dark Room and new soil line for water fountain outside restrooms. Sewer tie in. 9/6/23: 3 new hand sinks in break room on south end of building. 10/26/23: Not ready for inspection of new soil lines. 10/27/23: new soil lines in Dark Room approved to cover |
|
| 10/31/2023 | COT - LCPL - Plumbing Final | Passed | ||
| 11/07/2023 | COT - FCON - Alarm - Final | Passed | ||
| 11/07/2023 | COT - FCON - Fire - Final | Passed | ||
| 11/14/2023 | COT - LCBU - Building Progress | Passed | ||
| 11/14/2023 | COT - LCEL - Electrical Progress | Passed | ||
| 11/14/2023 | COT - LCPL - Plumbing Progress | Passed | ||
| 12/01/2023 | COT - LCME - Mechanical Progress | Passed | ||
| 12/01/2023 | COT - LCBU - Building Final | Passed |