Inspection History Details
Inspection Status: Not Ready
Inspection History: COT - LCBU - Building Final
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/11/2023 | COT - LCBU - Building Final | Not Ready | consultation | |
| 10/30/2023 | COT - LCBU - Building Final | Re-inspection required | 10/30/23: complete all plumbing and the breaker room before TCO. | |
| 10/31/2023 | COT - LCBU - Building Final | Partial Pass | 10/31/23: OK to issue TCO level 2 | |
| 11/09/2023 | COT - LCBU - Building Final | Canceled | 10/30/23: complete all plumbing and the breaker room before TCO. 10/31/23: OK to issue TCO level 2 11/9/23: cancel building final inspection per Brandy. |
|
| 11/14/2023 | COT - LCBU - Building Final | Re-inspection required | 11/14/23: waiting on air balance report. | |
| 12/01/2023 | COT - LCBU - Building Final | Passed |