Inspection History Details
Inspection Status: Partial Pass
Inspection History: COT - HCPL - Rough Soil
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/23/2023 | COT - HCPL - Rough Soil | Partial Pass | 8/23/23: new floor sink in Dark Room and new soil line for water fountain outside restrooms. | |
| 08/31/2023 | COT - HCPL - Rough Soil | Partial Pass | ||
| COT - HCPL - Rough Soil | Partial Pass | 8/23/23: new floor sink in Dark Room and new soil line for water fountain outside restrooms. Sewer tie in. 9/6/23: 3 new hand sinks in break room on south end of building. |
||
| 09/07/2023 | COT - HCPL - Rough Soil | Canceled | ||
| 10/26/2023 | COT - HCPL - Rough Soil | Not Ready | 10/26/23: Not ready for inspection of new soil lines. | |
| 10/27/2023 | COT - HCPL - Rough Soil | Passed | 8/23/23: new floor sink in Dark Room and new soil line for water fountain outside restrooms. Sewer tie in. 9/6/23: 3 new hand sinks in break room on south end of building. 10/26/23: Not ready for inspection of new soil lines. 10/27/23: new soil lines in Dark Room approved to cover |