Permit: TC-COM-0425-00741
Permit Details
Status:
Complete
Type:
Commercial Building
Address:
2730 E DREXEL RD BLDG 2 UNIT 2110
Address NEW:
2730 E DREXEL RD BLDG 2 UNIT 2110
Apply Date:
04/14/2025
Applicant:
Amy Cotner
Description:
Speculative TI buildout in unoccupied Shell under separate permit.
Permit Reviews
Permit Number - TC-COM-0425-00741
Permit Status: Complete
Permit Description: Speculative TI buildout in unoccupied Shell under separate permit.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 03/24/2026 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 04/06/2026 | APPROVED |
| 05/04/2026 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 05/05/2026 | APPROVED |
| 04/16/2025 | COMMERCIAL REVIEW - FULL v.1 | 05/08/2025 | REQUIRES RESUBMIT |
| 06/06/2025 | COMMERCIAL REVIEW - FULL v.2 | 06/10/2025 | APPROVED |
| 06/10/2025 | RESTAMP - COMMERCIAL v.1 | 06/23/2025 | APPROVED |
Conditions
Permit Number - TC-COM-0425-00741
Permit Status: Complete
Permit Description: Speculative TI buildout in unoccupied Shell under separate permit.
| Date | Description | Comments |
|---|---|---|
| 04/16/2025 | BLDG 2 UNIT 2110 Needs to be added to cover sheet as part of the address to reflect this permit application. | |
| 04/16/2025 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact. | |
| 07/02/2025 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. For review and assessment: apply online at https://permits.pima.gov/ or contact us at sewer@pima.gov, (520) 724-9900. |
Outstanding Inspections
Permit Status: Complete
Permit Number: TC-COM-0425-00741
Permite Description: Speculative TI buildout in unoccupied Shell under separate permit.
Total Outstanding Inspections - 7
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/19/2025 | COT - HCPL - Plumbing Intermediate | N/A | Partial Pass | In wall DWV and domestic lines have been approved per Fernando D. Refer notes under plumbing progress. 11/19/2025 |
| 01/29/2026 | COT - HCEL - Electrical Intermediate | N/A | Partial Pass | 1-29-26: in wall electrical verified per plans. Okay to continue with construction at progress areas. |
| 11/18/2025 | COT - HCPL - Plumbing Progress | N/A | Partial Pass | 11-18-25: in wall domestic & DWV verified per plans. Okay to continue with construction at progress areas. |
| 12/04/2025 | COT - HCME - Mechanical Progress | N/A | Partial Pass | 12-4-25: verified pookie joint on duct. Okay to continue with TI. |
| 04/09/2026 | COT - BULD - SWG Clearance | N/A | Not Applicable | 4-9-26: not applicable. |
| 11/17/2025 | COT - HCEL - Electrical Progress | N/A | Partial Pass | 11-17-25: partial pass-in wall rough electrical for Suite 2110. |
| 10/24/2025 | COT - HCBU - Building Above Ceiling | N/A | Not Ready |
Completed Inspections
Permit Status: Complete
Permit Number: TC-COM-0425-00741
Permit Description: Speculative TI buildout in unoccupied Shell under separate permit.
Total Completed Inspections - 23
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/29/2026 | COT - HCBU - Framing | Passed | 1-29-26: interior office framing approved. | |
| 02/09/2026 | COT - HCBU - Building Progress | Passed | Ok to tape walls throughout. | |
| 03/04/2026 | COT - HCME - Mechanical Intermediate | Passed | 3-4-26: MEP's approved. | |
| 03/04/2026 | COT - HCME - Mechanical Above Ceiling | Passed | 3-4-26: MEP's approved. | |
| 03/04/2026 | COT - HCPL - Plumbing Intermediate | Passed | 3-4-26: MEP's approved. | |
| 03/04/2026 | COT - HCPL - Plumbing Above Ceiling | Passed | 3-4-26: MEP's /above ceiling approved. | |
| 03/04/2026 | COT - HCEL - Electrical Intermediate | Passed | 3-4-26: MEP's approved. | |
| 03/23/2026 | BULD - Electrical Clearance | Passed | 3-23-26: okay to energize suite 2110-panel#6. ECO clearance issued to TEP. | |
| 03/26/2026 | COT - HCEL - Electrical Above Ceiling | Passed | 3-26-26: electrical above ceiling approved. | |
| 03/26/2026 | COT - HCPL - Plumbing Progress | Passed | 3-26-26: plumbing progress approved. | |
| 03/26/2026 | COT - HCME - Mechanical Progress | Passed | 3-26-26: approved. | |
| 04/20/2026 | ENGR Engineering Final | Passed | Site is complete in accordance with approved plans. | |
| 04/20/2026 | COT - FCON - Alarm - Final | Passed | ||
| 04/20/2026 | TRSP - ROW - Final/Close-Out | Passed | ||
| 04/20/2026 | COT - FCON - Fire - Final | Passed | ||
| 04/20/2026 | COT - HCME - Mechanical Final | Passed | 4-20-26: approved. | |
| 04/20/2026 | COT - HCEL - Electrical Progress | Passed | 4-20-26: approved. | |
| 04/23/2026 | COT - HCBU - Building Above Ceiling | Passed | 4-23-26: building above ceiling approved. | |
| 04/23/2026 | COT - FCON - Sprinkler - Final | Passed | ||
| 04/23/2026 | COT - HCPL - Plumbing Final | Passed | 4-23-26: plumbing final approved. | |
| 05/05/2026 | COT - HCBU - CofO | Passed | 5-5-26: building final approved & all conditions met. Okay to apply for C of O. | |
| 05/05/2026 | COT - HCBU - Building Final | Passed | 5-5-26: building final approved. | |
| 05/05/2026 | COT - HCEL - Electrical Final | Passed | 5-5-26: electrical final approved. |