Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Inspection Status: Re-inspection required

Inspection History: COT - HCEL - Electrical Final 

Date Description Inspector Results Comments
04/20/2026 COT - HCEL - Electrical Final  Re-inspection required 4-20-26: add R3 insulation to hot water side of water heater, install ADA restroom signs-must contain braille, adjust both doors at restrooms to 5 pounds of pressure, missing subpanel schedule, install knockout on RTU3 disconnect,
Note: roof drain covers were approved on the shell finals but are now missing due to theft. We will verify them at the TCO Final.
04/23/2026 COT - HCEL - Electrical Final  Partial Pass 4-23-26: pending panel schedule.
04/29/2026 COT - HCEL - Electrical Final  Not Ready 4-29-26: not ready.
05/05/2026 COT - HCEL - Electrical Final  Passed 5-5-26: electrical final approved.