Permit Details

Status:
Complete
Type:
Commercial Building
Apply Date:
04/14/2023
Applicant:
MG2 Representative
Description:
A new, single-story, 107,434 SF commercial building with fully automatic sprinkler and fire alarm system and a 28,118 SF exterior Garden Center.

Permit Reviews

Permit Number - TC-COM-0423-01064
Permit Status: Complete
Permit Description: A new, single-story, 107,434 SF commercial building with fully automatic sprinkler and fire alarm system and a 28,118 SF exterior Garden Center.
Start Date Submittal Complete Date Status  
04/19/2023 COMMERCIAL REVIEW - FULL v.1 04/19/2023 REQUIRES RESUBMIT Review Details
05/09/2024 COMMERCIAL REVIEW - FULL v.2 05/10/2024 APPROVED Review Details
08/01/2024 BUILDING DEFERRED SUBMITTAL REVIEW v.1 08/05/2024 APPROVED Review Details
10/10/2024 BUILDING DEFERRED SUBMITTAL REVIEW v.2 10/11/2024 APPROVED Review Details
08/26/2024 BUILDING DEFERRED SUBMITTAL REVIEW v.1 08/26/2024 REQUIRES RESUBMIT Review Details
05/19/2023 COMMERCIAL REVIEW - FULL v.2 06/09/2023 REQUIRES RESUBMIT Review Details
09/26/2023 COMMERCIAL REVIEW - FULL v.4 10/12/2023 REQUIRES RESUBMIT Review Details
06/25/2024 RESTAMP - COMMERCIAL v.1 06/27/2024 APPROVED Review Details
04/11/2024 COMMERCIAL REVIEW - FULL v.1 05/07/2024 REQUIRES RESUBMIT Review Details
07/05/2023 COMMERCIAL REVIEW - FULL v.3 08/18/2023 REQUIRES RESUBMIT Review Details
10/23/2023 COMMERCIAL REVIEW - FULL v.5 11/28/2023 APPROVED Review Details
11/28/2023 RESTAMP - COMMERCIAL v.1 11/28/2023 APPROVED Review Details

Conditions

Permit Number - TC-COM-0423-01064
Permit Status: Complete
Permit Description: A new, single-story, 107,434 SF commercial building with fully automatic sprinkler and fire alarm system and a 28,118 SF exterior Garden Center.
Date Description Comments
06/05/2024 SPECIAL INSPECTION FOR BOLTS INSTALLED IN CONCRETE IS REQUIRED.
06/05/2024 SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED.
06/05/2024 Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact.
06/05/2024 SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED.
06/05/2024 SPECIAL INSPECTION FOR EXPANSION ANCHORS IS REQUIRED.
06/05/2024 SPECIAL INSPECTION FOR FIELD WELDING IS REQUIRED.
06/05/2024 SPECIAL INSPECTION FOR FOUNDATION/EXCAVATION IS REQUIRED.
06/05/2024 SPECIAL INSPECTION FOR HIGH STRENGTH BOLTING IS REQUIRED.
06/05/2024 Masonry Inspection Report submittal review is required.
06/05/2024 SPECIAL INSPECTION FOR REINFORCING STEEL AND/OR PRE-STRESSING TENDONS IS REQUIRED.
06/05/2024 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment.
06/05/2024 Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy.
08/26/2024 SPECIAL INSPECTION FOR SPECIAL MOMENT RESISTING STEEL FRAMES IS REQUIRED.

Outstanding Inspections

Permit Status: Complete
Permit Number: TC-COM-0423-01064
Permite Description: A new, single-story, 107,434 SF commercial building with fully automatic sprinkler and fire alarm system and a 28,118 SF exterior Garden Center.
Total Outstanding Inspections - 13
Last Inspection Date Description Inspector Results Comments
04/15/2024 COT - HCPL - Plumbing Above Ceiling N/A Canceled
05/22/2024 COT - HCBU - Masonry Pregrout N/A Partial Pass 5/22/24: lumber yard entry columns okay to grout and cap. Main entry 21' to 30' okay to grout
07/11/2024 COT - HCBU - Firewall/Fire Barrier/Firestop N/A Not Applicable
07/12/2024 COT - HCBU - CofO N/A Partial Pass Men's, women's, and family restrooms are fully functional. Electrical outlets, light fixtures, and mechanical equipment is fully operational. Outdoor lighting is fully operational. Fire will be doing their inspection late morning. Okay to issue a Level 2 TCO allowing stocking of store shelves and staff training once Fire has completed their inspection and approved a TCO.
05/24/2024 COT - HCPL - Plumbing Intermediate N/A Partial Pass 5/24/24: family restroom, employee break room, TRC. Okay to cover.
01/31/2024 COT - HCPL - Yard Water Line N/A Partial Pass 1/31/24: partial pass for fire riser okay to backfill inside of building and outside still need connection
06/26/2024 COT - HCME - Mechanical Above Ceiling N/A Canceled 6/26/24: canceled per contractor
12/11/2023 COT - HCEL - Electrical Underground N/A Partial Pass 12/4/23: Electric underground in Section 1. From the SES to approximately 80 l/f north. (Section 1)
2@3 1/2", 1@4", 2@2 1/2", 2@2", 2@1 1/2"

12/11/23: 2@ 3 1/2", 1@4", 2@2 1/2", 2@2", 2@1 1/2" (section 2 & 3)
05/22/2024 COT - HCEL - Electrical Intermediate N/A Partial Pass 5/22/24: partial pass for pad mount transformer and electrical room panels.
05/30/2024 COT - HCBU - Preslab N/A Partial Pass 5/30/24: lumber canopy okay to place concrete for ground
06/15/2024 COT - HCBU - Excavation/Rebar/Zoning N/A Partial Pass 6/15/24: trc canopy slab okay to pour

Contact: Ethan (832)992-9893
COT - FCON - Sprinkler - Final N/A Not Ready
COT - FCON - Alarm - Final N/A Not Ready

Completed Inspections

Permit Status: Complete
Permit Number: TC-COM-0423-01064
Permit Description: A new, single-story, 107,434 SF commercial building with fully automatic sprinkler and fire alarm system and a 28,118 SF exterior Garden Center.
Total Completed Inspections - 38
Date Description Inspector Results Comments
03/20/2024 COT - HCEL - Electrical Progress Passed
04/17/2024 COT - HCPL - Plumbing Above Ceiling Passed
04/17/2024 COT - HCPL - Plumbing Progress Passed 4/17/24:over head plumbing to plan and under test.
04/26/2024 COT - HCPL - Rough Soil Passed 4/26/24: Underground plumbing for roof drains on lumber canopy is complete. Underground plumbing is totally complete for this project.
05/23/2024 COT - HCBU - Masonry Pregrout Passed 5/23/24: okay to grout and cap main entry.
06/10/2024 BULD - Electrical Clearance Passed TEP ECO 10100 E VAIL RD
07/02/2024 COT - HCPL - Gas Pressure Test Passed
07/03/2024 COT - HCEL - Electrical Above Ceiling Passed 7/3/24: Restroom hallway, ASDS #136, Training Room #121, and Learning Center #122 have wires properly attached to light fixtures and grid ceiling. Okay to proceed with ceiling tile installation.
07/03/2024 COT - HCBU - Building Above Ceiling Passed 7/3/24: Restroom hallway, ASDS #136, Training Room #121, and Learning Center #122 have wires properly attached to light fixtures and grid ceiling. Okay to proceed with ceiling tile installation.
07/08/2024 COT - HCBU - Building Progress Passed 7/8/24: Building shell is complete. Mechanical, electrical, and plumbing trim-out is ongoing. Workers are installing and setting up store shelving. Store signage is being installed along with store security. Superintendent will be calling for mechanical and plumbing final inspections later this week.
08/02/2024 COT - HCPL - Plumbing Final Passed 8/2/24: Men's, Women's, and Family Restrooms are complete. Plumbing fixtures operate properly on photo sensor flush and sink water on/off. All toilets and urinals are properly installed and caulked to the wall.
08/15/2024 COT - HCME - Mechanical Final Passed
08/15/2024 COT - HCEL - Electrical Final Passed
08/20/2024 COT - HCPL - Plumbing Intermediate Passed
08/20/2024 COT - HCPL - Yard Water Line Passed
08/20/2024 COT - HCPL - Backwater Valve Passed
08/20/2024 COT - HCME - Mechanical Progress Passed
08/20/2024 COT - HCME - Mechanical Intermediate Passed
08/20/2024 COT - HCME - Mechanical Above Ceiling Passed
08/20/2024 COT - HCEL - Outdoor Lighting Passed
08/20/2024 COT - HCEL - Grounding/Bonding Passed
08/20/2024 COT - HCEL - Electrical Underground Passed
08/20/2024 COT - HCEL - Electrical Intermediate Passed
08/20/2024 COT - HCBU - Roof Nailing Passed
08/20/2024 COT - HCBU - Preslab Passed
08/20/2024 COT - HCBU - Interior Shear Bracing Passed
08/20/2024 COT - HCBU - Exterior Clips/Sheathing Passed
08/20/2024 COT - HCBU - Excavation/Rebar/Zoning Passed
08/20/2024 PDSD Heavy Commercial Building Division Pre-Construction Meeting Passed
08/20/2024 COT - BULD - SWG Clearance Passed SWG FOR METER ONLY
08/20/2024 COT - HCPL - Gas Final Passed
08/20/2024 COT - HCBU - Framing Passed
08/22/2024 COT - FCON - Sprinkler - Final Passed
08/23/2024 COT - HCBU - Building Final Passed Construction is totally completed. Owner has all shelving fully stocked. Okay to issue a Level 4 TCO.
10/09/2024 ENGR Engineering Final Passed
10/10/2024 COT - FCON - Alarm - Final Passed
10/10/2024 COT - FCON - Fire - Final Passed
10/16/2024 TRSP - ROW - Final/Close-Out Passed all RoW work complete, site closed

Documents

File Name Document Type  
COFO_FINALCOFO_COMMERCIAL.PDF DOCUMENTS VIEW
TC-COM-0423-01064.63231129.REPORTS - UPDATED-2024-10-09_V1.PDF DOCUMENTS VIEW
COFO_TEMPORARYCOFO.PDF DOCUMENTS VIEW
L240420 4-2-24 VASQUEZ-2024-07-31_V1.PDF DOCUMENTS VIEW
COFO_TEMPORARYCOFO.PDF DOCUMENTS VIEW
01_ADDRESS REV_THD RITA RANCH_BUILDING PERMIT_V1.PDF DOCUMENTS VIEW
01_ADDRESS REV_THD RITA RANCH_ENERGY_V1.PDF DOCUMENTS VIEW
01_ADDRESS REV_THD RITA RANCH_GEOREPORT_V1.PDF DOCUMENTS VIEW
01_ADDRESS REV_THD RITA RANCH_MBS CALCS_V1.PDF DOCUMENTS VIEW
01_ADDRESS REV_THD RITA RANCH_MBS LOC_V1.PDF DOCUMENTS VIEW
01_ADDRESS REV_THD RITA RANCH_SPECS_V1.PDF DOCUMENTS VIEW
01_ADDRESS REV_THD RITA RANCH_STRUCT CALCS_V1.PDF DOCUMENTS VIEW
02_ADDRESS REV_THD RITA RANCH, AZ_HMIS PERMIT_V1.PDF DOCUMENTS VIEW
03_ADDRESS REV_THD RITA RANCH, AZ_RACKING CALCS_V1.PDF DOCUMENTS VIEW
03_ADDRESS REV_THD RITA RANCH, AZ_RACKING PERMIT_V1.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
SEWER RECEIPT_V1.PDF DOCUMENTS VIEW
CONS-CONS-THD RITA RANCH, AZ - PERMIT RESUBMISSION 03 - COMBINED_V2.PDF DOCUMENTS VIEW
1. THD RITA RANCH - PERMIT RESPONSE LETTERS - NARRATIVE OF CHANGES_V1.PDF DOCUMENTS VIEW
4. THD RITA RANCH HMIS 2023-06-30_V1.PDF DOCUMENTS VIEW
CONS-THD RITA RANCH, AZ - PERMIT RESUBMISSION 01 - COMBINED_V3.PDF DOCUMENTS VIEW