Permit: TC-COM-0423-01064
Permit Details
Apply Date:
04/14/2023
Applicant:
MG2 Representative
Description:
A new, single-story, 107,434 SF commercial building with fully automatic sprinkler and fire alarm system and a 28,118 SF exterior Garden Center.
Permit Reviews
Permit Number - TC-COM-0423-01064
Permit Status: Complete
Permit Description: A new, single-story, 107,434 SF commercial building with fully automatic sprinkler and fire alarm system and a 28,118 SF exterior Garden Center.
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
04/19/2023 | COMMERCIAL REVIEW - FULL v.1 | 04/19/2023 | REQUIRES RESUBMIT |
05/09/2024 | COMMERCIAL REVIEW - FULL v.2 | 05/10/2024 | APPROVED |
08/01/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 08/05/2024 | APPROVED |
10/10/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.2 | 10/11/2024 | APPROVED |
08/26/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 08/26/2024 | REQUIRES RESUBMIT |
05/19/2023 | COMMERCIAL REVIEW - FULL v.2 | 06/09/2023 | REQUIRES RESUBMIT |
09/26/2023 | COMMERCIAL REVIEW - FULL v.4 | 10/12/2023 | REQUIRES RESUBMIT |
06/25/2024 | RESTAMP - COMMERCIAL v.1 | 06/27/2024 | APPROVED |
04/11/2024 | COMMERCIAL REVIEW - FULL v.1 | 05/07/2024 | REQUIRES RESUBMIT |
07/05/2023 | COMMERCIAL REVIEW - FULL v.3 | 08/18/2023 | REQUIRES RESUBMIT |
10/23/2023 | COMMERCIAL REVIEW - FULL v.5 | 11/28/2023 | APPROVED |
11/28/2023 | RESTAMP - COMMERCIAL v.1 | 11/28/2023 | APPROVED |
Conditions
Permit Number - TC-COM-0423-01064
Permit Status: Complete
Permit Description: A new, single-story, 107,434 SF commercial building with fully automatic sprinkler and fire alarm system and a 28,118 SF exterior Garden Center.
Date | Description | Comments |
---|---|---|
06/05/2024 | SPECIAL INSPECTION FOR BOLTS INSTALLED IN CONCRETE IS REQUIRED. | |
06/05/2024 | SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED. | |
06/05/2024 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact. | |
06/05/2024 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. | |
06/05/2024 | SPECIAL INSPECTION FOR EXPANSION ANCHORS IS REQUIRED. | |
06/05/2024 | SPECIAL INSPECTION FOR FIELD WELDING IS REQUIRED. | |
06/05/2024 | SPECIAL INSPECTION FOR FOUNDATION/EXCAVATION IS REQUIRED. | |
06/05/2024 | SPECIAL INSPECTION FOR HIGH STRENGTH BOLTING IS REQUIRED. | |
06/05/2024 | Masonry Inspection Report submittal review is required. | |
06/05/2024 | SPECIAL INSPECTION FOR REINFORCING STEEL AND/OR PRE-STRESSING TENDONS IS REQUIRED. | |
06/05/2024 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. | |
06/05/2024 | Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy. | |
08/26/2024 | SPECIAL INSPECTION FOR SPECIAL MOMENT RESISTING STEEL FRAMES IS REQUIRED. |
Outstanding Inspections
Permit Status: Complete
Permit Number: TC-COM-0423-01064
Permite Description: A new, single-story, 107,434 SF commercial building with fully automatic sprinkler and fire alarm system and a 28,118 SF exterior Garden Center.
Total Outstanding Inspections - 13
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
04/15/2024 | COT - HCPL - Plumbing Above Ceiling | N/A | Canceled | |
05/22/2024 | COT - HCBU - Masonry Pregrout | N/A | Partial Pass | 5/22/24: lumber yard entry columns okay to grout and cap. Main entry 21' to 30' okay to grout |
07/11/2024 | COT - HCBU - Firewall/Fire Barrier/Firestop | N/A | Not Applicable | |
07/12/2024 | COT - HCBU - CofO | N/A | Partial Pass | Men's, women's, and family restrooms are fully functional. Electrical outlets, light fixtures, and mechanical equipment is fully operational. Outdoor lighting is fully operational. Fire will be doing their inspection late morning. Okay to issue a Level 2 TCO allowing stocking of store shelves and staff training once Fire has completed their inspection and approved a TCO. |
05/24/2024 | COT - HCPL - Plumbing Intermediate | N/A | Partial Pass | 5/24/24: family restroom, employee break room, TRC. Okay to cover. |
01/31/2024 | COT - HCPL - Yard Water Line | N/A | Partial Pass | 1/31/24: partial pass for fire riser okay to backfill inside of building and outside still need connection |
06/26/2024 | COT - HCME - Mechanical Above Ceiling | N/A | Canceled | 6/26/24: canceled per contractor |
12/11/2023 | COT - HCEL - Electrical Underground | N/A | Partial Pass | 12/4/23: Electric underground in Section 1. From the SES to approximately 80 l/f north. (Section 1) 2@3 1/2", 1@4", 2@2 1/2", 2@2", 2@1 1/2" 12/11/23: 2@ 3 1/2", 1@4", 2@2 1/2", 2@2", 2@1 1/2" (section 2 & 3) |
05/22/2024 | COT - HCEL - Electrical Intermediate | N/A | Partial Pass | 5/22/24: partial pass for pad mount transformer and electrical room panels. |
05/30/2024 | COT - HCBU - Preslab | N/A | Partial Pass | 5/30/24: lumber canopy okay to place concrete for ground |
06/15/2024 | COT - HCBU - Excavation/Rebar/Zoning | N/A | Partial Pass | 6/15/24: trc canopy slab okay to pour Contact: Ethan (832)992-9893 |
COT - FCON - Sprinkler - Final | N/A | Not Ready | ||
COT - FCON - Alarm - Final | N/A | Not Ready |
Completed Inspections
Permit Status: Complete
Permit Number: TC-COM-0423-01064
Permit Description: A new, single-story, 107,434 SF commercial building with fully automatic sprinkler and fire alarm system and a 28,118 SF exterior Garden Center.
Total Completed Inspections - 38
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
03/20/2024 | COT - HCEL - Electrical Progress | Passed | ||
04/17/2024 | COT - HCPL - Plumbing Above Ceiling | Passed | ||
04/17/2024 | COT - HCPL - Plumbing Progress | Passed | 4/17/24:over head plumbing to plan and under test. | |
04/26/2024 | COT - HCPL - Rough Soil | Passed | 4/26/24: Underground plumbing for roof drains on lumber canopy is complete. Underground plumbing is totally complete for this project. | |
05/23/2024 | COT - HCBU - Masonry Pregrout | Passed | 5/23/24: okay to grout and cap main entry. | |
06/10/2024 | BULD - Electrical Clearance | Passed | TEP ECO 10100 E VAIL RD | |
07/02/2024 | COT - HCPL - Gas Pressure Test | Passed | ||
07/03/2024 | COT - HCEL - Electrical Above Ceiling | Passed | 7/3/24: Restroom hallway, ASDS #136, Training Room #121, and Learning Center #122 have wires properly attached to light fixtures and grid ceiling. Okay to proceed with ceiling tile installation. | |
07/03/2024 | COT - HCBU - Building Above Ceiling | Passed | 7/3/24: Restroom hallway, ASDS #136, Training Room #121, and Learning Center #122 have wires properly attached to light fixtures and grid ceiling. Okay to proceed with ceiling tile installation. | |
07/08/2024 | COT - HCBU - Building Progress | Passed | 7/8/24: Building shell is complete. Mechanical, electrical, and plumbing trim-out is ongoing. Workers are installing and setting up store shelving. Store signage is being installed along with store security. Superintendent will be calling for mechanical and plumbing final inspections later this week. | |
08/02/2024 | COT - HCPL - Plumbing Final | Passed | 8/2/24: Men's, Women's, and Family Restrooms are complete. Plumbing fixtures operate properly on photo sensor flush and sink water on/off. All toilets and urinals are properly installed and caulked to the wall. | |
08/15/2024 | COT - HCME - Mechanical Final | Passed | ||
08/15/2024 | COT - HCEL - Electrical Final | Passed | ||
08/20/2024 | COT - HCPL - Plumbing Intermediate | Passed | ||
08/20/2024 | COT - HCPL - Yard Water Line | Passed | ||
08/20/2024 | COT - HCPL - Backwater Valve | Passed | ||
08/20/2024 | COT - HCME - Mechanical Progress | Passed | ||
08/20/2024 | COT - HCME - Mechanical Intermediate | Passed | ||
08/20/2024 | COT - HCME - Mechanical Above Ceiling | Passed | ||
08/20/2024 | COT - HCEL - Outdoor Lighting | Passed | ||
08/20/2024 | COT - HCEL - Grounding/Bonding | Passed | ||
08/20/2024 | COT - HCEL - Electrical Underground | Passed | ||
08/20/2024 | COT - HCEL - Electrical Intermediate | Passed | ||
08/20/2024 | COT - HCBU - Roof Nailing | Passed | ||
08/20/2024 | COT - HCBU - Preslab | Passed | ||
08/20/2024 | COT - HCBU - Interior Shear Bracing | Passed | ||
08/20/2024 | COT - HCBU - Exterior Clips/Sheathing | Passed | ||
08/20/2024 | COT - HCBU - Excavation/Rebar/Zoning | Passed | ||
08/20/2024 | PDSD Heavy Commercial Building Division Pre-Construction Meeting | Passed | ||
08/20/2024 | COT - BULD - SWG Clearance | Passed | SWG FOR METER ONLY | |
08/20/2024 | COT - HCPL - Gas Final | Passed | ||
08/20/2024 | COT - HCBU - Framing | Passed | ||
08/22/2024 | COT - FCON - Sprinkler - Final | Passed | ||
08/23/2024 | COT - HCBU - Building Final | Passed | Construction is totally completed. Owner has all shelving fully stocked. Okay to issue a Level 4 TCO. | |
10/09/2024 | ENGR Engineering Final | Passed | ||
10/10/2024 | COT - FCON - Alarm - Final | Passed | ||
10/10/2024 | COT - FCON - Fire - Final | Passed | ||
10/16/2024 | TRSP - ROW - Final/Close-Out | Passed | all RoW work complete, site closed |